Microsoft Word - 03-3290_s_ETASR_V10_N2_pp5361-5366


Engineering, Technology & Applied Science Research Vol. 10, No. 2, 2020, 5361-5366 5361 
 

www.etasr.com Mangi et al.: Parametric Study of Pile Response to Side-by-Side Twin Tunneling in Stiff Clay 

 

Parametric Study of Pile Response to Side-by-Side 

Twin Tunneling in Stiff Clay 
 

Naeem Mangi 

Department of Civil Engineering 
Quaid-e-Awam University of 

Engineering, Science & Technology 

Nawabshah, Pakistan 
naeem08ce30@gmail.com 

Daddan Khan Bangwar 

Department of Civil Engineering 
Quaid-e-Awam University of 

Engineering, Science & Technology 

Nawabshah, Pakistan 
daddan@quest.edu.pk 

Hemu Karira 

Department of Civil Engineering 
Mehran University of Engineering & 

Technology 

Khairpur Mir’s, Sindh, Pakistan 
engr.hemu07civil@gmail.com 

Samiullah Kalhoro 

Department of Civil Engineering 
Quaid-e-Awam University of Engineering, Science & Technology 

Nawabshah, Pakistan 

samiullahkalhoro63@gmail.com 

Ghulam Rasool Siddiqui 

Department of Civil Engineering 
Mehran University of Engineering & Technology 

Khairpur Mir’s, Sindh, Pakistan 

ghulamrasoolsiddiqui@gmail.com 
 

 

Abstract—A three dimensional coupled-consolidation numerical 

parametric study was carried out in order to gain new insight of 

single pile response to side-by-side twin tunneling in saturated 

stiff clay. An advanced hypo plasticity (clay) constitutive model 

with small-strain stiffness was adopted. The effects of relative to 

the pile tunnel depths were investigated by simulating the twin 
tunnels near the pile at various depths of tunnels, namely near 

the pile shaft, adjacent to the pile toe, and below the pile toe. It 

was found that the second tunneling in each case resulted in a 

larger settlement than the one due to the first tunneling with a 

maximum percentage difference of 175% in the case of twin 

tunneling near the mid-depth of the shaft. This occurred due to 
the degradation of clay stiffness around the pile during the first 

tunneling. Conversely, the first tunneling-induced bending 

moment was reduced substantially during the second tunneling. 

The most critical location of twin tunnels relative to the pile was 
found to be below the pile toe. 

Keywords-twin tunneling; pile foundation; parameteric study 

I. INTRODUCTION  

Tunnel excavation-induced stress relief and ground 
movements inevitably cause additional deformation and stress 
on adjacent pile foundations. It is a major concern for designers 
and engineers to evaluate the adverse effects on the existing 
piles. To understand the pile–soil–tunnel interaction 
mechanism, many field monitoring studies and centrifuge 
model tests [1-3] and analytical solutions and numerical 
modeling studies [4-7] have been conducted. They all 
concluded that tunneling adjacent to existing pile foundations 
caused pile settlement, additional axial load on piles, and 
induced bending moments along the piles, which is 
unfavourable for piled foundations. Their magnitudes are likely 
depended on the relative locations of tunnels and piles. 
However, most previous studies have focused on the effects of 
a single tunnel on single piles and pile groups. In fact, twin 

tunneling is particularly favoured when developing 
underground transportation systems [8]. To obtain a 
satisfactory numerical model of the single pile response to side-
by-side twin-tunneling, the analysis needs to take account of 
the soil’s small strain non-linearity. In view of the 
aforementioned issues, this study aims to systematically 
investigate the settlement and load transfer mechanism of an 
existing single pile due to side-by-side twin tunnels in saturated 
stiff clay. To achieve these objectives, a three-dimensional 
coupled-consolidation numerical parametric study was carried 
out by varying the twin tunnel depths relative to the pile.  

II. THREE DIMENSIONAL COUPLED CONSOLIDATION 

ANALYSIS 

To investigate single pile response to side-by-side twin 
tunneling in stiff saturated clay, a three-dimensional coupled 
consolidation numerical parametric study was conducted. To 
facilitate validation of the numerical model, the tunnel 
diameter, pile diameter, embedded length, and clear distance 
between the pile and the tunnel were identical (in prototype 
scale) to those in the centrifuge test [9]. Figure 1 shows the 
elevation view of the configuration of a typical numerical 
simulation in which twin tunnels were excavated adjacent to 
the pile toe. The diameter of each tunnel (D) was 6m. The 
embedded length (Lp) and diameter (dp) of the pile were 18m 
and 0.8m respectively. The modeled pile represents a 
cylindrical reinforced concrete (grade 40, reinforcement 
ratio=1) with a bending moment capacity of 800kNm. The 
center-to-center distance between each tunnel and the pile was 
5.5m (0.92D). It is worth noting that, in reality, high-rise 
buildings are unlikely to be built on a single pile. This 
hypothesized study is a more virtual case [3]. This 
simplification was made to understand the settlement and load 
transfer mechanism more clearly. The length of each model 
tunnel (along its longitudinal direction) is 72m, which is 

