Engineering, Technology & Applied Science Research Vol. 7, No. 3, 2017, 1670-1675 1670  
  

www.etasr.com Naderpour et al.: Application of Fuzzy Expert Systems to Manage the Projects Time in Iranian Gas Refineries 

 

Application of Fuzzy Expert Systems to Manage the 
Projects Time in Iranian Gas Refineries 

 

Abbas Naderpour 
Department of Civil Engineering 

Islamic Azad University  
Central Tehran Branch, Iran  

Aba.Naderpour.eng@Iauctb.ac.ir 

Javad Majrouhi Sardroud 
Department of Civil Engineering 

Islamic Azad University  
Central Tehran Branch, Iran  
J.Majrouhi.eng@Iauctb.ac.ir 

Masood Mofid 
Department of Civil Engineering 
Sharif University of Technology 

Tehran, Iran  
Mofid@Sharif.edu 

 

 
Abstract-The National Iranian Gas Company (NIGC) is one of the 
top ten gas companies in the gas industry in the Middle East and 
is comprised of 7 gas refineries. So this company needs to apply 
the most optimum time management methods to achieve its goals. 
Custom scheduling calculation of project planning uses the 
Critical Path Method (CPM) as a tool for Planning Projects 
activities. CPM is now widely used in planning and managing 
projects but in spite of its wide application, this method has a 
critical weak point of not taking into account the uncertainties in 
scheduling calculation. This article aims to present a precise 
method based on the application of Fuzzy Expert Systems in 
order to improve the Time Estimation Method in construction 
projects and in this regard, reviews the results of the 
implementation of this method in construction projects of Iranian 
Gas Refineries. The results show that the proposed method 
increases the accuracy of time estimation about 7 to 22 percent. 

 
Keywords-Critical Path Method; Fuzzy Expert Systems; 

Uncertainty; Time Estimation Method 

I. INTRODUCTION  
Time management can be effective in a project when the 

project schedule is based on reasonable and comprehensive 
time estimation. In industries with complex processes such as 
gas refineries, considering limitations and risks involved in the 
project implementation and also many uncertainties that affect 
the project activities, the importance of the time management is 
great. As the ongoing projects are directly or indirectly linked 
with continuous production in gas refineries, operational 
condition and site classification based on the HSE risks, 
increases more uncertainties to the project schedule. 
Considering the very low reliability of planning with certainty 
and project control by this approach, using more secure 
methods for control and interaction with uncertainty is to be 
placed on the agenda. This article presents a method for 
implementing an extended method of CPM based on the 
application of fuzzy expert systems (FCPM) to manage 
schedule uncertainties in Iranian gas refinery projects. The 
concept of FCPM is explained by a real and applicable 
example and then, the proposed model and the method of its 
implementation in projects will be described. 

II. FUZZY CRITICAL PATH METHOD (FCPM) 
FCPM is an extension of Critical Path Method in terms of 

fuzzy approach. In this method, fuzzy function defines the time 
of project activities to manage their uncertainties. For 
understanding the main concepts of FCPM, consider the project 
network indicated in Figure 1. This project network is a part of 
a small one-story building construction planning that contained 
excavation, concreting and installing the building structures. 
The resistance system against the earthquake is A.D.A.S 
bracing.  The description of all activities regarding the 
mentioned project is presented in Table Ι. 

 

 
Fig. 1.  CPM of small one-story building construction 

 

As it could be seen from Table Ι, 10 out of whole 11 
activity times have triangular fuzzy type format and only the 
remaining one (related to A.D.A.S braces) is in trapezoidal 
form. Equations (1) to (8) represent the stages of FCPM 
calculations of the project network. The calculations indicate 
that the project total time is the maximum of three fuzzy 
numbers (Eq.8). Consequently, in order to determine the 
project time, it is necessary to rank the fuzzy numbers and 
select the maximum. 

