9-3-2011.pdf Al-Qadisiya Journal For Engineering Sciences Vol. 4 No. 3 Year 2011 COMPUTER-AIDED SELECTION OF THE OPTIMAL LOT SIZING SYSTEM (CALS) Farah Kamil Abd Muslim Department of Mechanics Technical Institute/ Dewanya ABSTRACT A lot of works have been done by the researchers to solve lot-sizing problems over the past few decades. Many techniques and algorithm have been developed to solve the lot-sizing problems. Basically, most of the algorithms are developed either based on heuristic or mathematical approach. Since Computer-Aided has been given attention by the researchers in many areas including production planning, therefore in this paper we implement Computer-Aided to solve single level lot-sizing problem. Five models are developed based on five well known heuristic techniques, which are Lot-For-Lot (LFL), Economic Order Quantity (EOQ), Periodic Order Quantity (POQ), Part Period Balancing (PPB) and Wagner-Within algorithm (WW). The planning period involves in the model is 5 period where demand in the periods are varies but deterministic. The model was developed using Visual Basic Version 5 with ACCESS database. Results show that when entering the needed inputs through the user interface, which is general inputs and special inputs, the (CALS) system selects the suitable lot size technique that gave optimum solution and easy application to the lot-sizing problem. KEYWORDS: Lot sizing techniques, Material requirements planning. )CALS( / يب . یة. LFL( حا EOQPOQPPBWW.( Al-Qadisiya Journal For Engineering Sciences Vol. 4 No. 3 Year 2011 ـ . ه ACCESS. ) (CALS . NOMENCLATURE BOM = Bill of Material C = Carrying Cost Per Item Per Unit Time. Ci = Duration For Which Inventory is Carried CALS = Computer aided lot sizing Co = Ordering Cost D = Average Demand EOQ = Economic Order Quantity EPP = Economic Part Period LFL = Lot For Lot LLC = Low Level Code LS = Lot Size LT = Lead Time MPS = Master Production Schedule MRP = Material Requirements Planning PP = Cumulative Part-Period for period PPB = Part period balancing POQ = Periodic Order Quantity Q = Economic Order Quantity. Ri = Requirement for period i. S = Setup Cost Per Batch SM = Silver - Meal T =Ordering Interval WW = Wagner- Within 1. INTRODUCTION Lot sizing is an approach used to determine optimum order or production quantity in each period in a planning horizon. It is widely used in Material Requirement Planning System. Many lot- sizing techniques have been developed and established by the researchers. The developments of lot- sizing techniques are basically based on either heuristic approach or mathematical modeling. Order Quantity (EOQ), Periodic order quantity (POQ), Lot-For-Lot (LFL) and Part Period Balancing (PPB) are amongst techniques that adopted heuristic approach. Meanwhile, Wagner-Within (WW) is considered mathematical approach in which it was developed based on dynamic programming. This paper will discuss about implementing computerized model to solve lot-sizing problems. The purpose of developing computerized model is to evaluate the performance of computer in solving lot sizing problems and to overcome the difficulties faced by the user in using either heuristic or mathematical approach. 2. LITERATURE REVIEW This section gives literature review on lot sizing, computer-Aided and the research that motivates the author to apply computer-Aided in MRP problem of lot sizing. Problem in determining the optimum quantities (lot sizes) to order in discrete time periods of a single item over Al-Qadisiya Journal For Engineering Sciences Vol. 4 No. 3 Year 2011 N periods to satisfy a certain demand pattern with the objective to minimize the sum of ordering and carrying cost is a common problem in keeping inventory always in stock. Method proposed by (Radzi, Haron and Johari 2006) shows neural network to solve single level lot-sizing problem. Three models are developed based on three well known heuristic techniques, which are Periodic Order Quantity (POQ), Lot-For-Lot (LFL) and Silver-Meal (SM). The model was developed using MatLab software. (Hoesell & Wagelmans 1990) study sensitivity analysis of the incapacitated single level economic lot-sizing problem, which was introduced by Wagner and Whitin about thirty years ago. (Cheng 1989) tested two other well-known non-cost-based heuristics: the lot-for-lot and fixed period requirement rules, and compared with the Wagner-Within(WW)optimization algorithm the lot-for-lot proves to be an effective rule to use when inventory cost is high. (De Matteis 1968) developed simpler algorithm that has been such as by PPB. (Saydam & Evans 1990) show the relative performances of four popular heuristic against the (WW). (AL-Juboory 2002) developed Computer-Aided Monitoring of Production Planning System which was built by means of the relational database technology using Visual Basic Version 5 with ACCESS database. (Gaafar 2000) applied neural network model in MRP problem of lot sizing. The performance of the model is analyzed and compared to common heuristic method. 