128 Oorsigsartikels • Review articles Building an infrastructure project performance in the North-West Province Department of Public Works and Roads Peer reviewed and revised Abstract Building and infrastructure projects at the North- West Province Department of Public Works and Roads (NW DPWR) often perform poorly in terms of overrunning both the original approved timeline and the budget. Adding to poor time and cost performances, these projects often do not meet the desired functional requirements. This article reports on findings of a study which investigated the causes of these poor performances in the NW DPWR. Fifty potential causes of poor performance were identified from literature. These factors were grouped under three main related categories of owner-related, contractor- related and consultant-related and were subjected to a questionnaire survey to identify the most critical causes of failure. The results were analysed using the Relative Importance Index (RII) and Spearman’s Rank Correlation Coefficients. The results indicated that the most significant causes of poor building and infrastructure project performance in the NW DPWR include underestimation of project cost, the lack of experience in executing projects, contractor’s cash-flow constraints, corruption and bribery during the bidding and contract award phase, as well as poor site management and supervision. Recommendations are made to prevent similar causes of projects failure in the NW DPWR in future. Keywords: Building, construction projects, cost overruns, infrastructure, project performance, Relative Importance Index, schedule delays Davison Murwira Mr Davison Murwira, M.Eng. student, Graduate School of Technology Management, University of Pretoria, Lynnwood Road, Pretoria, 0002, South Africa. Phone: +27 (0)12-420-2822. Michiel Bekker Dr Michiel (C.) Bekker, Senior Lecturer, Graduate School of Technology Management, University of Pretoria, Lynnwood Road, Pretoria, 0002, South Africa. Phone: +27 (0)12-420-2822, email: DOI: http://dx.doi. org/10.18820/24150487/ as24i2.5 ISSN: 1023-0564 e-ISSN: 2415-0487 Acta Structilia 2017 24(2): 128-145 © UV/UFS mailto:Michiel.bekker@up.ac.za http://dx.doi.org/10.18820/24150487/as24i2.5 http://dx.doi.org/10.18820/24150487/as24i2.5 http://dx.doi.org/10.18820/24150487/as24i2.5 Murwira & Bekker • Building an infrastructure project 129 Abstrak Bou- en infrastruktuurprojekte by die Noordwes Provinsie se Departement van Openbare Werke en Paaie (NW DPWR) ondervind gereeld tydvertragings in projekvoltooiing sowel as probleme soos oorspandering en die gebrek aan voldoening aan funksionele spesifikasies. Hierdie artikel rapporteer resultate van ’n studie wat onderneem is ten einde die redes waarom projekte in die NW DPWR swak presteer, te ondersoek. Vanuit literatuur is vyftig potensiële redes vir projekfaling geïdentifiseer. Die redes is in drie verwante kategorieë gegroepeer, naamlik eienaarverwante, kontrakteurverwante en konsultantverwante kategorieë. Deur middel van ’n vraelysopname is die mees kritieke redes vir projekfaling geïdentifiseer. Die resulate is ontleed deur gebruik te maak van ’n Relatiewe Sterkte Indeks asook die Spearman Rangorde Korrelasie Koëffisiënte. Die resultate toon dat die mees beduidende redes vir projekfaling in NW DPWR sluit onderberaming van projekkoste, gebrekkige ervaring in projekimplementering, beperkte kontantvloei deur kontrakteurs, korrupsie en omkopery tydens die tenderproses en kontrakaanstellings, sowel as swak terreinbestuur en toesig in. Aanbevelings is gemaak om soortgelyke probleme met toekomstige projekte in die NW DPWR te beperk. Sleutelwoorde: Gebou, konstruksieprojekte, koste-oorskryding, infrastruktuur, projekprestasie, Relative Importance Index, skedulevertragings 1. Introduction The North-West Provincial Government (NWPG) has a constitutional responsibility to provide better services to the people of the North- West Province. The NWPG, through the Department of Public Works and Roads (DPWR), is mandated to provide office, residential and other service delivery facilities to provincial departments and political office-bearers. The initial policy of the NW DPWR, in full support of the objectives and targets of the government’s Reconstruction and Development Programme (RDP), is to ensure that all South Africans have access to basic infrastructure (RDP, 1994: online). The Chief Directorate Infrastructure in the Department is responsible for infrastructure planning, design and project implementation of infrastructure assets to meet the needs identified by the client departments under the capital expansion (Capex) programme. The implementation of projects by the NW DPWR is based on the North-West Infrastructure Delivery Management System (NW IDMS), which provides a systematic approach to infrastructure delivery, covering the full life cycle from needs identification, planning and budgeting to procurement, construction, handover, operations and maintenance. The NW DPWR often perform