FES1 = (0, 0, 0) + (1, 2, 4) = (1, 2, 4) (1) 



Engineering, Technology & Applied Science Research Vol. 7, No. 3, 2017, 1670-1675 1671  
  

www.etasr.com Naderpour et al.: Application of Fuzzy Expert Systems to Manage the Projects Time in Iranian Gas Refineries 

 

FES2 = (0, 0, 0) + (1, 5,10) = (1, 5,10) (2) 

FES3 = (0, 0, 0) + (1, 2, 3) = (1, 2, 3) (3) 

FES5 = (0, 0, 0) + (2,14,18) = (2,14,18) (4) 

FES4 = Max ((1, 2, 4) + (2 , 3 ,4) , (1, 4,10) 

  + (1, 2, 3) , (1, 2, 3) + (1, 2, 3)) = (2, 6,13) 
(5) 

    FES6 = (2, 6,13) + (3, 4, 5) = (5 ,10,18) (6) 

FES7 = Max ((5,10,18) + (4, 5, 9), (2,14,18) 

  +(1, 4, 6), (0, 12, 21, 24)) 
(7) 

FES7 = Max ( A , B, C)  St: A= (9, 15, 27) ; 

B= (3, 18, 24) & C =(0, 12, 21, 24) 

 

(8) 

The calculations indicate that the project total time is the 
maximum of three fuzzy numbers (8). Consequently, in order 
to determine the project time, it is necessary to rank the fuzzy 
numbers and select the maximum. Since fuzzy numbers do not 
form a natural linear order (similar to real numbers) a key issue 
in applications of fuzzy set theory is how to compare fuzzy 
numbers. Various approaches have been developed for ranking 
fuzzy numbers up to now. Initially a method using the concept 
of maximizing set to order the fuzzy numbers was proposed in 
[1]. In [2] four indices which may be employed for the purpose 
of fuzzy ranking were introduced. In [3], an index for ordering 
(ranking) fuzzy numbers was proposed. In [4] a new method of 
fuzzy numbers ranking with integral value was described. 

In [5], fuzzy sets were ranked based on the concept of 
existence of vibration frequencies. In [6] a new approach for 
ranking fuzzy numbers by distance method was proposed. In 
[7], ranking alternatives with fuzzy weights by maximizing and 
minimizing set was introduced. A new methods for ranked 
fuzzy sets was described in [8]. In [9], authors ranked fuzzy 
numbers with an area between centroid point and original point 
while in [10] authors used fuzzy distance measure for fuzzy 
numbers comparison in the same year. In [11], authors 
proposed another fuzzy ranking method based on distance 
method. In [12], authors ranked fuzzy numbers by sign 
distance. In [13], authors ranked fuzzy numbers by distance 
minimization. In [14], authors ranked trapezoidal fuzzy 
numbers with integral value. In [15], authors published the 
result of their research about fuzzy ranking. In [16], authors 
ranked fuzzy numbers with an area method using a radius of 
gyration in torsion stiffness. In [17], authors ranked trapezoidal 
fuzzy numbers based on mode, spread, and weight. In [18], 
authors improved the ranking method for fuzzy numbers based 
on centroid-index. In [19], authors proposed a new method 
based on angle measure and finally in [20] a new 
lexicographical approach for ranking fuzzy numbers was 
proposed. 

For ranking the three fuzzy numbers of (8), five methods 
were considered. Table II shows the results of this ranking and 
Figure 2 compares the results in bar charts. Also, the project 
total time and critical path for each method are indicated in 
Table III. 

TABLE I.  THE  PROJECT  INFORMATION  OF ACTIVITIES 

Activity Activity Description Time (days) 
0 - 1 Steel Bars Cutting (1, 2, 4) 
0 - 2 Excavation (1, 5, 10) 
0 - 3 Base Plate Making (1, 2, 3) 
0 - 5 Making the Beams (2, 14, 18) 

0 - 7 Making & Installation of A.D.A.S braces (0, 12, 21, 24) 

5 - 7 Installing the Beams (1, 4, 6) 
1 - 4 Making Reinforce Cage (1, 2, 3) 
2 - 4 Foundation Forming (1, 2, 3) 
3 - 4 Base Plate Installation (1, 2, 3) 
4 - 6 Concreting (3, 4, 5) 

6 - 7 Columns Making and Installation (4, 5, 9) 

TABLE II.  RESULTS OF FUZZY RANKING BY 5 METHODS  

Fuzzy Ranking 
Method 

Result of Ranking Method Calculation 
A B C Result 

Choobineh & Li 17.5 18.33 15 18.33 C < A < B 
Yager 15.75 16.5 13.5 16.5 C < A < B 

Cheng 21.77 21.72 21.32 21.77 C < B < A 
Chen 

& Sanguansat 17.1 18.75 15.6 18.75 C < A < B 

Abbasbandy 
& Hajjari 15.75 15.73 14.25 15.75 C < B < A 

TABLE III.  RESULTS OF PROJECT CRITICAL PATH  

Fuzzy Ranking Method Project Critical Path project time (days) 