3. REASEARCH METHODOLOGY 3.1. Data Preparation: The necessary information for (CALST) system are shown in figure (1). They are: erial (BOM): for all parent items -times: for all items 3.2. The developed (CALS) system: The (CALS) system is developed specifically to select the suitable lot size technique that give optimal solution, also it is easy to be applied in lot-sizing problems. The developed system can perform several functions as depicted in figure (1). Each function interface with the other functions. 3.2.1. User interface: The user interface main module plays a key role in various (CALST) system activities, by providing the possibility of accessing any part of the system. User interface is the communication mechanism between the user and other modules of the system. When the user enters the needed inputs through the user interface, the system selects the suitable techniques relative to the input. 3.2.2. Common Database: the database must contain high level information about the product, because in such system we need common database that supports the user interface. This database consists of: 1. Item Master Database. The item master database (also called part master database or inventory record database) contains a record for every item in the company's inventory products, assemblies, components, materials, and supplies. A typical list of the data stored for each item is represented in table (1). We will describe the elements on the list. a- Item Number: The item number is a unique number that identifies the item and is the key to record in the file. b- Projected Inventory on Hand: The projected inventory on hand is the current inventory of the item. c- Lead times: The lead-time is the time between placing an order and receiving it. d- Scheduled receipt: Scheduled receipt is the previously released orders, either purchased from the market or manufactured. Al-Qadisiya Journal For Engineering Sciences Vol. 4 No. 3 Year 2011 e- Ordering Cost: The cost of order release. f- Holding Cost: the cost of carrying. 2. Bill of Material Database. The bill of material database specifies what materials, components, assemblies, and subassemblies are used in making the product. We will describe the elements on the list. a- Low Level Code (LLC): Level refers to where an item fits in the product structure. The final product is at level 0. The components used directly in making the final products are at level 1. Components used in making level 1 items are at level 2, and so forth. b- Quantity per Assembly: it is the required number of a part in each assembly. 3.2.3. Lot Sizing Module: lot sizing function is the process of determining the quantities in which order are placed. This module consists of several lot sizing techniques. Therefore, depending on the type of inputs that the user enter, the system has been designed and developed to suggest the best lot sizing technique that correspond to these inputs as shown in figure (2). 1. LFL Function: it is the name given to the method that orders exactly what is required in each period. It should produce units only as needed with no safety stock and no anticipation of future orders. Lot for lot is frequently used for expensive items and high discontinuous demand item. The LFL function is built as shown in figure (3). {Net Requirements}= {Gross Requirements} {On-hand Inv.} {Scheduled Receipts} Gross Requirements: The anticipated future usage of the item (MPS). Scheduled Receipts: Previously released orders, either purchased or manufactured. Current: On-hand inventory (end-item, subassembly, or processed parts). Lot-Sizing (LS) Rule: How the jobs will be sized in order to minimize the cost. Planned Lead-Time: The time between placing an order and to receiving it. Planned Order Receipts: Purchase or manufactured items that must be available at the beginning of a timer bucket. Planned Order Released: Planned orders after offsetting using lead-time. 2. EOQ Function: EOQ module assumes that the demand is constant. In the EOQ formula, annual demand is replaced with average demand per period. A weakness of the EOQ technique is that large quantities of units, which are not immediately required, are carried in stock. The order quantity is specified by the economic order formula: Q = 2SD/ C (1) Where: Q= Economic order quantity. S= Setup cost per batch. D= Average demand for item per unit time. C=Carrying cost per item per unit time. The EOQ function is built as shown in figure (4). 