poorly in the delivery of all construction and maintenance projects on time, within budget and in accordance to the pre-determined requirements. A study undertaken by the South African Government in 2002 to determine the issues and gaps in the delivery of infrastructure reported that there was a shortfall in Acta Structilia 2017: 24(2) 130 effective and systematic delivery systems, as well as a shortage in skills to deliver projects as per requirements (SAICE, 2016: 2). The most critical problems facing Government’s infrastructure service delivery programme are the following: • Delayed infrastructure investment, also known as the ‘blocked infrastructure project pipeline’, often due to inadequate planning allocation of resources, as well as excessive bureaucracy; • Infrastructure delivery backlogs, particularly in respect of buildings infrastructure; • Budgetary challenges in addressing backlogs in infrastructure delivery; • Inheritance of unequal spatial distribution of infrastructure resulting in rural areas with limited access to basic, social and economic services; • Underspending of capital expenditure; • Poor application of project management practices, and • Poor time management. The South African Government has identified infrastructure development as a means to stimulate the economy (NPC, 2011: 137). The Government is the most significant construction client, contributing between 40% and 50% of the entire domestic construction expenditure (Dlungwana, Nxumalo, Van Huysteen, Rwelamila & Noyana, 2002: 2). According to Ramokolo and Smallwood (2008: 46), South Africa aims to invest 5.1% of South Africa’s Gross Domestic Product (GDP) in construction. They also indicated that 45% of the more than 500,000 people, employed in the construction industry, are estimated to be working in the formal sector. In order to address infrastructure backlogs across the country, the Government is committed to invest in infrastructure development in order to achieve economic growth and address the backlog. Approximately 60% of the projects being implemented by the NW DPWR are not completed on time and on budget, often resulting in service delivery protests by local communities. In a bid to get to uncover some of the problems experienced in the delivery of building infrastructure projects by the NW DPWR, a preliminary internal evaluation and analysis of project performances and operational deficiencies in the NW DPWR was done. It was evident that there were various challenges facing the NW DPWR in delivering building and infrastructure projects, including termination of contractors for poor performance, cost and schedule overruns on projects such as Murwira & Bekker • Building an infrastructure project 131 Vryburg Mini Garona Office Park, Vryburg Hospital, and DPWR Head Office in Mmabatho. These problems were further exacerbated by poor procurement practices and poor controls in the delivery process. Despite overall poor performance, some projects were delivered successfully, namely Tlakgameng Community Library, new hostels at Bophelong Special School, and Tlou le Tlou Traditional Offices. The discrepancies in overall project performance prompted the researcher to investigate and identify the causes of infrastructure project failures in the NW DPWR. This study aims to address the following three questions related to projects at NW DPWR: • What are the general factors causing the time and cost overrun of building and infrastructure projects? • What are the critical factors causing the time and cost overrun of building and infrastructure projects? • What are the perceptions of owners, contractors and consultants regarding the causes of time and cost overrun of building and infrastructure projects? 2. Literature survey Construction projects worldwide often suffer from poor performance in terms of time delays, cost overruns and quality defects. Pheng and Chuan (cited in Adebowale & Ayodeji, 2015: 1118) stated that, traditionally, successful delivery of a construction project hinges on the performance of the project manager, who must consider delivery time, budgeted cost and expected quality. However, with the delivery of projects predominantly a team effort, the allocation of single accountability for project performance to one individual might not achieve the desired results. In the past, various studies investigated and analysed factors causing poor performance on construction-related projects (Table 1). The majority of these studies focused on identifying the major causes of time and schedule overruns, challenges facing contractors, as well as quality management in various construction projects. Table 1 provides a summary of some of the common causes for poor performance of construction-related projects as per categories identified. Acta Structilia 2017: 24(2) 132 Table 1: Summary of typical factors causing the poor performance of construction-related projects Critical performance factors Authors Owner-related factors Delayed monthly payments