DOI: 10.3303/CET2188071 
 

 
 

 
 
 

 
 

 
 
 

 
 
 

 
 
 

 
 
 

 
 
 

 

 

 
 
 

 
 
 

 
 
 

 
 
 

 
 

 

Paper Received: 7 May 2021; Revised: 27 August 2021; Accepted: 8 October 2021 
Please cite this article as: Castro M.T., Ocon J.D., 2021, Can Off‑grid Islands Powered by Renewable Energy Microgrids be Operated 
Sustainably without Subsidies? A Techno‑economic Case Study in the Philippines, Chemical Engineering Transactions, 88, 427-432 
DOI:10.3303/CET2188071

CHEMICAL ENGINEERING TRANSACTIONS

VOL. 88, 2021 

A publication of

The Italian Association
of Chemical Engineering
Online at www.cetjournal.it 

Guest Editors: Petar S. Varbanov, Yee Van Fan, Jiří J. Klemeš

Copyright © 2021, AIDIC Servizi S.r.l. 

ISBN 978-88-95608-86-0; ISSN 2283-9216

Can Off-grid Islands Powered by Renewable Energy
Microgrids be Operated Sustainably without Subsidies?

A Techno-economic Case Study in the Philippines
Michael T. Castroa, Joey D. Ocona,b,*
a Laboratory of Electrochemical Engineering (LEE), Department of Chemical Engineering, University of the Philippines 

Diliman, Quezon City 1101, Philippines
b Energy Engineering Program, National Graduate School of Engineering, College of Engineering, University of the 

Philippines Diliman, Quezon City 1101, Philippines
jdocon@up.edu.ph

The Philippines is home to thousands of off-grid islands that are too distant from the mainland and consequently
expensive to connect to the main grid. These islands are typically powered by diesel generators, which will
require more subsidies as fuel costs continue to increase. Hybrid renewable energy systems (HRES) are an
alternative energy source with lower reliance on fuel and generation costs. In this work, the financial
sustainability of deploying HRES in Philippine off-grid islands of various sizes was evaluated. Patongong Island,
Lapinigan Island, Balabac Island, and Sibuyan Island were selected as case studies as their peak electrical
demand varies from 4.4 kW in Patongong Island to 3.2 MW in Sibuyan Island, representing  a large fraction of
off-grid islands in the country. HRES consisting of solar photovoltaics, wind turbines, lithium-ion batteries, and
diesel generators in these islands were modeled in Island Systems LCOEmin Algorithm (ISLA), an in-house
energy systems modeling tool. Profitability metrics, such as the net present value, internal rate of return (IRR),
and payback period (PBP), were then calculated at varying electricity prices. The large Sibuyan island was
already profitable at 0.2 USD/kWh, comparable to the mainland rate, which suggests that subsidies in large
islands can be removed. The low 11 % IRR and 13-year PBP may not be attractive to private investors, but this
may be alleviated by raising electricity prices. Other islands, however, will still require subsidies as the small
Patongong Island becomes profitable only at 1.5 times the mainland rate. This work encourages private sector
participation by providing financial insights absent in many techno-economic studies. Moreover, this study
enlightens the public sector about the necessity of subsidies for providing energy access in small off-grid islands.