Choobineh & Li 0 – 5 – 7 18.33 
Yager 0 – 5 – 7 16.5 
Cheng 0 – 2 – 4 – 6 - 7 21.77 

Chen & Sanguansat 0 – 5 – 7 18.75 
Abbasbandy & Hajjari 0 – 2 – 4 – 6 - 7 15.75 

 

 
Fig. 2.  Project time calculation by various fuzzy ranking methods 

According to the results of FCPM calculations, selecting 
the fuzzy ranking method for project scheduling has a great 
influence on the determination of project total time and critical 
path. As a result, a suitable fuzzy ranking method, compatible 



Engineering, Technology & Applied Science Research Vol. 7, No. 3, 2017, 1670-1675 1672  
  

www.etasr.com Naderpour et al.: Application of Fuzzy Expert Systems to Manage the Projects Time in Iranian Gas Refineries 

 

to project nature should be considered by project management 
team. 

III. FUZZY TIME ESTIMATION 
Several methods have been proposed for finding the fuzzy 

time management. The main common topic in all of these 
methods is converting the classic time of project activities to 
fuzzy numbers for schedule calculation. For the reason that 
CPM calculation needs to compare the time of activities to 
determining critical path, ranking of fuzzy numbers is 
necessary. Consequently, fuzzy numbers ranking is the most 
important factor in these methods. In [21], authors introduced 
the preliminary concept of Fuzzy CPM. They presented the 
time of project activities by fuzzy set in the time space. Their 
method provides more direct processing verbally expressed 
opinions of experts. The significant problem not quite solved in 
their method was the question of deriving membership 
functions for activity duration times. In [22] algebraic operators 
were used to estimate the time of project activities and project 
critical path. In [23] a way to to compute total floats and find 
critical paths in a project network by the fuzzy approach was 
described. In [24], a methodology to calculate the fuzzy 
completion project time was presented and in [25] an extension 
of fuzzy schedule networks was proposed. New methods were 
recently introduced in [26]. They proposed a method for 
ranking fuzzy numbers without the need for any assumptions 
and used both positive and negative values to define ordering 
which is applied to CPM.  

In [27], authors presented an approach to the critical 
concept in a network with fuzzy activity times. In [28], a 
taxonomy of fuzzy graphs that treated fuzziness in vertex 
existence, edge connectivity and edge weight was presented. In 
[29], a new approach to implementing a fuzzy CPM for activity 
networks based on statistical confidence interval estimates and 
a ranking method for level fuzzy numbers was introduced. In 
[30], authors presented an algorithm to perform fuzzy critical 
path analysis for project network problem. In [31], authors 
presented another method to calculate fuzzy critical paths and 
critical activities and activity delays and in [32] authors 
extended some results for interval numbers to the fuzzy case 
for determining the possibility distributions to describe latest 
starting time of activities. In [33], authors proposed an 
approach based on the extension principle and linear 
programming (LP) formulation to critical path analysis in 
networks with fuzzy activity durations. In [34], authors 
introduced the problems of determining possible values of 
earliest and latest starting times of an activity in networks with 
minimal time lags and imprecise durations that are represented 
by means of the interval of fuzzy numbers. In [35], authors 
proposed a new approach based on fuzzy critical path 
calculation. They used fuzzy arithmetic and the fuzzy ranking 
method to determine the fuzzy critical path of the project 
network without converting the fuzzy activity times to classical 
numbers and compared their method with other methods. In 
[36], authors proposed a new method of fuzzy critical path 
analysis based on the centroid of centroids of fuzzy numbers 
and in [37] authors proposed new algorithms identify the 
critical path in a fuzzy environment of project network.. 

 

IV. PROPOSED FUZZY BASE METHOD 
The uncertainties that must be managed in each project are 

categorized into two main groups; the First group includes 
probable uncertainties which are managed by risk management 
and the second group covers non-probable uncertainties that are 
related to project nature and its complexity. Many industries, 
such as gas refineries manage probable uncertainties in their 
projects by risk management but in the field of non-probable 
uncertainties, actions are very scarce. This article considers the 
managing of non-probable uncertainties in gas refineries 
projects. The diagram of proposed model is shown in Figure 3. 
 