for completed work Assaf & Al-Hejji (2006: 349); Frimpong, Oluwoye & Crawford (2003: 321); Fugar & Agyakwah-Baah (2010: 111); Mansfield, Ugwu & Doran (1994: 254); Odeh & Battaineh (2002: 67); Sambasivan & Soon (2007: 526); Sweis, Sweis, Hammad & Shboul (2008: 671) Owner’s cash-flow problems Al-Momani (2000: 51); Assaf & Al-Hejji (2006: 349); Kaliba, Muya & Mumba (2009: 522); Koushki, Al-Rashid & Kartam (2005: 294); Monyane & Okumbe (2012: 192); Sweis et al. (2008: 671) Scope changes from owner Al-Momani (2000); Assaf & Al-Hejji (2006: 349); Kaliba et al. (2009: 522); Koushki et al. (2005: 294); Monyane & Okumbe (2012: 192); Sweis et al. (2008: 671) Delays in decision-making Chan & Kumaraswamy (1997: 55); Monyane & Okumbe (2012: 192) Contractor-related factors Inadequate and poor planning Assaf & Al-Hejji (2006: 349); Dlungwana, Nxumalo, Van Huysteen, Rwelamila & Noyana (2002: 25-26); Sambasivan & Soon (2007: 526); Sweis et al. (2008: 671) Contractor’s financial difficulties Aibinu & Odeyinka (2006: 667-677); Frimpong et al. (2003: 321); Sweis et al. (2008: 671) Shortage of skilled labour Baloyi & Bekker (2011: 63); Dlungwana et al. (2002: 25-26); Sweis et al. (2008: 671); Thwala & Phaladi (2009: 533) Poor site management and supervision Assaf & Al-Hejji (2006: 349); Chan & Kumaraswamy (1997: 55); Kaliba et al. (2009: 522); Sambasivan & Soon (2007: 526) Underestimation of project cost Dlakwa & Culpin (1990: 239); Fugar & Agyakwah-Baah (2010: 111); Mansfield et al. (1994: 254); Thwala & Phaladi, (2009: 535) Lack of experience in executing projects Koushki (2005: 294); Muhwezi, Acai & Otim (2014: 21); Nguyen & Chileshe (2015: 398); Sambasivan & Soon (2007: 526); Thwala & Phaladi (2009: 533) Increase in material cost Baloyi & Bekker (2011: 62); Dlakwa & Culpin (1990: 239); Koushki et al. (2005: 294); Mansfield et al. (1994: 254) Consultant-related factors Poor design capacity and design changes Al-Momani (2000: 51); Baloyi & Bekker (2011: 63); Jackson (2002: 4); Nguyen & Chileshe (2015: 398); Muhwezi et al. (2014: 13-23) Incomplete designs by architect and engineering disciplines Aibinu & Odeyinka (2006: 667-677); Baloyi & Bekker (2011: 63); KPMG International (2013: 4); Muhwezi et al. (2014: 13-23) Architect’s incomplete drawing Aibinu & Odeyinka (2006: 675) Design error made by the designers Muhwezi et al. (2014: 13-23); Tumi, Omran & Pakir (2009: 268) Murwira & Bekker • Building an infrastructure project 133 3. Research methodology Due to the number of projects and stakeholders involved, it was decided to conduct a quantitative research design rather than a qualitative approach. As stated by Cooper and Schindler (1998: 21), a questionnaire survey assists with the standardisation of data gathering, decreases non-response errors and increases response rates. The number of people and entities participating in NW DPWR projects are numerous, and it is believed that the inputs and views of as many participants as possible will be valuable to objectively identify the key factor that leads to poor project performance. The structured survey questionnaire invitations were sent via e-mail. For this investigation, an e-mail distribution method offered the opportunity to access a bigger group of potential research participants. 3.1 Sampling method A list of 310 approved consultants (258) and contractors (52) were obtained from the internal NW DPWR procurement database. This database is merely a list of consultants and contractors that are eligible to work for the Department and contains the contact their names, telephone numbers and email addresses. A total of 258 consultants were listed in the database and included architects, civil and structural engineers, electrical engineers, mechanical engineers, and quantity surveyors. A total of 52 contractor names were retrieved. Introductory letters and questionnaires were sent to all companies listed. Owner participants included employees from NW DPWR who interfaced directly with consultants and contractors on projects and had the mandate to provide managerial and technical guidance on the projects as well as approve or disapprove project deliverables. A total of 45 project owner participants were identified to participate. A simple random sampling selecting method resulted in a sample size of 355, representing project owners (45), contractors (52), and consultants (258). 3.2 Data collection A structured questionnaire was distributed electronically, via email, to a total randomly selected sample of 355 project owners, contractors and consultants involved in building construction projects under the NW DPWR Infrastructure Chief Directorate in South Africa. The major causes of construction projects failure in the NW DPWR topics listed in the questionnaire were extracted from reviews of the literature, resulting in the formulation of a questionnaire divided into two Acta Structilia 2017: 24(2) 134 sections, namely the respondent’s profile, and a ranking list of the 50 critical project failure factors where respondents were requested to rank each of the 50 critical project failure factors. The profile section consisted of questions pertaining to general demographics about the respondents. It was divided into three subsections: Type of organisation owner, consultant or contractor; the respondent’s designation, and the professional experience of each respondent. To reduce the respondent’s biasness, and facilitate coding of the questionnaire, closed-ended questions were preferred (Akintoye & Main, 2007: 601). 