Corresponding author: Naeem Mangi



Engineering, Technology & Applied Science Research Vol. 10, No. 2, 2020, 5361-5366 5362 
 

www.etasr.com Mangi et al.: Parametric Study of Pile Response to Side-by-Side Twin Tunneling in Stiff Clay 

 

equivalent to 12D. Each tunnel excavation was simulated in 28 
steps. At each step, the tunnel advanced a distance of 2.5m 
(0.42D) [2]. The time increment of one day for each step was 
adopted in the finite element analysis. A monitoring section 
was selected at the transverse centreline of the pile (i.e. y/D=0) 
as a reference for the tunnel advancements. The parametric 
study consisted of nine different numerical simulations (in 
total) in which the existing single pile was located between the 
twin tunnels, which were excavated one after the other on 
either side of the pile at various depths of tunnels (zt) relative to 
the pile length (Lp), namely near the pile shaft (zt/Lp=0.67 and 
0.83), adjacent to the pile toe (zt/Lp=1.00) and below the pile 
toe (zt/Lp=1.17, 1.33, 1.50, 1.67, 1.83 and 2.00). In addition to 
these simulations, a pile load test (L) was conducted 
numerically in “greenfield” conditions (i.e. with no tunnels 
present) to obtain the ultimate capacity of the pile in stiff clay. 
Based on this, the working load was then calculated with a 
factor of safety of 3.0. The obtained working load was applied 
to the pile in the parametric analysis simulating twin tunneling. 
Table I summarises the conducted numerical simulations. 

 

 
Fig. 1.  Configuration of a typical numerical run representing case of 

zt/Lp=1.00 

TABLE I.  NUMERICAL SIMULATIONS SUMMARY 

Description of numerical run zt/Lp C/D 

Twin tunneling near the pile shaft 
0.67 1.5, 1.5 

0.83 2.0, 2.0 

Twin tunneling next to the pile toe 1.00 2.5, 2.5 

Twin tunneling below the pile toe 

1.17 3.0, 3.0 

1.33 3.5, 3.5 

1.50 4.0, 4.0 

1.67 4.5, 4.5 

1.83 5.0, 5.0 

2.00 5.5, 5.5 

zt=tunnel depth, Lp=pile length, C/D=cover to diameter of tunnel ratio 

III. FINITE ELEMENT MESH AND BOUNDARY CONDTIONS 

Figure 2 shows an isometric view of a typical finite element 
mesh (for the case of zt/Lp=1.0).The size of the mesh for each 
numerical simulation is 72m×72m×60m. These dimensions 
were sufficiently large to minimize the boundary effects in the 

numerical simulation because a further increase in the 
dimensions of the finite element mesh did not lead to any 
change in the computed results. Regarding the element size in 
the mesh, it is found that further halving the adopted mesh size 
leads to a change in the computed results of no more than only 
0.2%, suggesting that the mesh is sufficiently fine. Eight-noded 
hexahedral brick elements were used to model the soil and the 
pile. Four-noded shell elements were adopted to model each 
tunnel lining. Roller and pin supports were applied to the 
vertical sides and the base of the mesh, respectively. Therefore, 
movements normal to the vertical boundaries and in all 
directions of the base were restrained. The water table was 
assumed to be at the ground surface. Initially, the pore water 
pressure distribution was assumed to be hydrostatic. Free 
drainage was allowed at the top boundary of the mesh. The 
tunnel lining was assumed to be continuous and impervious. 

 

 
Fig. 2.  Finite element mesh and boundary conditions of a typical 

numerical analysis (zt/Lp=1.00) 