 

 
Fig. 3.  Diagram of the proposed model 

For implementing the models, at first, two professional 
questionnaires were distributed between a professional team 
which was selected by the staff of 70 contractors, consultant 
and employer companies. The first questionnaire was designed 
to identify effective factors such as site organization, weather, 
labor skills and quality of equipment on doing project 
activities. Then obtained Linguistic variables were translated 
into mathematical measures. For instance, the questionnaire 
was designed for excavation activity is presented in Table IV. 

TABLE IV.  QUESTIONNAIRE OF EXCAVATION ACTIVITY 

Please determine the effect of each factor in the time of excavation 
Activity.   

1- Excavation Equipment (Hand Tools, loader, Backhoe, Excavator, Dozer) 
Very Poor  Poor  Medium  High  Very High  
2- Climatic Condition (Very Warm, Warm, Moderate, Cold, Very Cold) 
Very Poor  Poor  Medium  High  Very High  
3- HSE Criteria (Classification of site in Operational Zones) 
Very Poor  Poor  Medium  High  Very High  
4- Classification of Rock (Earthy, Soft, Moderate, Hard, Very Hard) 
Very Poor  Poor  Medium  High  Very High  
5- The level of underground water in Meter (>15, 10-15, 5-10, 1-5, <1) 
Very Poor  Poor  Medium  High  Very High  
6- Depot Distance in Meter (>10000,1000-10000, 500-1000, 100-500,<100) 
Very Poor  Poor  Medium  High  Very High  
7- Depth of Excavation in Meter (>15, 10-15, 5-10, 1-5, <1) 
Very Poor  Poor  Medium  High  Very High  
8- years of driver Experience of (>20, 15-20, 10-15, 5-10, <5) 
Very Poor  Poor  Medium  High  Very High  

 



Engineering, Technology & Applied Science Research Vol. 7, No. 3, 2017, 1670-1675 1673  
  

www.etasr.com Naderpour et al.: Application of Fuzzy Expert Systems to Manage the Projects Time in Iranian Gas Refineries 

 

As it can be seen in Table IV, the value of the Linguistic 
variables is classified into 5 types (Figure 4). As it could be 
seen in Table IV, a large number of factors are considered to 
estimate the time of excavation activity. To examine the 
reliability of the questionnaire, data analysis was done by 
SPSS. The results of this analysis are shown in Table V. 
According to SPPS analysis, the Cronbach's alpha (Reliability 
Index) was 0.387, while it should be greater than 0.7. The 
results show that factors 2, 3, 5, 6 and 8 do not have an 
effective influence on the timing of excavation activity. So 
these factors were eliminated and the calculations were 
repeated. In the new analysis, the index rose up to 0.888 which 
is desirable. So the main factors of excavation activity are 
Excavation Equipment, Classification of Rock and Depth of 
Excavation. In the next step, the second questionnaire which 
relates to estimating activity durations was distributed among 
team members. After summing up the results of the first and 
second questionnaires, obtained results were examined by a 
team of experts (composed of 8 expert project managers) to 
determine its content validity. Then, according to satisfactory 
results, the structural validity of survey questionnaires was 
evaluated by Factor Analysis method. According to the KMO 
index, the acceptable construct validity of research was 
approved. The analysis results are summarized in Table VI. 
Also, the results of the total variance of analysis explained that 
these three factors are not reducible to the number of agent-less 
(Table VII). 

 

 
Fig. 4.  The value of the linguistic variables classification 

TABLE V.  RESULTS OF RELIABILITY INDEX CALCULATED BY SPSS 

 Scale Mean if Item Deleted 
Scale Variance 
if Item Deleted

Total 
Correlation 

Cronbach's 
Alpha if Item 

Deleted 
S01 12.11 5.951 0.443 0.290 
S02 13.75 8.639 0.136 0.449 
S03 13.75 9.231 0.110 0.505 
S04 11.86 5.460 0.621 0.190 
S05 13.25 8.120 0.000 0.526 
S06 13.68 8.300 0.109 0.457 
S07 12.75 6.861 0.368 0.153 
S08 13.61 7.803 0.276 0.404 

TABLE VI.  THE RESULTS OF KMO TEST 

Kaiser-Meyer-Olkin Measure of Sampling Adequacy 0.692 

Bartlett's Test of Sphericity 
Approx. Chi-Square 13.522 

df 3 
Sig. 0.003 

 

TABLE VII.  THE RESULTS OF TOTAL VARIANCE  

Component Total Variance Explained Total % of Variance Cumulative %
1 1.823 46 46 
2 1.076 28 74 
3 1.041 26 100 

According to the results obtained from computing of the 
Pearson Correlation coefficient, the correlation between these 
factors is also desirable. Table VIII indicates related results. 