3.3 Response rate A total of 100 validly completed responses were received, representing a response rate of 28.2%. According to Moyo & Crafford (2010: 68), contemporary built-environment survey response rates range from 7% to 40% in general. It is significant in respect of the reliability of the response rate that, although the number of questionnaires distributed to consultants seems disproportionally high, the response rate from this category was relatively low, thus not causing any bias towards the results. The questionnaire return rate is provided in Table 2. Table 2: Questionnaire return rate Respondents Questionnaires distributed Responses returned Response rate (%) Owner 45 30 66.67 Contractors 52 26 50.00 Consultants 258 44 17.05 Total 355 100 28 3.4 Data analysis and interpretation of findings A 5-point Likert scale was used to measure the opinions of the respondents. Likert-type or frequency scales use fixed choice response formats and are designed to measure attitudes or opinions (Bowling, 1997; Burns & Grove, 1997). For the purpose of analysis and interpretation, the following scale measurement was used: 1 - no contribution to failure; 2 - slight contribution to failure; 3 - significant contribution to failure; 4 - very significant contribution to failure, and 5 - major cause of project failure. From this general data, each of the 50 critical project failure factors could be ranked from having no, slightly, significant, very significant or major contribution to project failure. Murwira & Bekker • Building an infrastructure project 135 To interpret the general data, a combination of the following three descriptive statistical analysis methods was used: • Relative Importance Index (RII); • Spearman’s Rank Correlation (rs), and • Probability values (p-values). 3.4.1 Relative Importance Index The Relative Importance Index (RII) is commonly used to assess comparative results from research in the field of project performance (Aibinu & Odeyinka, 2006; Baloyi & Bekker, 2011; Chan & Kumaraswamy, 1997; Kikwasi, 2012; Muhwezi et al., 2014). For this study, RII was used to determine the ranking of different causes of building construction projects failure from the point of view of owners, contractors and consultants. RII = ∑ W ∕ (A x N), (0 ≤ RII ≤ 1) (1) Where: W = the weight given to each factor by the respondents and ranges from 1 to 5 as per the Likert scale. A = is the highest weight (i.e. 5 in this case). N = is the total number of respondents. The cause with the highest index is the most important, and with the smallest number the least important. The rankings made it possible to cross-compare the failure factors as perceived by the three groups of respondents. 3.4.2 Spearman’s Rank Correlation This study used the Spearman’s Rank Correlation (rs) to identify and test the strength of a relationship between the rankings of any two parties for a single failure cause, while ignoring the ranking of the third party (Assaf & Al-Heijj, 2006; Fugar & Agyakwah-Baah, 2010; Odeh & Battaineh, 2002). The correlation coefficients are calculated using the following formula (2): rs = 1- 6∑d2 (n3 - n) .......................................................................................... (2) Where: rs = Spearman’s Rank Correlation Coefficient. d = the difference in ranking between any two parties. n = the number of causes of failure, which in this case is 50. Acta Structilia 2017: 24(2) 136 The correlation coefficient varies between +1, which implies a perfect positive correlation (agreement) and -1, which implies a perfect negative correlation (disagreement). Values close to unity in magnitude imply good correlation, whereas those near zero indicate little or no correlation (Assaf & Al-Heijji, 2006). When r = 0, it means that there is no correlation (Assaf & Al-Heijji, 2006). 3.4.3 Probability values The p-value is the probability of observing a sample value as extreme as, or more extreme than the value actually observed, given that the null hypothesis is true (Kamanga & Steyn, 2013: 82). To determine whether the parties displayed significant agreement in their rankings, the null hypothesis stated as owner and contractors, contractors and consultants, and owner and consultants do not agree on ranking of the causes of construction projects failure in the NW DPWR was tested at a 95% confidence level (2 tailed tests). The p-value indicates if the correlation is statistically significant. The analysis was aided by the use of MoonStats statistical software. 