Interaction between the piles and surrounding soil was 
modeled by the surface-to-surface contact provided in Abaqus 
software package [10]. The surface-to-surface contact 
considers the shape of both the master and slave surface in the 
contacting region and allows pile-soil friction. The penalty 
approach was used for tangential contact and the normal 
behavior was modeled as hard contact with no normal relative 
displacement between the pile and the surrounding soil. The 
interface was modelled by the Coulomb’s friction law, in which 

the interface friction coefficient (µ) and limiting displacement 
(γlim) are required as input parameters. A limiting shear 
displacement of 5mm was assumed to achieve full mobilization 

of the interface friction equal to µ×p', where p' is the normal 
effective stress between two contact surfaces, and a typical 

value of µ for a bored pile of 0.35 was used [11]. The tunneling 
stress release process was modelled by the “element death” 
technique which is widely used in finite element analysis. In 
this technique, elements and nodes can be deactivated and 
activated. In this study, the volume loss is predefined before 
tunneling by specifying the area of the annulus gap between the 
tunnel lining and the excavated soil. Pattern of the non-uniform 
displacement boundaries was determined according to the 
displacement controlled model (DCM) in [5]. The soil inside 
the segment is excavated by deactivating soil elements inside it 

 Ground water table

 Working load
    (1.93 MN)

Existing single pile

       (Lp=18 m)

Stiff clay

Note:- Lp is embedded length of pile

            zt is depth of tunnel axis from the ground surface

zt=18 m

11 m

First

Tunnel

Second

Tunnel
2.5 m 2.5 m



Engineering, Technology & Applied Science Research Vol. 10, No. 2, 2020, 5361-5366 5363 
 

www.etasr.com Mangi et al.: Parametric Study of Pile Response to Side-by-Side Twin Tunneling in Stiff Clay 

 

and by specifying zero horizontal displacement at the tunnel 
face of the tunnel segment to be excavated. In the meantime, 
the shell elements representing the tunnel lining are activated.  

IV. CONSTITUTIVE MODEL AND MODEL PARAMETERS USED 
IN FINITE ELEMENT ANALYSIS 

A basic hypoplastic model was developed to capture the 
nonlinear behavior (upon monotonic loading at medium-to 
large-strain levels) of granular materials [12]. The basic model 
consists of five parameters (Table II). To account for the strain 
dependency and path dependency of the soil stiffness (at small 
strains), authors in [12] further improved the basic hypoplastic 
model by incorporating the concept of intergranular strain, 
which requires five additional parameters. The hypoplastic clay 
model with small strain stiffness has been implemented in the 
finite element software package Abaqus through a user-defined 
subroutine. The coefficient of lateral earth pressure at rest, Ko 
was estimated by the relevant equation in [14]. The concrete 
pile and tunnel lining were assumed to be linear elastic with 
Young's modulus of 35GPa and Poisson's ratio of 0.25. The 
thickness of the lining was taken as 0.25m. The unit weight of 
concrete was taken as 24kN/m

3
. The parameters for the piles 

and the tunnel lining are summarized in Table III. 

TABLE II.  ADOPTED MODEL PARAMETERS OF KAOLIN CLAY 

Description Value 

Effective angle of shearing resistance at critical state, φ’ 22
o
 

Parameter controlling the slope of the isotropic normal 

compression line in the ln(1+e) versus lnp plane, λ* [13] 
0.11 

Parameter controlling the slope of the isotropic normal 

compression line in the ln(1+e) versus lnp plane, κ* [13] 
0.026 

Parameter controlling the position of the isotropic normal 

compression line in the ln(1+e)–lnp plane, N 
1.36 

Parameter controlling the shear stiffness at medium- to 

large- strain levels, r 
0.65 

Parameter controlling the initial shear modulus upon 180° 

strain path reversal, mR 
14 

Parameter controlling the initial shear modulus upon 90° 

strain path reversal, mT 
11 

Size of elastic range, R 1×10
-5
 

Parameter controlling the rate of degradation of the stiffness 

with strain, βr 
0.1 

Parameter controlling the degradation rate of stiffness with 

strain, χ 
0.7 

Initial void ratio, e 1.05 

Dry density (kg/m
3
) 1136 

Coefficient of permeability, k (m/s) 1×10
-9
 

 

TABLE III.  ADOPTED CONCRETE PARAMETERS IN FEM 

Description Value 

Young's Modulus, E 35GPa 

Poisson's ratio, νννν 0.3 

Density, ρρρρ 2400kg/m
3
 

 

