american_scientific_journal-4903	Thet Soe, Thet; Mya Cho, Aye	Development of Better Time and Cost Plan by Integrating Information in a Construction Project	2019	14	.pdf	application/pdf	3972	222	56	According to traditional method, the estimated time is seven years and total construction cost is 58571 lakhs. - After applying BIM, the estimated time is five years and construction cost is 54325 lakhs. As a result of Microsoft Project software, the estimated time is five years and construction cost is 54325 lakhs.	cache/american_scientific_journal-4903.pdf	txt/american_scientific_journal-4903.txt