4. Results 4.1 Relative Importance Index Table 3 shows a complete set of the survey results illustrating the RII as well as the ranking order where 1 shows the factors contributing the most to failure. Murwira & Bekker • Building an infrastructure project 137 Table 3: Overall RII and rank of construction projects failure according to owner, contractors and consultants ID Causes of failure Owner Contractors Consultants All parties RII Rank RII Rank RII Rank Average RII Rank Owner-related factors 1 Late payment of completed works 0.759 13 0.792 7 0.682 28 0.744 16 2 Owner’s cash-flow problems or non-access to funds constraints 0.753 14 0.769 13 0.758 10 0.760 12 3 Late or delayed contract award by owner 0.593 45 0.536 50 0.526 49 0.552 49 4 Late reviewing and approval of design documents 0.620 44 0.608 42 0.600 43 0.609 44 5 Difference between selected bid and consultants’ estimates 0.552 49 0.592 43 0.662 32 0.602 45 6 Delays in decision-making 0.733 19 0.746 23 0.702 24 0.727 18 7 Unrealistic design development period 0.653 40 0.738 25 0.714 20 0.702 30 8 Late issue of instructions 0.703 29 0.677 35 0.718 17 0.700 31 9 Owner interference 0.717 24 0.669 39 0.643 35 0.676 35 10 Poor project scope definition by owner 0.767 12 0.762 15 0.753 11 0.761 11 11 Owner initiated changes during implementation 0.703 29 0.592 43 0.645 34 0.647 39 12 Awarding of contracts primarily on price 0.772 11 0.776 12 0.823 5 0.791 6 13 Corruption and bribery during the bidding and contract award phase 0.857 4 0.800 5 0.809 6 0.822 4 14 Poor information dissemination by owner 0.640 42 0.685 34 0.679 29 0.668 36 Contractor-related factors 15 Late payment of subcontractors for completed works by contractor 0.827 6 0.769 13 0.716 19 0.770 10 16 Fluctuations in material, labour and plant cost 0.669 38 0.631 41 0.609 41 0.636 41 17 Contractor’s cash-flow constraints 0.867 1 0.815 4 0.842 2 0.841 3 18 Underestimation of project cost 0.867 1 0.877 1 0.836 3 0.860 1 19 Shortage of skilled labour 0.793 8 0.762 15 0.786 9 0.780 8 20 Increase in material cost 0.683 33 0.585 45 0.595 45 0.621 42 21 Delay by subcontractor 0.673 35 0.672 38 0.636 38 0.661 37 22 Poor site management and supervision 0.747 16 0.862 2 0.832 4 0.813 5 23 Underestimation of time for completion by contractor 0.793 8 0.777 10 0.791 7 0.787 7 Acta Structilia 2017: 24(2) 138 ID Causes of failure Owner Contractors Consultants All parties RII Rank RII Rank RII Rank Average RII Rank 24 Contractor work overload 0.720 23 0.715 31 0.712 21 0.716 27 25 Lack of experience in executing projects 0.867 1 0.824 3 0.870 1 0.853 2 26 Unforeseen ground conditions 0.673 35 0.577 46 0.614 40 0.621 42 27 Inclement weather 0.513 50 0.546 49 0.507 50 0.522 49 28 Poor planning of material acquisition (shortage of available steel, concrete) 0.697 31 0.792 7 0.691 25 0.727 18 29 Poor risk management by contractor 0.733 19 0.704 33 0.740 13 0.726 21 30 Inadequate contingency allowance 0.587 47 0.569 47 0.595 45 0.584 48 31 Defective works and reworks 0.752 15 0.754 20 0.750 12 0.752 15 32 Incompetent subcontractor 0.747 16 0.731 28 0.791 7 0.756 14 33 Lack of effective communication by contractor 0.747 16 0.715 31 0.712 21 0.725 23 34 Deficiencies in the initial bill of materials 0.707 25 0.738 25 0.641 36 0.695 32 Consultant-related factors 35 Discrepancy between design specification and building code 0.673 35 0.677 35 0.600 43 0.650 38 36 Incomplete designs by engineering disciplines 0.833 5 0.762 15 0.718 17 0.771 9 37 Incomplete design by architect 0.807 7 0.731 28 0.738 14 0.759 13 38 Poor quality of tender documents 0.707 25 0.754 20 0.738 14 0.733 17 39 Poor design capacity 0.733 19 0.762 15 0.676 31 0.724 24 40 Non-adherence to project schedule 0.707 25 0.777 10 0.595 45 0.693 33 41 Complexity of building design 0.587 47 0.677 35 0.536 48 0.600 46 42 Delays in issuing information to contractors 0.690 32 0.762 15 0.686 26 0.713 28 43 Owner-initiated changes during design 0.593 45 0.562 48 0.609 41 0.588 47 44 Lack of project coordination and integration 0.647 41 0.754 20 0.709 23 0.703 29 45 Poor project conceptualisation and design 0.680 34 0.800 5 0.686 26 0.722 25 46 Poor project scope definition by owner 0.660 39 0.785 9 0.735 16 0.726 21 47 Risk identification and allocation 0.628 43 0.646 40 0.636 38 0.637 39 48 Poor constructability 0.733 19 0.746 23 0.679 29 0.720 26 49 Poor stipulation of quality parameters 0.707 25 0.728 30 0.638 37 0.691 34 50 Lack of effective communication by consultants 0.793 8 0.733 27 0.656 33 0.727 18 Murwira & Bekker • Building an infrastructure project 139 The RII of each cause, as perceived by all respondents, was used to illustrate the relative ranking. The results revealed that the three groups of respondents differ in the factors they identified as causing construction projects failure in the NW DPWR and in their ranking. 