V. INTERPRETATION OF COMPUTED RESULTS 

A. Induced Pile Settlement Due to Twin Tunnels 

Figure 3 illustrates the pile settlement induced after the first 
and th second tunnel at different depths relative to the pile 
(zt/Lp). The long-term pile settlement (i.e. 15 years after twin 

tunneling completion) is included in the figure. The measured 
induced pile settlement tunneling at different depths in 
centrifuge modeling reported by [9, 15] is also shown in the 
figure for comparison. A linear increase in twin tunneling-
induced settlement was observed as the tunnel depth increased 
from zt/Lp=0.67 to 1.33. However, as the depth increased 
further (1.50≤zt/Lp≤2.0), the induced settlement decreased with 
a similar trend. This computed result is consistent with the one 
measured in centrifuge tests simulating tunneling at different 
depths relative to piles in stiff clay [9] and in sand [8]. This 
tunneling-induced settlement mechanism with zt/Lp can be 
attributed to the influence zone of tunneling-induced ground 
movement and stress-release-affected regions. In the case of 
zt/Lp=1.33, the entire pile stood within the influence zone of 
tunneling-induced ground movement, and the stress release 
region was developed directly underneath the pile toe. When 
zt/Lp=0.67, 0.83 and 1.00, the pile was located only partially 
within the influence zones. Therefore, the pile experienced 
larger settlement in the case of zt/Lp=1.33 than in these cases. 
Although the entire pile in the cases of zt/Lp=1.50, 1.67, 1.83 
and 2.00 was located inside the tunneling-induced ground 
movement, the tunneling-induced pile settlement was less than 
that of zt/Lp=1.33. This is because the location of the pile toe 
was beyond the tunneling-induced stress-release-affected 
region in these cases. 

 

 
Fig. 3.  Computed load settlement curve from the pile load test without 

tunneling  

Qualitatively, the second tunneling-induced settlement 
trend with respect to zt/Lp was similar to the first tunneling-
induced settlement. However, the magnitude of the pile 
settlement induced by the second tunnel was higher than that 
induced by the first tunnel in each case. This can be attributed 
to the degradation of clay stiffness around the pile due to stress 
release and the development of shear strains as a result of the 
first tunnel excavation. The largest settlement (175% of Sp due 
to the first tunnel) was induced by the second tunnel when 
zt/Lp=0.67. It can be seen that the settlement of the pile reduced 
in the long term (i.e. 15 years after completion of the twin 
tunnels) in all cases. This pile heave is attributed to the 
dissipation of excessive negative pore pressure generated 

0.00

0.50

1.00

1.50

2.00

2.50

3.00

3.50

4.00

4.50

5.00

5.50

6.00

6.50

7.00

7.50

8.00

0.50 0.67 0.83 1.00 1.17 1.34 1.50 1.67 1.84 2.00

N
o
rm
a
li
se
d
 p
il
e
 h
e
a
d
 s
e
tt
le
m
e
n
t 
(S

p
/d

p
):
 %

Tunnel depth relative to pile (zt/Lp)

Loganathan et al., 2000 After first tunnel

Ng et al., 2013 After twin tunnels

Series6 sLong term settlement (15 years after twin tunnelling)

(Cummulative)

Computed (This study)Measured (Centrifuge) 

1.33 1.83



Engineering, Technology & Applied Science Research Vol. 10, No. 2, 2020, 5361-5366 5364 
 

www.etasr.com Mangi et al.: Parametric Study of Pile Response to Side-by-Side Twin Tunneling in Stiff Clay 

 

around the pile due to the twin tunnels. The maximum 
reduction of the pile settlement (17.2% of the settlement after 
twin tunnels) was observed in the case zt/Lp=1.33. 

B. Changes in Axial Load Distribution 

Figure 4 illustrates the axial force distribution along the pile 
with normalized depth (i.e., Z/Lp) below the ground surface 
after twin tunneling when zt/Lp=0.67, 1.00 and 1.33. The axial 
load distribution before tunneling (after applying the working 
load) is also included in the Figure as a reference. Before 
tunneling, the pile carried approximately 75% of the working 
load (i.e. 1010kN) with its shaft resistance and the remainder 
with its end-bearing resistance. Because tunneling was carried 
out near the mid-depth of the pile shaft in the case zt/Lp=0.67, 
tunnel-induced reduction in normal stresses to the pile shaft 
and downward soil movement caused an increase in axial load 
along the entire length of the pile after the first and second 
tunnel excavations. At the end of the first tunneling, the 
maximum increment in the axial force (63% of that at working 
load) was computed at Z/Lp=0.7, which is above the tunnel 
spring line. By inspecting the axial load distribution after the 
first tunnel excavation, it is observed that along the upper half 
of the pile (0≤Z/Lp≤0.6), the shaft resistance decreases to zero. 
Consequently, the load was transferred to the lower half of the 
pile. To maintain equilibrium, the pile had to settle to further 
mobilize the end-bearing and shaft resistance along the lower 
portion (Z/Lp>0.6). This led to increases of 73% and 24% in the 
mobilized end-bearing and shaft resistance at the lower portion 
(Z/Lp>0.5) respectively upon completion of the first tunnel. The 
second tunneling in the case zt/Lp=0.67 caused a further 
reduction of the normal stresses to the pile shaft. Consequently, 
soil settled more than the pile, resulting in Negative Skin 
Friction (NSF) along the upper half of the pile (0≤Z/Lp≤0.6). 
This suggests that this portion of the pile is subjected to 
dragload by the surrounding soil. This caused the pile to settle 
more than that due to the first tunnel. To maintain vertical 
equilibrium of the pile, the soil surrounding the lower part of 
the pile (Z/Lp>0.6) resisted its settlement by mobilizing 
Positive Skin Friction (PSF) at the pile–soil interface and end-
bearing resistance at the toe of the pile. Owing to the second 
tunneling, the end-bearing and mobilized shaft resistance 
increased to 190% and 18%, respectively. 

