Microsoft Word - 18-2449_s


Engineering, Technology & Applied Science Research Vol. 9, No. 1, 2019, 3762-3764 3762  
  

www.etasr.com Soomro et al.: Causes of Time Overrun in Construction of Building Projects in Pakistan 

 

Causes of Time Overrun in Construction of Building 

Projects in Pakistan 
 

Faheem Ahmed Soomro 

Department of Civil Engineering, 

Mehran University of Engineering and 

Technology, Shaheed Zulfiqar Ali Bhutto 

Campus, Khairpur Mirs, Pakistan 

faheemahmed_soomro@yahoo.com 

Muhammed Jaffar Memon 

Department of Civil Engineering, 

Mehran University of Engineering and 

Technology, Shaheed Zulfiqar Ali Bhutto 

Campus, Khairpur Mirs, Pakistan 

 ja2far@gmail.com 

Abdul Fattah Chandio  

Department of Electronics Engineering, 

Quaid-e-Awam University of 

Engineering, Science & Technology, 

Nawabshah, Pakistan 

fattahchandio@yahoo.com 

Samiullah Sohu 

Department of Civil Engineering, Quaid-e-Awam University of 

Engineering, Science & Technology, Nawabshah, Pakistan 

sohoosamiullah@gmail.com 

Rizwanullah Soomro 

Faculty of Civil Engineering, 

Universiti Teknologi Malaysia 

rizwantn16@gmail.com 
 

 

Abstract—Time overrun in construction projects is a very serious 

issue in developed and developing countries. The main object of 

this research is to find the main causes of time overrun in the 

construction of building project and its possible mitigation 

measures. Quantitative approach was adopted in this research to 

achieve object and RIW (relative importance weight) approach 

was used for collecting data. Financial issues faced by the 

contractor, contractor’s inexperience, weather impacts, late 

delivery of material, mistakes in design, shortage of skilled labor, 

incompetent subcontractor and mistakes in time estimation were 

identified as main causes of time overrun in construction projects 

and possible mitigation measures were also proposed from 

experts. This research will help in giving awareness to 

stakeholders to narrow down the factors of time overrun in 

construction projects in Pakistan. 

Keywords-time overrun; causes; building projects; mitigation 

measures; Pakistan 

I. INTRODUCTION  

Time overrun is one of the most serious issues in 
construction industry globally [1]. “Construction time overrun 
is the change between a project’s actual contract period at the 
time of tender and its final contract period on which 
construction project finished” [2]. Time overrun can result in 
many negative impacts on the construction project like budget 
overrun, low productivity, contract expiration, work 
acceleration resulting in bad quality, and disputes among 
construction stakeholders [3]. It is observed that many 
construction projects face the issue of time overrun worldwide 
both in developing and developed countries like USA or UK 
[4, 5]. Authors in [6] stated that more than 40% of projects in 
construction industry experiences time overrun. Construction 
industry is not famous in terms of project completion within 
time. Ignorance of time overrun analysis resulted in many 
construction projects failing to complete on the given time 
frame [7]. According to [8] only 47% of projects were 

completed within approved time frame, around 38% of 
construction projects were behind time frame and 15% of 
construction projects were completed ahead of time in 
Indonesia. Like other countries, time overrun is one of the most 
severe problems in the construction industry of Pakistan [9, 
10]. Author in [11] reported that the majority of the Pakistan 
construction projects were 11% to 30% below their approved 
time fame. Only a few studies have been carried out to find 
factors of time overrun in the construction of building projects 
in Pakistan. 

II. PREVIOUS STUDIES 

Many researchers conducted studies on the causes of time 
overrun in different kinds of construction projects to find 
factors and causes of time overrun. Authors in [12] conducted 
survey on 130 randomly selected engineers. Identified causes 
of time overrun were delayed payments, material shortage, 
changes in selected material prices, poor site management, and 
problems in bank credit. Authors in [13] identified 83 common 
factors of time overrun and arranged these factors in 8 groups. 
By using relative importance index five causes of time overrun 
were identified which were poor supervision at site and site 
management, delay in making decisions, owner interference in 
the project, ground conditions, and necessary changes from the 
owner. Authors in [14] identified 16 causes of time overrun, the 
top 5 being: financial problems faced by the contractor, poor 
contract management, site supervision, lack of planning, and 
delay in material supply. Authors in [15] carried out a survey 
through questionnaire distribution to selected experts of 
construction industry in Nigeria. Identified causes of time 
overrun were inexperienced sub-contractors, shortage of labor, 
poor site management, shortage of selected materials and 
mistakes during works. Authors in [16] conducted survey about 
the causes of time overrun in infrastructure projects of Qatar. 
The results of the survey revealed that major causes of time 
overrun were design changes, inadequate planning and 