1. Introduction

The Philippines is inhabited by about 5.5×106 people without access to electricity (World Bank, 2020). This is
attributed to the country’s archipelagic geography, which results in thousands of off-grid islands that are too
expensive to interconnect to the main grid. Electricity in these islands is generated by diesel generators operated
by the National Power Corporation - Small Power Utilities Group (NPC-SPUG). The logistical difficulty in
transporting diesel fuel, however, has resulted in a costly electricity supply that is limited to a few hours each
day. The combustion of fossil fuels also generates greenhouse gases that contribute to climate change. Lastly,
the subsidies required to operate these generators is projected to increase due to rising fuel costs and the
growing demand for electricity (Aziz et al., 2019).
Hybrid renewable energy systems (HRES) have therefore been investigated as an alternative energy source in
off-grid islands (Manoj Kumar et al., 2020). These consist of a renewable energy (RE) technology, such as solar
photovoltaics (PV) and wind turbines, to displace reliance on fossil fuels, energy storage technologies, such as
lithium-ion (Li-ion) batteries to stabilize the intermittency of RE, and conventional sources, such as diesel
generators, that can be dispatched whenever RE is unavailable. The techno-economic potential of HRES has
been demonstrated in various studies. Ocon and Bertheau (2019) showed that a transition from a diesel-only
scenario to an HRES consisting of solar PV, Li-ion, and diesel generators in 215 Philippine off-grid areas can
reduce the levelized cost of electricity (LCOE) by an average of 20 %.

427



While the rapidly decreasing cost of RE technologies (Schmidt et al., 2017) has accelerated the energy transition
worldwide, the rate of HRES deployment in the Philippines has been rather slow. In the public sector, the
Department of Energy (DOE) has plans to phase out the Universal Charge for Missionary Electrification (UCME)
subsidy scheme that currently supports energy access in off-grid areas (BusinessWorld, 2019). As for the private
sector, the financial viability of off-grid electrification projects has yet to be analyzed in detail. It should be noted
that the lower cost of HRES with respect to diesel-only systems does not necessarily imply that the deployment
of HRES is profitable.
In this work, the financial viability of installing HRES in Philippine off-grid islands was evaluated. First, Philippine
off-grid islands with representative electrical demands were selected as case studies. Next, the solar and wind
resource availability in each island was estimated and the techno-economic parameters describing the energy
components (e.g., solar PV, wind turbines, Li-ion batteries, and diesel). The energy systems in each island was
then modeled using Island Systems LCOEmin Algorithm (ISLA), an in-house energy systems modeling tool.
Lastly, techno-economic and profitability metrics were calculated and the financial viability of HRES in each
island was discussed. This work provides insights on the financial viability of HRES projects, which has not been
assessed in previous techno-economic studies.

2. Methodology

The methodology section is organized as follows. First, the process of selecting representative islands was
explained. Second, the modeling of the islands was discussed, Third, the techno-economic modeling
parameters were shown. Lastly, the profitability metrics used to assess the islands were presented.

2.1 Island selection 

A list of Philippine off-grid islands and their corresponding peak power demand was generated so that off-grid
islands with representative electrical demands could be identified. An initial list of islands was formed based on
Google Maps™ and Bing Maps™. The list was then refined by removing wholly touristic islands identified by 

the Department of Tourism and grid-connected islands according to NPC-SPUG. Stilts, shallow communities,
and non-residential islands were identified based on satellite images from Google Maps™ and were also 
removed. This yielded a list of 634 Philippine off-grid islands.
Next, the peak power demand of each island was determined. Some islands had available electrical demand
data from NPC-SPUG. For the other islands, however, a correlation between peak demand and island
population was utilized. The island population was estimated by multiplying the island area determined via
geographic information systems (GIS) mapping and the population density given by the Population Density
Maps from Facebook™. The correlation was then developed by determining the proportionality constant 

between the known peak demands of some islands and their corresponding population.
Based on the resulting peak power demands, the islands can be categorized into very small (1-10 kW), small
(10-100 kW), medium (100-1000 kW), and large (1-10 MW). For a representative case study, the island in the
median of each interval was selected. These islands were Patongong Island, Lapinigan Island, Balabac Island,
and Sibuyan Island with peak loads of 4.42 kW, 32.5 kW, 206 kW, and 3.20 MW, respectively.