 

TABLE VIII.  THE RESULTS OF CORRELATION INDEX 

Correlation Results S01 S04 S07 

S01 
Pearson Correlation 1 0.910 0.576 

Sig. (2-tailed)  0.000 0.001 
N 28 28 28 

S04 
Pearson Correlation 0.910 1 0.511 

Sig. (2-tailed) 0.000  0.005 
N 28 28 28 

S05 
Pearson Correlation 0.576 0.511 1 

Sig. (2-tailed) 0.001 0.005  
N 28 28 28 

 
In later stages of the proposed model, membership 

functions of these factors were drawn according to the second 
questionnaire. The second questionnaire is about estimating the 
time of each activity based on the experience of the 
professional team. In this research, Fuzzy diagrams were of 
triangular and trapezoidal types. In the present example, 
Figures 5 to 7 indicate the Fuzzy membership functions of 
excavation activity factors. These diagrams are considered as 
the input of analysis. 

 

 
Fig. 5.  Fuzzy membership of excavation equipment factor 

 

 
Fig. 6.  Fuzzy membership of classification of rock factor 

 

 
Fig. 7.  Fuzzy membership of excavation depth factor 

Then the results of the previous step as input were analyzed 
in Fuzzy Toolbox of MATLAB. This toolbox follows a Rule 
Base System. Analysis of model is presented in Figure 8. As it 



Engineering, Technology & Applied Science Research Vol. 7, No. 3, 2017, 1670-1675 1674  
  

www.etasr.com Naderpour et al.: Application of Fuzzy Expert Systems to Manage the Projects Time in Iranian Gas Refineries 

 

can be seen in Figure 8, inputs are processed by a smart and 
rule base system. 

 

 
Fig. 8.  A pictorial view of analysis model in MATLAB 

“IF …Then …” rules were set by the expert team in Rule 
Base system. For example, for these three factors, about 125 
operating modes may occur. Three states of these rules are 
observed in Table IX and Software environment can be seen in 
Figure 9. 

TABLE IX.  AN EXAMPLE OF ANALYSIS RULES  

Rule No The Rule 

Rule 1 
If Excavation Equipment is a Dozer and Classification of 
Rock is Very Hard and Depth of Excavation is more than 15 
meter ThenThe Time of Excavation is Very Long. 

Rule 2 
If Excavation Equipment is a Backhoe and Classification of 
Rock is Soft and Depth of Excavation is Less than 1 meter 
ThenThe Time of Excavation is Very Short. 

Rule 3 
If Excavation Equipment is a Dozer and Classification of 
Rock is Hard Or Depth of Excavation is between1 to 5 meter 
ThenThe Time of Excavation is Moderate. 

 

 
Fig. 9.  A pictorial view of setting the rules in the software  

After analysis, the duration of activities under uncertainty 
and fuzzy approach can be achieved. For example, this time for 
an above-mentioned activity (Excavation) will be 4.5 days for 
each 200 cubic meters of concrete. (Figures 10-11). Finally, 
after calculating the time of all activities by this method, 
project schedule was run and the total time of project was 
calculated. 

 
 

 

Fig. 10.  A pictorial view of analysis output 

 
Fig. 11.  A pictorial view of MATLAB output diagram 

V. RESULTS 
The proposed model of the research has been implemented 

in one gas refinery in the North East of Iran. The study period 
was between 2014 and 2016 and the population of this study 
was composed of 30 projects by Cochran formula. The result of 
the research shows the estimated project duration is about 7 to 
22percent closer to actual time. Figure 12 indicates the percent 
of improvement in project time estimation. 