3. POQ Function: The periodic order quantity (POQ) technique is based on the same thinking as the EOQ method. For the EOQ technique the order quantity is constant while ordering interval varies. However, for the POQ model the ordering interval is constant while the order quantity various, thus: T=Q/D (2) Where: T=Ordering interval. Q= Economic order quantity. D= Average demand for item per unit time. Al-Qadisiya Journal For Engineering Sciences Vol. 4 No. 3 Year 2011 The POQ function is built as shown in figure (5). 4. PPB Function: PPB is a more dynamic approach to balance setup and holding cost, PPB uses additional information by changing the lot size to reflect requirements of the next lot size in the future. It divides demand requirements into order periods such that ordering and holding cost are balanced. Although the technique does not guarantee an optimum solution, it does produce a very good solution. The procedure for PPB is as follows: Calculate an economic part period or EPP, for the problem. This value is expressed as a ratio between ordering and holding cost. It is used as a measuring tool to determine when to place an order. EPP = Ordering cost/ Carrying cost = Co/Cc (3) This technique selects the order quantity at which the part period cost matches the EPP value, most closely PPi= PPi-1 + (Ri*Ci) (4) Where: PP: Cumulative Part-Period for period i. Ri: Requirement for period i. Ci: Duration for which inventory is carried. The PPB function is built as shown in figure (6). 5. WW function: The Wagner-Within procedure is a dynamic programming model that adds some complexity to the lot-size computation. Wagner-Within begins with the first period in the planning horizon and evaluates all possible combinations of orders to meet demand in that period. It then proceeds to period two and does the same, and so on, until the optimal method for meeting demand in all periods is determined. The WW function is built as shown in figure (7). 4. RESULTS AND DISCUSSION To show the validity of our approach and for the purpose of completeness, we applied this system in state company of rubber industries. This company provided us the necessary information such as (production plan, ordering and carrying cost for product, operation time for all the production processes, and the inventory information). The company produces several types of products. Product (X) is being selected which consists of (21) part. Planned order is released at the same time for all the parts. The monthly quantity of product (X) are (1716) for September 2010. The researcher selected part number (1) of product (X) to test the (CALS) system as follow: By entering the following data(current year, month, monthly quantity, days per period, and holiday at each period), and by using the bill of material database that consist of(part number, quantity per assembly, and low level code). The cost database provide the system (ordering cost and carrying cost). The inventory database provide the system (scheduled receipts, projected on hand and lead time).the results are master production schedule table from the following equations: Quantity per day= monthly quantity / number of work days during the month = 1716 / 26= 66 Quantity per period= Quantity per day number of work days per period Quantity per period1 = 66 2 = 132 Then the system calculate the lot sizing techniques as follow: 1- Lot-for-lot: { Gross Requirements }= {Quantity per period} { Quantity per assembly } { Gross Requirements for period1}= 132 1 =132 Al-Qadisiya Journal For Engineering Sciences Vol. 4 No. 3 Year 2011 {Net Requirements}= {Gross Requirements} {On-hand Inventory} {Scheduled Receipts} {Net Requirements for period1}= 132 0 0=132 {Planned Order Receipts}={Net Requirements}=132 Total cost= Ordering cost for all period+ Carrying cost for all period = (8072.4 5) + 0 = 40362 $ 2- Economic order quantity: { Gross Requirements }= {Quantity per period} { Quantity per assembly } { Gross Requirements for period1}= 132 1 =132 Average demand for item per unit time(D)=SUM{ Gross Requirements for all periods}/ number of periods= (132+396+396+396+396)/ 5=343.2 Economic order quantity (Q )= 2 Ordering cost per batch (S Average demand for item per unit time(D) / Carrying cost per item per unit time(C) Economic order quantity (Q )for period1= (2 8072.4 343.2) / 16.1448=586 {Net Requirements}= {Gross Requirements} {On-hand