2.2 Scenario modeling 

Two scenarios were considered in this study to better analyze the installation of HRES in off-grid islands. First,
a diesel-only scenario was simulated wherein the electrical demand in each island was satisfied by diesel
generators only. This is representative of the status quo in Philippine off-grid islands. Second, the HRES
scenario was examined. The HRES consisted of solar PV, wind turbines, Li-ion, and diesel generators.
The scenarios were modeled in ISLA, an energy systems optimization software. ISLA determines the sizes (i.e.,
power or energy ratings) of each component such that the net present cost (NPC) was minimized under the
constraint that the electrical load is continuously served. It also calculates other techno-economic metrics such
as the levelized cost of electricity (LCOE), renewable energy share (RE-Share), CO2 emissions, and capital
costs. Details regarding the operation of ISLA can be found in a previous publication (Castro et al., 2020).

2.3 Techno-economic data 

The optimization in ISLA will require the load profile, global horizontal irradiance (GHI), and wind speeds in each
island, as well as techno-economic parameters describing each component. The load profiles were obtained by
multiplying the peak demand with the normalized profiles reported by Bertheau and Blechinger (2018). The
monthly average GHI and wind speeds at 10 m were obtained from the Phil-LIDAR database. The hub heights
of the wind turbines were also at 10 m, so no wind speed corrections were necessary. The techno-economic
assumptions used in this work are presented in Table 1.

428



Table 1: Techno-economic modeling parameters used as input in ISLA. 

Component Parameter Value Ref. Component Parameter Value Ref.
Solar PV CapEx [USD/kW] 1,500 [a] Diesel CapEx [USD/kW] 500 [b]

OpEx [USD/kW·y] 15 [a] OpEx [USD/kW·y] 20 [b]
Lifetime [y] 20 [a] OpEx [USD/kWh] 0.02 [b]

Wind CapEx [USD/kW] Size-dependent Lifetime [y] 10 [c]
OpEx [USD/kW·y] 1 % of CapEx Fuel Cost [USD/L] 0.9 [c]
Lifetime [y] 20 [a] CO2 emissions [kg/L] 2.67 [c]

Li-ion CapEx [USD/kWh] 700 [a] Project CapEx [USD] 0 [a]
OpEx [USD/kWh·y] 5 [a] Discount rate [%] 8 [a]
Lifetime [y] 10 [a] Lifetime [y] 20 [a]

[a] (Bertheau, 2020) [b] (Bertheau & Cader, 2019) [c] (Ocon & Bertheau, 2019)

The per-kW capital cost of wind turbines was lower for larger units based on a review of commercially available
turbines, as shown in Figure 1. Small installations below 31.6 kW cost 7900 USD/kW, medium installations from
31.6 kW to 316 kW cost 5700 USD/kW, and large installations above 316 kW cost 1,300 USD/kW.

Figure 1: Per-kW capital cost of wind turbine vs. size of wind turbine. 

It should also be noted that Balabac Island and Sibuyan Island have existing diesel generator capacities of
486 kW and 2.96 MW, respectively. These were assumed to have zero capital costs in both scenarios. It is
possible to install an additional diesel generator in these islands, but this will incur capital costs. This analysis
also quantifies CO2 emissions solely during operation, so only the emissions of diesel generators were
considered.

2.4 Profitability metrics 

The financial viability of the HRES projects was assessed based on the net present value (NPV), internal rate
of return (IRR), and payback period (PBP). The NPV is defined as the sum of all discounted cash flows, as given
by Eq(1) (Lee et al., 2016). A positive value of the NPV indicates that the project is profitable. The IRR is the
discount rate at which the NPV becomes zero, as shown in Eq(2) (Lee et al., 2016). This quantifies the growth
rate of the investment, so investors are likely to choose projects with a higher IRR. The PBP is the time required
for the project to break even, as given by Eq(3) (Novaes Pires Leite et al., 2019). A shorter PBP is preferrable
as investors can recover their investment within a shorter timeframe.