Corresponding author: S. Sohu



Engineering, Technology & Applied Science Research Vol. 9, No. 1, 2019, 3762-3764 3763  
  

www.etasr.com Soomro et al.: Causes of Time Overrun in Construction of Building Projects in Pakistan 

 

scheduling, changes in scope of project, inadequate estimation 
project time duration, and shortage of skilled labour. Authors in 
[17] identified the major causes of time overrun through 
quantitative approach in construction projects of Vietnam. The 
main causes of time overrun were poor monitoring, poor 
project management and financial problems faced by owner.  

III. RESEARCH METHODOLOGY 

This study was divided in two phases. In the first phase the 
objective was to find the main causes of time overrun and in 
the second phase was to find the mitigation measures of these 
identified causes. In the first phase, a literature review was 
carried out providing a total of 51 probable causes of time 
overrun. A questionnaire was developed, in which the 
aforementioned causes were imposed and respondents were 
asked to rank them. In the second phase, another questionnaire 
was distributed in which mitigation measures from literature 
review and unstructured interviews were incorporated. 

IV. DATA COLLECTION AND ANALYSIS  

For the first phase, the developed questionnaire was 
distributed among 131 professional respondents (either 
consultants, clients or contractors) involved in handling the 
construction of building projects, 87 were received back and 84 
were usable for data analysis (Table I). Table II indicates the 
respondents’ qualification and Table III indicates their 
experience.  

TABLE I.  SURVEY DETAILS  

Parameter Value 

Total distributed questionnaires 131 

Received back questionnaires 87 

Invalid questionnaires  3 

Valid questionnaires 84 

Percentage of valid questionnaires 96 

TABLE II.  QUALIFICATION OF RESPONDENTS 

Degree  name Frequency Percentage 

Bachelor 68 80.9 

Master 14 16.7 

PhD  2  2.40 

Total 84 100 

TABLE III.  EXPERIENCE OF RESPONDENTS 

Experience Frequency Percentage 

0-5 years   8  9.52 

6-10 years  24 28.58 

11-15 years  21 25.00 

16-20 years  18 21.43 

20 and above 13 15.47 

Total 100 100 
 

For the first phase respondents were given questionnaires 
and were asked to rank each cause on a Likert scale. RIW 
approach was successfully used in previous studies giving 
accurate and good results [18]. The weight formula in RIW was 
calculated as shown in (1): 

i i

i

a x
RIW

x
=
∑
∑

    (1) 

where ai shows a constant which represents the weight given to 
i, and xi is a variable denoting the frequency of the answer for i. 
The values are established from x1 having the least importance 
and a1 being 1, to x5 for most significant and a5 equal to 5. The 
results are shown in Table IV. 

TABLE IV.  CAUSES OF TIME OVERRUN 

Rank Identified Causes RIW Value 

1 Financial issues faced by contractor 0.834 

2 Inexperienced contractor 0.831 

3 Weather impact 0.812 

4 Delay in supply of materials 0.783 

5 Mistakes in design 0.769 

6 Shortage of skilled labour 0.761 

7 Incompetent subcontractor 0.688 

8 Errors in time estimation 0.511 
 

A. Financial Issues Faced by Contractor 

Financial issues faced by the contractor were found as the 
most major cause of time overrun. Contractors play important 
role from execution to completion of a project. Construction 
activities are suspended and stopped by the contractors due to 
financial issues [19]. Continuous funding to contractors can 
help to complete project on approved time. 

B. Inexperienced Contractor 

Inexperienced and incompetent contractor can cause time 
overrun. Selection of contractor on favoritism causes time 
overrun in construction projects [20]. 

C. Weather Impact 

Most buildings constructed in tropical regions face chances 
of heavy rains, floods and earthquakes which affect 
construction activities causing delays on building projects. 
Weather impact causes time overrun from approved time in 
construction projects [21]. 