Inventory} {Scheduled Receipts} {Net Requirements for period1}= 132 0 0=132 {Planned Order Receipts}={ Economic order quantity }=586 Total cost= Ordering cost for all period+ Carrying cost for all period = (8072.4 4) + (7329.7392+ 7329.7392+ 936.3984+0+9202.536)= 57088.0128 $ 3- Periodic order quantity: { Gross Requirements }= {Quantity per period} { Quantity per assembly } { Gross Requirements for period1}= 132 1 =132 Average demand for item per unit time(D)=SUM{ Gross Requirements for all periods}/ number of periods= (132+396+396+396+396)/ 5=343.2 Economic order quantity (Q )= 2 Ordering cost per batch (S Average demand for item per unit time(D) / Carrying cost per item per unit time(C) Economic order quantity (Q) for period1= (2 8072.4 343.2) / 16.1448=586 Ordering interval(T)=Economic order quantity(Q)/Average demand for item per unit time(D) =586/343.2=2 {Net Requirements}= {Gross Requirements} {On-hand Inventory} {Scheduled Receipts} {Net Requirements for period1}= 132 0 0=132 {Planned Order Receipts}={ Planned Order Receipts for pereiod1+ Planned Order Receipts for pereiod2 }=132+396= 528 Total cost= Ordering cost for all period+ Carrying cost for all period = (8072.4 3) + (6393.3408 2)= 37003.8816 $ 4- Part-Period balancing: { Gross Requirements }= {Quantity per period} { Quantity per assembly } { Gross Requirements for period1}= 132 1 =132 Economic part period(EPP)=Ordering cost(Co)/Carrying cost(Cc)= 8072.4/16.1448 =500 Cumulative Part-Period for period 1 (PP1)= Cumulative Part-Period for period 0 (PP0) + {Requirement for period 1 (R1)* Duration for which inventory is carried (C1)} Cumulative Part-Period for period1(PP1)=0-(132 0)=0 (is this closet match to EPP) ? No {Prospective lot size for period 1 }={Net Requirements for period 1 + Net Requirements for period 0 }=132-0=132 Al-Qadisiya Journal For Engineering Sciences Vol. 4 No. 3 Year 2011 Total cost= Ordering cost for all period+ Carrying cost for all period = (8072.4 4) + (10655.568+4262.2272+6393.3408)= 53600.736$ 5- Wagner-Within: { Gross Requirements }= {Quantity per period} { Quantity per assembly } {Gross Requirements for period1}= 132 1 =132 {Net Requirements}= {Gross Requirements} {On-hand Inventory} {Scheduled Receipts} {Net Requirements for period1}= 132 0 0=132 period alternatives Ordering cost Carrying cost Total cost Optimal policy 1 (1) 8072.4 0 8072.4 (1) After calculate all period the optimal policy is (1,2,3,4,5) {Planned Order Receipts}=SUM{Net requirements}=132+396+396+396+396=1716 Total cost= Ordering cost for all period+ Carrying cost for all period = (8072.4) + (25573.363+19180.022+12786.6811+6393.3408)= 72005.808$ From the above techniques the system selects the best technique (Periodic order quantity) that have minimum cost The application of the proposed system is introduced here. Figure (8) shows the proposed input frame and the result ( master production schedule MPS) depend upon database in figure (9),(10),(11) to calculate the lot sizing technique for the five techniques as shows in figures (12),(13),(14),(15),(16). Figure (17) shows the output of the system and the selected suitable lot sizing technique depend on minimum cost. 4. CONCLUSIONS In this paper, we construct a software program that selects the suitable lot sizing technique depend upon scientific bases. The (CALS) system provides with bill of material database, inventory database, and cost database that can be updated at any time. This model can be applied to solve lot sizing problems faster and easier because it can give optimum solution and posses certain characteristic that make the model more effective to be used. From the (CALS) system we conclude the following: Lot-for-lot techniques order just what is required for production based on net requirements and it may not always be feasible. If setup costs are high, costs may be high as well EOQ using average demand and expects a known constant demand and MRP systems often deal with unknown and variable demand Part-period balancing tries to make the setup costs as close to the carrying costs as possible. Fixed order quantity method constant lot sizes Wagner-Whitin REFERENCEES [1] AL-Juboory, F.K., "Computer aided monitoring of production planning", M.Sc. thesis, Baghdad, 2002. [2] Cheng, T.C.E., " A Comparative study of some non-cost-based lot-sizing heuristics", Computers Ind. Engng. VOL. 16, No.1, PP87-96,1989, Pergamon Press PLC. [3] De Matteis, J.J. and Mendoza, A.G., 1968. An economic lot sizing technique. IBM systems Journal, 7: 30- Al-Qadisiya Journal For Engineering Sciences Vol. 4 No. 3 Year 2011 [4] Gaafar, L.K. and Choueiki, M.H., 2000, "A neural network model for solving the lot sizing problem", The International Journal of Management Science, Omega. 