NPV = ∑
𝐶(𝑛)

(1 + 𝑑)𝑛

𝑁

𝑛=0

(1)

∑
𝐶(𝑛)

(1 + IRR)𝑛

𝑁

𝑛=0

= 0 (2)

∫
𝐶(𝑛)

(1 + 𝑑)𝑛
 𝑑𝑛

PBP

0

= 0 (3)

429



The revenue of the HRES projects is assumed to depend on the electricity rate. The mainland rate of
0.2 USD/kWh was considered as the base case, and a sensitivity analysis from 0.1 USD/kWh to 0.3 USD/kWh
was performed afterwards.

3. Results and discussion

This section is divided into four parts. First, the transition from a diesel-only to a HRES scenario is discussed.
Second, the techno-economic metrics of the optimized HRES systems in the off-grid islands are presented.
Third, the profitability of the HRES systems is assessed. Lastly, a sensitivity analysis of the profitability with
respect to electricity prices is conducted.

3.1 Diesel to HRES transition 

A comparison between the techno-economic metrics of diesel-only and HRES systems is presented in Table 2.
The transition to HRES was generally beneficial for off-grid islands. The lower LCOE indicated lower generation
costs, while the decreased CO2 emissions suggested a cleaner source of electricity. The normalized NPV
represents the per-kWh profit, so a negative value implies that a per-kWh subsidy equal to the absolute value
of the normalized NPV is required. In this regard, the transition to HRES also decreased the subsidy
requirements and even made large islands profitable. The transition, however, was marked by a sharp increase
in capital costs due to the installation of RE technologies. This can discourage HRES transition in marginalized
communities, so strategies for mitigating capital costs should be employed (Mohapatra et al., 2019).

Table 2: Techno-economic metrics of diesel-only and HRES scenarios at a 0.2 USD/kWh electricity rate 

Island LCOE [USD/kWh] CapEx* [USD/kWh] CO2† [kg/y·kWh] NPV* [USD/kWh]
Diesel HRES Diesel HRES Diesel HRES Diesel HRES

Sibuyan (L) 0.270 0.183 0.0044 0.0675 0.695 0.263 -0.3408 +0.01714
Balabac (M) 0.286 0.222 0.0009 0.0679 0.736 0.355 -0.3721 -0.02194
Lapinigan (S) 0.296 0.268 0.0170 0.0529 0.727 0.540 -0.3933 -0.06856
Patongong (VS) 0.296 0.261 0.0170 0.0549 0.727 0.510 -0.3933 -0.06077
*Normalized by the energy generated during entire lifespan. †Normalized by annual energy generated.

3.2 Techno-economic metrics 

The techno-economic metrics of the cost optimum HRES in each island are presented in Table 3. The larger
islands were more dependent on RE as indicated by the larger proportion of solar PV and wind sizes, higher
RE-Share, and lower CO2 emissions. The RE-dependent systems in larger islands had lower LCOEs than the
diesel-dependent systems in smaller islands, which is consistent with the results of other researchers (Ocon &
Bertheau, 2019). As for smaller islands, the prohibitively high cost of small wind turbines contributed to a higher
LCOE, lower RE-Share, and increased CO2 emissions. The lower dependence on RE, however, resulted in
lower capital costs. This is advantageous for small islands, which are typically home to marginalized
communities (Meschede et al., 2019) deterred by high capital costs (Mohapatra et al., 2019).

Table 3: Techno-economic metrics of the cost optimum HRES in the islands 

Island Solar PV
[kW]

Wind
[kW]

Li-ion
[kWh]

Diesel*
[kW]

LCOE
[USD/kWh]

RE-Share
[%]

CO2†
[kg/y·kWh]

CapEx‡
[USD/kWh]

Sibuyan (L) 2,100 4,899 700 1,400 0.183 63.3 0.263 0.0675
Balabac (M) 224.8 359.6 89.9 0 0.222 53.9 0.355 0.0679
Lapinigan (S) 28.45 0.00 3.56 42.68 0.268 27.1 0.540 0.0529
Patongong (VS) 3.868 0.000 0.967 5.801 0.261 31.1 0.510 0.0549
*Additional diesel capacity. †Normalized by annual energy generated. ‡Normalized by the energy generated

during entire lifespan.