D. Delay in Supply of Materials at Site 

Construction site of building is often located at remote and 
sometimes in tropical areas, so it is difficult to have a 
continuous supply of materials on time. Delay in material 
supply creates gaps in construction activities at site which 
causes time overrun in construction projects [22].  

E. Mistakes in Design 

Before project tendering, easy and accurate design should 
be prepared. Mistakes in design delay the project construction 
activities which can lead the project to time overrun [23]. 

F. Shortage of Skilled Labor 

Shortage of skilled labor is one of the main causes of time 
overrun in the construction industry. Pakistan is a developing 
country and many workers are not skilled enough. Another 
cause of shortage of skilled labour is that many construction 
projects are running simultaneously [24]. 

G. Incomplete Subcontractor 

Contractor appoints subcontractors for the completion of 
different activities of the project but appointment of 
incompetent subcontractor, can cause construction activities to 
run very slow compared to the given schedule. Incompetent, 



Engineering, Technology & Applied Science Research Vol. 9, No. 1, 2019, 3762-3764 3764  
  

www.etasr.com Soomro et al.: Causes of Time Overrun in Construction of Building Projects in Pakistan 

 

with no experience contractors and subcontractors do many 
mistakes during construction [25]. 

H. Errors in Time Estimation 

Errors in making estimation of time duration because of 
lack of experienced engineers or planners leads to improper 
estimation of completion period of project. Estimation of 
project length is based on resources and their output [26]. 

V. MITIGATION MEASURES 

The second phase of this study was to identify mitigation 
measures of the identified causes. A questionnaire was 
developed having mitigation measures identified from literature 
review and interviews from experts. The respondents were 
asked to highlight their relative importance on a Likert scale. 
The collected data were analyzed by using RII (relative 
importance index) and the results are shown in Table V. 

TABLE V.  MITIGATION MEASURES OF CRITICAL FACTORS 

Mitigation Measure Value 

Adequate funds should be allocated for each project. 3.0 

Highly experienced contractors should be appointed. 2.97 

Proper arrangements should be done in flood and rainy seasons 2.94 

Suitable resources should be used for supply of materials. 2.91 

Well reputed consultants should be hired. 2.90 

Skilled labor should be with facilities. 2.89 

Favorite subcontractor should not be appointed. 2.88 

Proper filed investigation should be made. 2.86 
 

 

VI. CONCLUSION 

The purpose of this study was to find the major causes of 
time overrun in the construction projects in Pakistan and 
possible mitigation measures. After statistical analysis, the 
major causes of time overrun were: financial issues faced by 
the contractor, inexperienced contractor, weather impact, delay 
in supply of materials at site, mistakes in design, shortage of 
skilled labour, incompetent subcontractor, and errors in time 
estimation. Possible mitigation measures to control these 
causes were recognized and are depicted in Table V. The 
outcomes of this study will help stakeholders to control causes 
of time overrun. 

REFERENCES 

[1] R. F. Aziz, A. A. Abdel-Hakam, “Exploring delay causes of road 
construction projects in Egypt”, Alexandria Engineering Journal, Vol. 2, 
No. 5, pp. 16-23, 2016 

[2] M. Y. Honrao, D. B. Desai, “Study of delay in execution of 
infrastructure projects–highway construction”, International Journal of 
Scientific and Research Publications, Vol. 5, No. 6, pp. 1-8, 2015 

[3] G. Kikwasi, “Causes and effects of delays and disruptions in 
construction projects in Tanzania”, Australasian Journal of Construction 
Economics and Building-Conference Series, Vol. 1, No. 2, pp. 52-59, 
2013 

[4] M. Tafazzoli, Dynamic Risk Analysis of Construction Delays Using 
Fuzzy-Failure Mode Effects Analysis, PhD Thesis, University of 
Nevada, USA, 2017 

[5] Y. A. Olawale, M. Sun, “Cost and time control of construction projects: 
inhibiting factors and mitigating measures in practice”, Construction 
Management and Economics, Vol. 28, No. 5, pp. 509-526, 2010 

[6] H. M. P. Moura, J. M. C. Teixeira, B. Pires, “Dealing with cost and time 
in the portuguese construction industry”, CIB World Building Congress, 
Cape Town, South Africa, May 14-17, 2007 

[7] O. Duran, Current Risk Management Applications in Turkish 
Construction Industry, MSc Thesis, University of Gaziantep, Turkey, 
2006 