28:175-184. [5] Hoesel, Stan Van, and Wagelmans, Albert, " Sensitivity analysis of the economic lot-sizing problem" OR 238-90 November 1990. [6] Radzi,Nor Haizan Mohamed, Haron, Habibollah, and Johari ,Tuan Irdawati Tuan, " Lot Sizing Using Neural Network Approach" School of Mathematical Sciences, Universiti Sains Malaysia, Penang, June 13-15, 2006 [7] SAYDAM, CEM& EVANS, JAMES R., "A Comparative performance analysis of the Wagner-Within algorithm and lot-sizing heuristics", Computers Ind. Engng. VOL. 18, No.1, PP.91- 93,1990, Pergamon Press PLC. Table (3): Lot Sizing Report PeriodItem: LLC: LS: LT: Current 1 2 3 4 5 6 7 8 Gross Requirements Scheduled Receipts Projected Inventory Balance Net Requirements Planned order Receipts Planned Order Released Item No. Projected on Hand Lead Time Scheduled Receipt Ordering Cost Holding Cost Serial No. Part No. LLC Quantity Per Assembly Table (1): Item Master File Table (2): Bill of Material File Al-Qadisiya Journal For Engineering Sciences Vol. 4 No. 3 Year 2011 WW function Start Enter your inputs PPB function POQ function EOQ function LFL function Suitable Lot Sizing Technique Figure (2): Flowchart of the Lot Sizing Module Item Master Database Bill of Material Database Figure (1): System architecture User interface Lot Sizing Module Common Database Lot Sizing Report Al-Qadisiya Journal For Engineering Sciences Vol. 4 No. 3 Year 2011 Start For i = 0 4 Input the lead time Calculate the gross requirements Calculate projected on hand Calculate net requirements Calculate planned order release Is I < 4 Lot Sizing Report No YesNext i Bill of material databaseInventory database Figure (3): Flowchart of the LFL Function Calculate planned order receipts Start For i = 0 4 Input the lead time Calculate the gross requirements Calculate average demand Calculate optimal quantity Calculate net requirements (NR) Is NR<= 4 Lot Sizing Report No Yes Next i Bill of material database Cost database Planned order receipts (POR1)=0 POR1= optimal quantity Calculate projected on hand Yes No Is i < 4 Inventory database Calculate planned order release (POR2) Al-Qadisiya Journal For Engineering Sciences Vol. 4 No. 3 Year 2011 Start For i = 0 4 Input the lead time Calculate the gross requirements Calculate average demand Calculate optimal quantity Calculate optimal ordering interval Lot Sizing Report Next i Bill of material database Cost database Figure (5): Flowchart of the POQ Function Calculate planned order receipts Calculate net requirements Calculate projected on hand Yes No Is i < 4 Inventory database Calculate planned order release Al-Qadisiya Journal For Engineering Sciences Vol. 4 No. 3 Year 2011 Start For i = 0 4 Input the lead time Calculate the gross requirements Calculate economic part-period (EPP) Calculate projected on hand Calculate net requirements Lot Sizing Report Next i Bill of material database Cost database Figure (6): Flowchart of the PPB Function Calculate part-period (Cumulative) Calculate prospective part-period Calculate carried in inventory Yes No Is i < 4 Inventory database Is PPC >EPP Yes No Calculate planned order receipts Calculate planned order release Al-Qadisiya Journal For Engineering Sciences Vol. 4 No. 3 Year 2011 Start For i = 0 4 Input the lead time Calculate the gross requirements Calculate projected on hand Calculate net requirements Lot Sizing Report Next i Bill of material database Cost database Figure (7): Flowchart of the WW Function Select least total cost probability Calculate Carrying cost Calculate Probability Yes No Is j < 4 Inventory database Is i < 4 Yes No Calculate planned order receipts Calculate planned order release Calculate Ordering cost For j = 0 4 Next j Al-Qadisiya Journal For Engineering Sciences Vol. 4 No. 3 Year 2011 Figure (8): The proposed input frame Figure (9): Bill of Material Database frame Figure (9): Cost Database frame Figure (10): Cost Database frame Al-Qadisiya Journal For Engineering Sciences Vol. 4 No. 3 Year 2011 Figure (11): Inventory Database frame Figure (12): Lot For Lot Technique Frame Al-Qadisiya Journal For Engineering Sciences Vol. 4 No. 3 Year 2011 Figure (14) Periodic Order Quantity Technique Frame Figure (13) Economic Order Quantity Technique Frame Al-Qadisiya Journal For Engineering Sciences Vol. 4 No. 3 Year 2011 Figure (15) Part Period Balancing Technique Frame Figure (16) Wagner -Within Algorithm Technique Frame Al-Qadisiya Journal For Engineering Sciences Vol. 4 No. 3 Year 2011 Figure (17) Select The Suitable Lot Size Technique Frame