3.3 Profitability metrics 

The NPV, IRR, and PBP of the cost optimum HRES under the mainland electricity rate (0.2 USD/kWh) are
shown in Table 4. Among the selected islands, only the largest island was profitable. This is evident in the
portfolio of energy project developers in the Philippines, which often consists of MW-scale projects in large
islands. For instance, the Culna Renewable Energy Corporation (CREC) project also aimed to install a 2.8 MW
solar PV, 4.8 MWh battery, and 2.4 MW diesel system in Culion Island (WERenewables, 2017). While the NPV
of the HRES in the large island is positive, the IRR and PBP suggest that it is not necessarily a good investment.
The IRR is close to the 8 % discount rate, which indicates a slow growth of the investment. This is supported by

430



the long PBP, which is already more than 60 % into the lifespan of the project. As for the other islands, the
magnitude of the normalized NPV indicates the subsidies required per kWh of electricity generated. The medium
island is easier to subsidize than the very small and small islands.

Table 4: Profitability metrics of the cost optimum HRES in the islands at a 0.2 USD/kWh electricity rate 

Island NPV
[103 USD]

IRR
[%]

PBP
[y]

Norm. NPV*
[USD/kWh]

Sibuyan (L) +2,720 11.36 13.3 +0.01714
Balabac (M) -280.3 -0.02194
Lapinigan (S) -86.20 -0.06856
Patongong (VS) -10.39 -0.06077
*Normalized by the energy generated during entire lifespan.

3.4 Sensitivity analysis 

The net present revenue (NPR), IRR, and PBP of the cost optimum HRES under electricity rates from
0.1 USD/kWh to 0.3 USD/kWh are shown in Figure 2. At the 0.25 USD/kWh price point, the medium island
became profitable, although the 13 % IRR and 9-year PBP may not be attractive to investors. The large island,
however, gained a 20 % IRR and 6-year PBP, which is a notable improvement over the IRR and PBP at the
mainland rate. The small and very small islands become profitable only at the 0.30 USD/kWh price point. The
IRR and PBP are decent, however, investors may opt to invest in the large and medium islands instead.

Figure 2: NPR (left), IRR (middle), and PBP (right) of the cost optimum HRES at electricity rates from 

0.1 USD/kWh to 0.3 USD/kWh. NPV = NPR-NPC, so the project is profitable when the NPR surpasses the NPC. 

4. Conclusions

In this work, techno-economic case studies and profitability analyses were conducted on representative
Philippine off-grid islands to determine if these can be electrified without subsidies. The transition from a
diesel-only scenario to HRES is economically and environmentally favorable. The techno-economic case
studies suggest that larger islands have a higher dependence on RE and lower LCOE, which is in line with the
findings of other researchers. This is attributed to the low cost of large wind turbines. In contrast, smaller islands
depend more on diesel generators for electricity. This results in a high LCOE, but the decreased capital cost
requirements are favorable for the marginalized communities in these islands.
The profitability analysis suggests that large islands will not require subsidies at the mainland electricity rate of
0.2 USD/kWh. The profitability of large islands is consistent with the fact that energy project developers have
invested in MW-scale projects in off-grid islands. The IRR and PBP, however, suggest that large islands are a
poor investment at the mainland rate. Increasing the electricity rate to 0.25 USD/kWh alleviates the low IRR and
high PBP in large islands and even makes medium islands profitable. Only at 0.30 USD/kWh do the very small
and small islands become profitable, but this is already much larger than the 0.10 USD/kWh subsidized rate
that off-grid island residents currently pay for electricity.
This study serves as a guide to project developers who want to invest in off-grid islands. This is also a call to
the government to rationalize the UCME scheme as subsidies are still necessary in small islands with
marginalized communities. Likewise, innovations and strategies for reducing subsidy requirements should be
sought after. Future work will involve extending the techno-economic case studies and profitability analysis to
all 634 off-grid islands identified in this study, rather than just the representative islands.