4.1.1 Owners’ viewpoints The top five causes of construction projects failure in the NW DPWR identified by the owner representatives were the following: • Contractor’s cash-flow constraints; • Underestimation of project cost; • Lack of experience in executing projects; • Corruption and bribery during the bidding and contract award phase, and • Incomplete designs by engineering disciplines. 4.1.2 Contractors’ viewpoints The contractors perceived the top five major causes of construction projects failure in the NW DPWR to be the following: • Underestimation of project cost; • Poor site management and supervision; • Lack of experience in executing projects; • Contractor’s cash-flow constraints, and • Corruption and bribery during the bidding and contract award phase. 4.1.3 Consultants’ viewpoints The top five causes of construction projects failure in the NW DPWR identified by the consultants were the following: • Lack of experience in executing projects; • Contractor’s cash-flow constraints; • Underestimation of project cost; • Poor site management and supervision, and • Awarding of contracts primarily on price. Notably, consultants did not rank any consultant-related factors in the top five. Acta Structilia 2017: 24(2) 140 4.1.4 Overall viewpoints The top five overall views of all three parties to the survey were as follows: • Owner and contractors ranked underestimation of project cost by the contractor as the major cause of construction projects failure in the NW DPWR; • Owner and consultants ranked contractors’ lack of experience in executing projects as the major cause of construction projects failure; • Owner and consultants ranked contractors’ cash-flow constraints as another major cause of construction projects failure in the NW DPWR; • According to owner and contractors, corruption and bribery during the bidding and contract award phase by the owner is among the major causes of construction projects failure in the NW DPWR, and • Based on their viewpoints, contractors claimed that poor project conceptualisation and design are major causes of project failure. All three parties agree that the following causes are the least important: • Inclement weather; • Late or delayed contract award by owner; • Inadequate contingency allowance by the contractor; • Owner-initiated changes, and • Complexity of building design. 4.2 Spearman Rank Correlation and p-values Table 4 provides the values of correlation coefficients among the parties and their corresponding p-values. Table 4: Correlation test of all factors among respondents Owner and contractors Contractors and consultants Owner and consultants Spearman Rank Correlation Coefficient p-value Spearman Rank Correlation Coefficient p-value Spearman Rank Correlation Coefficient p-value 0.694 0.000 0.736 0.000 0.763 0.000 Murwira & Bekker • Building an infrastructure project 141 The rank correlation coefficients calculated for all factors among the respondents were: 0.694 for “owner and contractors”; 0.736 for “contractors and consultants” and 0.763 for “owner and consultants”, respectively. These values show that there is a positive correlation between the three groups. The p-values for the three groups were 0.000, denoting a significant relationship between the causes of construction project failure ranked by these three respondent groups. All the groups generally agreed on the ranking of the causes of construction projects failure in the NW DPWR. 5. Conclusions Table 5 reveals the overall ranking of the top ten most important factors causing construction projects failure in the NW DPWR. All the major stakeholders agreed that seven out of the top ten causes of construction projects failure are linked to contractor-related factors. Four of the top five causes of construction projects failure in the NW DPWR are all contractor related. The highest ranked owner- related cause of construction projects failure is corruption and bribery during the bidding and contract award phase; incomplete designs by engineering disciplines is the highest ranked consultant- related factor. All the top ten factors are linked to the traditional view of project success/failure, which hinges on the ‘iron triangle’ parameters of time, cost and quality. Table 5: Top ten factors causing failure of construction projects ID Causes of failure Average RII Rank Related category 18 Underestimation of project cost 0.860 1 Contractor 25 Lack of experience in executing projects 0.853 2 Contractor 17 Contractor’s cash flow constraints 0.841 3 Contractor 13 Corruption and bribery during the bidding and contract award phase 0.822 4 Owner 22 Poor site management and supervision 0.813 5 Contractor 12 Awarding of contracts primarily on price 0.791 6 Owner 23 Underestimation of time for completion by contractor 0.787 7 Contractor 19 Shortage of skilled labour 0.780 8 Contractor 36 Incomplete designs by engineering disciplines 0.771 9 Consultant 15 Late payment of subcontractors for completed works by contractor 0.770 10 Contractor Acta Structilia 2017: 24(2) 142 6. Recommendations Given the results of the research the following recommendations