 

 
Fig. 12.  Diagram of improvement in project time estimation new method 

VI. CONCLUSION 
This study investigated a new method for precise time 

estimation in construction projects of the Iranian Gas 
Refineries. A gas refinery has a complicated process and 



Engineering, Technology & Applied Science Research Vol. 7, No. 3, 2017, 1670-1675 1675  
  

www.etasr.com Naderpour et al.: Application of Fuzzy Expert Systems to Manage the Projects Time in Iranian Gas Refineries 

 

ongoing projects are directly or indirectly linked with 
continuous production in this industry. Consequently managing 
the project time is a critical issue and considering the very low 
reliability of the project planning with certainty, using more 
secure models for control and interact with uncertainty is a 
necessity. It is obvious that successful project time 
management should be based on comprehensive time 
estimation. Therefore, considering the uncertainty in the 
estimation of project time is the main object. From the above 
discussion, the following conclusions were derived: 

1. Many industries, such as gas refineries manage probable 
uncertainties in their projects by risk management but in the 
field of non-probable uncertainties, actions are very scarce.   

2. This research considered the managing of non-probable 
uncertainties in gas refineries projects by a proposed 
method based on Fuzzy Critical Path Method.  

3. The result of the implementation of proposed method 
shows that the accuracy of project time estimation increases 
about 7 to 22 percent. Finally, due to successful results of 
this research, it has been suggested that the proposed 
method could be generalized to other industries projects. 

REFERENCES 
[1] R. Jain, “Decision-Making in the presence of fuzzy variables”, IEEE 

Transactions on Systems Man and Cybernetics, Vol. 6, pp. 698-703, 
1976  

[2] R. Yager, “A procedure for ordering fuzzy subsets of the unit 
interval”, Information Science, Vol. 24, pp. 143-161, 1981  

[3] F. Choobineh, H. Li, “An index for ordering fuzzy numbers”, Fuzzy 
Sets and Systems, Vol. 5, pp.1-19, 1985 

[4] S. L. Liou, M. J. Wang, “Ranking fuzzy numbers with integral 
value”, Fuzzy Sets, and Systems, Vol. 50, pp 247-255, 1992 

[5] P. T. Chang, E. S. Lee, “Ranking of Fuzzy Sets Based on the 
Concept of Existence”, Computers and Mathematics with 
Applications, Vol. 27, No 9, pp.1-21, 1994 

[6] C. H. Cheng, “A new approach for ranking fuzzy numbers by 
distance method”, Fuzzy Sets and Systems, Vol. 95, pp. 307-317, 
1998 

[7] P. A. Raj, A. Kumar, “Ranking alternatives with fuzzy weights 
using maximizing set and minimizing set”, Fuzzy Sets and Systems, 
Vol. 105, pp. 365-375, 1999 

[8] J. S. Yao, F. T. Lin, “Fuzzy critical path method based on signed 
distance ranking of fuzzy numbers”, IEEE Transactions on Systems, 
Man, and Cybernetics-Part A: Systems and Humans, Vol. 30, No 1, 
pp.76-82, 2000 

[9] T. C. Chu, C. T. Tsao, “Ranking fuzzy numbers with an area 
between the centroid point and the original point”, Computers and 
Mathematics with Applications, Vol. 43, pp.111-117, 2002.  

[10] L. Tran, L. Duckstein, “Comparison of fuzzy numbers using a fuzzy 
distance measure”, Fuzzy Sets and Systems, Vol. 130, pp. 331-341, 
2002 

[11] C. Lucas, B. Asady, “A new method for ranking of fuzzy numbers 
through using distance method”, Journal of Teacher Training 
University, Vol. 3, pp. 83-88, 2003 

[12] S. Abbasbandy, B. Asady “Ranking of fuzzy numbers by sign 
distance”, Information Sciences, Vol. 176, pp. 2405-2416, 2006 

[13] B. Asady, A. Zendehnam, “Ranking fuzzy numbers by distance 
minimization”, Applied Mathematical Modelling, Vol. 31, pp. 2589-
2598, 2007 

[14] C. Chen, H. Tang, “Ranking Non-Normal P-Norm Trapezoidal 
fuzzy numbers with integral value”, Computers and Mathematics 
with Applications, Vol. 56, pp. 2340-2346, 2008 

[15] S. Abbasbandy, T. Hajjari, “A new approach for ranking of 
trapezoidal fuzzy numbers”, Computers and Mathematics with 
Applications, Vol. 57, pp. 413-419, 2009 

[16] S. Chen, K. Sanguat, “Analyzing fuzzy risk analysis based on a new 
fuzzy ranking method between generalized fuzzy numbers”, Expert 
Systems with Applications, Vol. 38, pp. 2163-2171, 2011 

[17] P. Rao, N. Ravi Shankar, “Fuzzy critical path analysis based on 
centroid of centroids of fuzzy numbers and new subtraction 
method”, International Journal of Mathematics in Operational 
Research, Vol. 5, No. 2, pp. 205-224, 2013 