431



Nomenclature

𝐶(𝑛) – nominal cash flow at year 𝑛, y
𝑑 – discount rate, -

𝑁 – project lifetime, y

Acknowledgements 

M.T.C. would like to acknowledge the Engineering Research and Development for Technology (ERDT)
Graduate Scholarship. J.D.O. would like to acknowledge the ElectriPHI Program funded by the University of the
Philippines Office of the Vice-President for Academic Affairs, and the CIPHER Project (IIID-2018-008) funded
by The Commission on Higher Education – Philippine California Advanced Research Institutes (CHED-PCARI),
The Republic of the Philippines.

References 

Aziz A.S., Tajuddin M.F.N., Adzman M.R., Azmi A., Ramli M.A.M., 2019, Optimization and sensitivity analysis
of standalone hybrid energy systems for rural electrification: A case study of Iraq, Renewable Energy, 775–
792.

Bertheau P., 2020, Supplying not electrified islands with 100% renewable energy based micro grids: A
geospatial and techno-economic analysis for the Philippines, Energy, 202, 117670.

Bertheau P., Cader C., 2019, Electricity sector planning for the Philippine islands: Considering centralized and
decentralized supply options, Applied Energy, 251, 113393.

BusinessWorld., 2019, DoE policy points to end of missionary electrification charge,
<https://www.bworldonline.com/doe-policy-points-to-end-of-missionary-electrification-charge/> accessed
03.02.2021.

Castro M.T., Alcanzare M.T., Esparcia E.A., Ocon J.D., 2020, A comparative techno-economic analysis of
different desalination technologies in off-grid islands. Energies, 13

Infranco Asia., n.d., Palawan Solar Hybrid Power, <https://infracoasia.com/our-portfolio/palawan-solar-hybrid-
power/> accessed 03.02.2021.

Lee J., Chang B., Aktas C., Gorthala R., 2016, Economic feasibility of campus-wide photovoltaic systems in
New England, Renewable Energy, 99, 452–464.

Manoj Kumar N., Chopra S.S., Chand A.A., Elavarasan R.M., Shafiullah G.M., 2020, Hybrid renewable energy
microgrid for a residential community: A techno-economic and environmental perspective in the context of
the SDG7, Sustainability (Switzerland), 12, 1–30.

Meschede H., Esparcia E.A., Holzapfel P., Bertheau P., Ang R.C., Blanco A.C., Ocon J.D., 2019, On the
transferability of smart energy systems on off-grid islands using cluster analysis – A case study for the
Philippine archipelago, Applied Energy, 251, 113290.

Mohapatra D., Jaeger J., Wiemann M., 2019, Private Sector Driven Business Models for Clean Energy Mini-
Grids, Alliance for Rural Electrification, Brussels, Belgium.

Novaes Pires Leite G.de Weschenfelder F., Araújo A.M., Villa Ochoa Á.A., Franca Prestrelo Neto N.da Kraj A.,
2019, An economic analysis of the integration between air-conditioning and solar photovoltaic systems,
Energy Conversion and Management, 185, 836–849.

Ocon J.D., Bertheau P., 2019, Energy Transition from Diesel-based to Solar Photovoltaics-Battery-Diesel Hybrid
System-based Island Grids in the Philippines – Techno-Economic Potential and Policy Implication on
Missionary Electrification, Journal of Sustainable Development of Energy, Water and Environment Systems,
7, 139–154.

Schmidt O., Hawkes A., Gambhir A., Staffell I., 2017, The future cost of electrical energy storage based on
experience rates, Nature Energy, 2, 1–8.

WERenewables., 2017, Culina Renewable Energy Corporation. <www.werenewables.com/projects/culna-
renewable-energy-corporation-crec/> accessed 03.02.2021.

World Bank, 2020, Access to electricity (% of population) - Philippines,
<https://data.worldbank.org/indicator/EG.ELC.ACCS.ZS?locations=PH> accessed 03.02.2021.

432