are proposed: • The NW DPWR should be wary of awarding tenders where the price of the recommended tender is below the pre-tender estimate by the quantity surveyor. The reason for low tender values could be due to various reasons such as desperation to get a contract and substitute the price with change order or an underestimation of the price of the works. • Contractors should critically evaluate their ability and competency to successfully complete the required assignment. It is important for contractors to ensure that they understand the requirements of the project during the pre- contract and bidding period so that they go for works for which they have a competitive advantage. • Contractors’ cash flow should be evaluated prior to bud evaluation and should also be part of the evaluation criteria. • Consultants should be encouraged to improve upfront planning. A schedule should be set to complete design documents on time, and the Department must ensure that they adhere to the agreed schedule in order to avoid delay of work completion. An agreed turnaround time for document reviews should be confirmed upon project kick-off. • All parties should put in place policies that will help retain their valuable human resources thereby avoiding high staff turnover. References Adebowale, O.J. & Ayodeji, F.J. 2015. Analysis of construction- related factors affecting the efficiency of construction labour. Journal of Construction Project Management and Innovation, 5(1), pp. 1115-1130. Aibinu, A.A. & Odeyinka, H.A. 2006. Construction delays and their causative factors in Nigeria. Journal of Construction Engineering and Management, 132(7), pp. 667-677. https://doi.org/10.1061/ (ASCE)0733-9364(2006)132:7(667) Akintoye, A. & Main, J. 2007. Collaborative relationships in construction: the UK contractors’ perception, Engineering, Construction and Architectural Management Journal, 14(6), pp. 597-617. https://doi. org/10.1108/09699980710829049 https://doi.org/10.1061/(ASCE)0733-9364(2006)132:7(667) https://doi.org/10.1061/(ASCE)0733-9364(2006)132:7(667) https://doi.org/10.1108/09699980710829049 https://doi.org/10.1108/09699980710829049 Murwira & Bekker • Building an infrastructure project 143 Al-Momani, A.H. 2000. Construction delay: A quantitative analysis. International Journal of Project Management, 18(1), pp. 51-59. https://doi.org/10.1016/S0263-7863(98)00060-X Assaf, S.A. & Al-Hejji, S. 2006. Causes of delay in large construction projects. International Journal of Project Management, 24(4), pp. 349-357. https://doi.org/10.1016/j.ijproman.2005.11.010 Baloyi, L. & Bekker, M.C. 2011. Causes of construction cost and time overruns: The 2010 FIFA World Cup stadia in South Africa. Acta Structilia, 18(1), pp. 51-67. Bowling, A. 1997. Research methods in health. Buckingham, UK: Open University Press. Burns, N. & Grove, S.K. 1997. The practice of nursing research conduct, critique, and utilization. Philadelphia, Pennsylvania: W.B. Saunders and Co. Chan, D.W.M. & Kumaraswamy, M.M. 1997. A comparative study of causes of time overruns in Hong Kong construction projects. International Journal of Project Management, 15(1), pp. 55-63. https://doi.org/10.1016/S0263-7863(96)00039-7 Cooper, D.R & Schindler, P.S. 1998. Business research methods. 6th edition. New York: Irwin/McGraw-Hill. Dlakwa, M.M. & Culpin, M.F. 1990. Reasons for overrun in public sector construction projects in Nigeria. International Journal of Project Management, 8(4), pp. 237-241. https://doi. org/10.1016/0263-7863(90)90032-7 Dlungwana, S., Nxumalo, H.X., Van Huysteen, S., Rwelamila, P.D. & Noyana, C. 2002. Development and implementation of the South African Construction Excellence Model (SACEM). In: Ahmad, A., Ahmed, S.M. & Azhar, S. (Eds). First International Conference on Construction in the 21st Century (CITC 2002), Challenges and Opportunities in Management and Technology, 25-26 April 2002, Miami, Florida, USA. Miami, Fl.: Florida International University. Frimpong, Y., Oluwoye, J. & Crawford, L. 2003. Causes of delay and cost overruns in construction of groundwater projects in developing countries; Ghana as the case study. International Journal of Project Management, 21(5), pp. 321-326. https://doi.org/10.1016/ S0263-7863(02)00055-8 Fugar, F.D.K. & Agyakwah-Baah, A.B. 2010. Delays in building construction projects in Ghana. Australasian Journal of Construction https://doi.org/10.1016/S0263-7863(98)00060-X https://doi.org/10.1016/j.ijproman.2005.11.010 https://doi.org/10.1016/S0263-7863(96)00039-7 https://doi.org/10.1016/0263-7863(90)90032-7 https://doi.org/10.1016/0263-7863(90)90032-7 https://doi.org/10.1016/S0263-7863(02)00055-8 https://doi.org/10.1016/S0263-7863(02)00055-8 Acta Structilia 2017: 24(2) 144 Economics and Building, 10(1/2), pp. 103-116. https://doi.org/10.5130/ ajceb.v10i1/2.1592 Jackson, S. 2002. Project cost overruns and risk management. Greenwood, D. (Ed.). Proceedings of the Association of Researchers in Construction Management, 18th Annual ARCOM Conference, 