[8] C. T. Amoatey, Y. A. Ameyaw, E. Adaku, S. Famiyeh, “Analysing 
delay causes and effects in Ghanaian state housing construction 
projects”, International Journal of Managing Projects in Business, Vol. 
8, No. 1, pp. 198-214, 2015 

[9] S. Haq, Y. Rashid, M. S. Aslam, “Effects of delay in construction 
projects of Punjub-Pakistan: An emperical study”, Journal of Basic and 
Applied Scientific Research, Vol. 4, No. 4, pp. 98-104, 2014 

[10] S. Sohu, N. A. Memon, S. A. Abbasi, M. A. Pahore, K. Ullah, “Causes 
of Delay in Highway Projects in Pakistan”, 8th International Civil 
Engineering Congress, Karachi, Pakistan, December 23-24, 2016 

[11] Z. K. Bangash, “Analyzing the Causes of Delays in Construction 
Projects for Peshawar: Contractor Perception”, Journal of Emerging 
Trends in Applied Engineering, Vol. 1, No. 3, pp. 12-18, 2016 

[12] F. D. K. Fugar, A. B. Agyakwah-Baah, “Delays in building construction 
projects in Ghana”, Australasian Journal of Construction Economics and 
Building, Vol. 10, No. 1-2, pp. 103-116, 2010 

[13] D. W. M. Chan, M. M. Kumaraswamy, “Reasons for delay in civil 
engineering projects - The case of Hong Kong”, Transactions, Vol. 2, 
No. 3, pp. 1–8, 1996 

[14] N. R. Mansfield, O. Ugwu, T. Doran, “Causes of delay and cost 
overruns in Nigerian, Construction project”, International Journal of 
Project Management, Vol. 12, No. 4, pp. 254-260, 1994 

[15] D. O. Ogeno, Factors Influencing Completion of Construction Projects 
in Kenya: A case of Government Buildings Construction Projects in 
Nairobi County, Kenya, MSc Thesis, University of Nairobi, Kenya, 
2016 

[16] H. Emam, P. Farrell, M. Abdelaal,“Causes of delay on infrastructure 
projects in Qatar”, 31st Annual ARCOM Conference, Lincoln, UK, 
September 7-9, 2015 

[17] L. Le-Hoai, Y. D. Lee, J. Y. Lee, “Delay and cost overruns in Vietnam 
large construction projects: A comparison with other selected countries”, 
KSCE Journal of Civil Engineering, Vol. 12, No. 6, pp. 367-377, 2008 

[18] G. Ballard, L. Koskela, G. Howell, T. Zabelle,“Production System 
Design in Construction”, 9th Annual Conference of International Group 
for Lean Construction, Singapore, August 6-8, 2001 

[19] Y. Frimpong, J. Oluwoye, “Significant Factors Causing Delay and Cost 
Overruns in Construction of Groundwater Projects in Ghana”, Journal of 
Construction Research, Vol. 4, No. 2, pp. 175-187 2003 

[20] W. Alaghbari, M. R. A. Kadir, A. Salim, Ernawati, “The significant 
factors causing delay of building construction projects in Malaysia”. 
Engineering, Construction and Architectural Management, Vol. 14, No. 
2, pp. 192-206, 2007 

[21] A. H. Al-Momani, “Construction delay: a quantitative analysis”, 
International Journal of Project Management, Vol. 18, No. 1, pp. 51-59, 
2000 

[22] A. S. Faridi, S. M. El-Sayegh,“Significant factors causing delay in the 
UAE construction industry”, Construction Management and Economics, 
Vol. 24, No. 11, pp. 1167-1176, 2006 

[23] R. F. Aziz, “Ranking of delay factors in construction projects after 
Egyptian revolution”, Alexandria Engineering Journal, Vol. 52, No. 3, 
pp. 387-406, 2013 

[24] M. Sambasivan, Y. W. Soon, “Causes and effects of delays in Malaysian 
construction industry”, International Journal of Project Management, 
Vol. 25, No. 5, pp. 517-526, 2007 

[25] A. Senouci, A. Ismail, N. Eldin, “Time Delay and Cost Overrun in 
Qatari Public Construction Projects”, Procedia Engineering, Vol. 164, 
pp. 368-375, 2016 

[26] G. Sweis, R. Sweis, A. A. Hammad, A. Shboul, “Delays in construction 
projects: The case of Jordan”, International Journal of Project 
Management, Vol. 26, No. 6, pp. 665-674, 2008