[18] L. Q. Dat, S. Y Chou, “An Improved Ranking Method for Fuzzy 
Numbers Based on the Centroid-Index”, International Journal of 
Fuzzy Systems, Vol. 14, pp. 413-419, 2012 

[19] M. Barkhordary Ahmadi, “Ranking of fuzzy numbers based on 
angle measure”, International Journal of Information, Security and 
System Management, Vol. 3, No 1, pp. 259-265, 2014 

[20] U. A. Sharma, “New lexicographical approach for ranking fuzzy 
numbers”, Mathematical Theory and Modeling, Vol. 5, No 2, pp. 
143-153, 2015 

[21] S. Chanas, J. Kamburowski, “The use of fuzzy variables in PERT”, 
Fuzzy Sets and Systems, Vol. 5, No 1, pp. 11-19, 1981 

[22] I, Gazdik, “Fuzzy network planning-FNET”, IEEE Transactions on 
Reliability, Vol. 32, No 3, pp. 304-313, 1981 

[23] S. H. Nasution, “Fuzzy critical path method”, IEEE Transactions on 
Systems, Man and Cybernetics, Vol. 24, pp. 48-57, 1994 

[24] S. Chang, Y. Tsujimura, T. Tazawa, “An efficient approach for 
large scale project planning based on fuzzy Delphi Method”, Fuzzy 
Sets and Systems, Vol. 76, pp. 277-288, 1995 

[25] P. Lorterapong, O. Moselhi, ”Project-network analysis using fuzzy 
sets theory”, Journal of Construction Engineering and Management, 
Vol. 122, pp. 308-318, 1996 

[26] J. S. Yao, F. T. Lin, “Fuzzy Critical path Method Based on Signed-
Distance Ranking and Statistical Confidence-Interval Estimates”, 
IEEE Transactions on Systems, Vol. 30, No. 1, pp. 76-82, 2000 

[27] S. Chanas, P. Zielinski, “Critical path analysis in the network with 
fuzzy activity times”, Fuzzy Sets and Systems, Vol. 122, pp. 195-
204, 2001 

[28] M. Blue, B. Bush, J. Puckett, “Unified approach to fuzzy graph 
problems”, Fuzzy Sets and Systems, Vol. 125, pp. 355-368, 2002 

[29] J. S. Yao, F. T. Lin, “Fuzzy critical path method based on signed 
distance ranking of fuzzy numbers”, The Journal of 
supercomputing, Vol. 24, pp. 305-325, 2003 

[30] G. S. Liang, T. C. Han, “Fuzzy critical path for project network”, 
Information and Management Sciences, Vol. 15, No 4, pp. 29-41, 
2004 

[31] A. Oliveros, A. Robinson, “Fuzzy Logic Approach for Activity 
Delay Analysis and Schedule Updating”, Journal of Construction 
and Management, Vol. 131, No. 1, pp. 42-51, 2005 

[32] S. Chanas, P. Zielinski, “Critical path analysis in the network with 
fuzzy activity times”, Fuzzy Sets and Systems, Vol. 122, pp. 195-
204, 2006 

[33] S. P. Chen, Y. J. Hsueh, “A simple approach to fuzzy critical path 
analysis in project networks, Applied Mathematical Modelling”, 
Vol. 32, No. 7, pp. 1289-1297, 2008 

[34] S. H. Yakhchali, S. H. Ghodsy Pour, “On latest starting times of 
activities in networks with imprecise durations and generalized 
precedence relations”, Applied Mathematical Modelling, Vol. 34, 
No. 8, pp. 2044-2058, 2010 

[35] S. Sathish, K.Ganessan, “A simple approach to fuzzy critical path 
analysis in project networks”, Journal of Scientific & Engineering 
Research, Vol. 2, No. 12, pp. 1-6, 2011 

[36] P. Rao, N. Ravi Shankar, “Fuzzy critical path analysis based on 
centroid of centroids of fuzzy numbers and new subtraction 
method”, International Journal of Mathematics in operational 
research, Vol. 5, No. 2, pp. 205-244, 2013 

[37] S. Elizabet, L. Sujatha, “Project Scheduling Method using 
Triangular fuzzy numbers and triangular fuzzy numbers”, Applied 
Mathematical Science, Vol. 9, No. 4, pp. 185-198, 2015