2-4 September 2001, Northumber University, Newcastle, UK. Newcastle, UK: ARCOM, pp. 99-108. Kaliba, C., Muya, M. & Mumba, K. 2009. Cost escalation and schedule delays in road construction projects in Zambia. International Journal of Project Management, 27(5), pp. 522-531. https://doi.org/10.1016/j. ijproman.2008.07.003 Kamanga, M. & Steyn, W. 2013. Causes of delay in road construction projects in Malawi. Journal of the South African Institution of Civil Engineering, 55(3), pp. 79-85. Kikwasi, G.J. 2012. Causes and effects of delays and disruptions in construction projects in Tanzania. Australasian Journal of Construction Economics and Building, Conference Series, 1(2), pp. 52-59. Koushki, P.A., Al-Rashid, K. & Kartam, N. 2005. Delays and cost increases in the construction of private residential projects in Kuwait. Construction Management and Economics, 23(3), pp. 285-294. https://doi.org/10.1080/0144619042000326710 KPMG International. 2013. Avoiding major project failure - Turning Black swans White. [online]. Available at: [Accessed: 11 March 2016]. Mansfield, N.R., Ugwu, O.O. & Doran, T. 1994. Causes of delay and cost overruns in Nigerian construction projects. International Journal of Project Management, 12(4), pp. 254-260. https://doi. org/10.1016/0263-7863(94)90050-7 Monyane, T.G. & Okumbe, J.O. 2012. An evaluation of cost performance of public projects in the Free State Province of South Africa. In: Proceedings of the 2nd NMMU Construction Management Conference, 25-27 November 2012, Port Elizabeth, South Africa. Port Elizabeth, South Africa: NMMU, pp. 191-197. Moyo, A. & Crafford, G.J. 2010. The impact of hyperinflation on Zimbabwean construction industry. Acta Structilia, 17(2), pp. 53-83. Muhwezi, L., Acai, J. & Otim, G. 2014. An assessment of the factors causing delays on building construction projects in Uganda. https://doi.org/10.5130/ajceb.v10i1/2.1592 https://doi.org/10.5130/ajceb.v10i1/2.1592 https://doi.org/10.1016/j.ijproman.2008.07.003 https://doi.org/10.1016/j.ijproman.2008.07.003 https://doi.org/10.1080/0144619042000326710 https://www.kpmg.com/BE/en/IssuesAndInsights/Articles https://www.kpmg.com/BE/en/IssuesAndInsights/Articles avoiding-major-project-failure.pdf https://doi.org/10.1016/0263-7863(94)90050-7 https://doi.org/10.1016/0263-7863(94)90050-7 Murwira & Bekker • Building an infrastructure project 145 International Journal of Construction Engineering and Management, 3(1), pp. 13-23. NPC (National Planning Commission). 2011. National Development Plan - Vision for 2030. South Africa: The Presidency. Nguyen, T.P. & Chileshe, N. 2015. Revisiting the critical factors causing failure of construction projects in Vietnam. Built Environment Project and Asset Management, 5(4), pp. 398-416. https://doi.org/10.1108/ BEPAM-10-2013-0042 Odeh, A.M. & Battaineh, H.T. 2002. Causes of construction delay: Traditional contracts. International Journal of Project Management, 20(1), pp. 67-73. https://doi.org/10.1016/S0263-7863(00)00037-5 Ramokolo, B. & Smallwood, J. 2008. The capacity of emerging civil engineering contractors. Acta Structilia, 15(2), pp. 45-74. RDP (The Reconstruction and Development Programme). 1994. [online]. Available at: [Accessed: 14 October 2015]. SAICE (South African Institution of Civil Engineers). 2016. Focus on: National Treasury Standard for Infrastructure Procurement and Delivery Management. Civilution, February 2016, pp. 1-84. Sambasivan, M. & Soon, Y.W. 2007. Causes and effects of delays in Malaysian construction industry. International Journal of Project Management, 25(5), pp. 517-526. https://doi.org/10.1016/j. ijproman.2006.11.007 Sweis, G., Sweis, R., Hammad, A.A. & Shboul, A. 2008. Delays in construction projects: The case of Jordan. International Journal of Project Management, 26(6), pp. 665-674. https://doi.org/10.1016/j. ijproman.2007.09.009 Thwala, D. & Phaladi, M.J. 2009. An exploratory study of problems facing small contractors in the North-West Province of South Africa. African Journal of Business Management, 3(10), pp. 533-539. Tumi, S.A., Omran, A. & Pakir, A.H.K. 2009. Causes of delays in construction industry in Libya. In: Proceedings of the International Conference on Administration and Business, 14-15 November 2009, Faculty of Administration and Business, University of Bucharest, Romania. Bucharest, Romania, University of Bucharest, pp. 265-272. https://doi.org/10.1108/BEPAM-10-2013-0042 https://doi.org/10.1108/BEPAM-10-2013-0042 https://doi.org/10.1016/S0263-7863(00)00037-5 http://www.sahistory.org.za/sites/default/files/the_reconstruction_and_development_programm_1994.pdf http://www.sahistory.org.za/sites/default/files/the_reconstruction_and_development_programm_1994.pdf https://doi.org/10.1016/j.ijproman.2006.11.007 https://doi.org/10.1016/j.ijproman.2006.11.007 https://doi.org/10.1016/j.ijproman.2007.09.009 https://doi.org/10.1016/j.ijproman.2007.09.009 1._Introduction 1.1._Management_of_construction_projects 1.2._Current_construction_project_manage 1.3._Research_problem