id	author	title	date	pages	extension	mime	words	sentence	flesch	summary	cache	txt
ajceb-4214	Ramachandra, Thanuja; Rotimi, James Olabode Bamidele	Causes of Payment Problems in the New Zealand Construction Industry	2015	13	.pdf	application/pdf	6928	336	47	Chain payment, work first get paid later .73 5 Cash flow difficulties due to delays and non-payments on other projects .54 6 Others (2.67% of variance) Improper supervision and financial control .538 Conclusions Unlike previous studies that focused on the generic factors causing payment delays on construction projects, this study focused on the underlying factors causing payment problems, with the aim of devising ways of mitigating payment problems. Accordingly, the study found that payment problems mainly relate to contractual issues, financial strength of industry players, disputes, short-comings of payment processes and ‘domino effects’.	cache/ajceb-4214.pdf	txt/ajceb-4214.txt