Owing to twin tunneling adjacent to the pile toe 
(zt/Lp=1.00), the axial load increased along the pile at depths 
ranging from 0.42 to 1.0Lp. The increase in axial load resulted 
from reduced shaft resistance, which was caused by stress 
release from twin tunneling adjacent to the pile toe. The 
reduction percentages in shaft resistance were 22% and 43% 
after the first and twin tunneling (cumulative) respectively. 
Consequently, the axial load borne by the shaft resistance along 
the pile at depths ranging from 0.42 to 1.0Lp was transferred 
downward to the pile toe, leading to a 75% and 156% increase 
in mobilized end-bearing resistance after the first and twin 
(cumulative) tunneling, respectively. In contrast to the 
tunneling near the mid-depth of the pile shaft (zt/Lp=0.67) and 
adjacent to the pile toe (zt/Lp=1.00), the axial load decreased 
along the entire length of the pile when twin tunnels were 
excavated below the pile toe (zt/Lp=1.33). The advancement of 
the twin tunnels led to reductions in the end-bearing of the pile 
as a result of stress release from 2% volume loss. To 

compensate for the decrease in end-bearing resistance, the pile 
had to settle substantially to mobilize the shaft resistance along 
the entire pile length. This result is similar to those measured in 
the field [16]. The end-bearing decreased by 12% and 28% 
owing to the first and twin tunnels, respectively. 

 

 
Fig. 4.  Axial load distribution along the pile length 

C. Twin-tunneling Induced Bending Moment along the Pile 

Figure 5 illustrates the induced bending moment along the 
pile after the first and second tunneling in the cases of 
zt/Lp=0.67, 1.00 and 1.33. A positive bending moment means 
that tensile stress was induced along the pile shaft facing the 
first tunnel. The measured bending moment of a single pile 
subjected to single tunneling in centrifuge model test [9] was 
also included for comparison. Since there was no rigid 
constraint at the pile head (pile head was free to move and 
rotate), no bending moment was induced at/near the head of the 
pile in all the cases. It can be observed that in the case of 
zt/Lp=0.67, the maximum positive bending moment was 
induced in the pile at Z/Lp=0.6 near spring line of the first 
tunnel. Authors in [17] have also reported a measured 
maximum bending moment occurring at the spring line of the 
tunnel near the shaft of the pile group. This happened because 
the pile was subjected to lateral soil movement towards the 
tunnel resulting from significant stress release. The magnitude 
of the maximum positive bending moment was 400kNm 
(which is 50% of the pile BM capacity). On the other hand 
negligible bending moment was induced near the pile toe 
(below the tunnel spring line), because the tunneling induced 
soil movement below the tunnel spring line was insignificant 
[2]. Subsequently, the pile was subjected to stress release on 
the opposite side of the pile as a result of the second tunnel’s 
excavation near the mid-depth of the pile shaft. Consequently, 
the induced-bending moment decreased along the pile after the 
second tunneling. The induced-bending moment along the pile 
was not returned to zero after the second tunneling as the soil 
does not behave elastically. Finally, a positive bending moment 

0.0

0.1

0.2

0.3

0.4

0.5

0.6

0.7

0.8

0.9

1.0

100 200 300 400 500 600 700 800 900 1000 1100 1200 1300 1400

N
o
r
m

a
li
z
e
d
 d

e
p
th

 (
Z
/L

p
)

Axial force: kN

Before tunnelling C/D=1.5

1st tunnel 2nd tunnel

C/D=1.5 C/D=1.5

C/D=1.5 C/D=1.5

C/D=1.5 C/D=1.5

After 1st tunnelling After 2nd tunnelling

zt/Lp = 0.67 zt/Lp = 0.67

zt/Lp = 1.00

zt/Lp = 1.33 zt/Lp = 1.33

zt/Lp = 1.00



Engineering, Technology & Applied Science Research Vol. 10, No. 2, 2020, 5361-5366 5365 
 

www.etasr.com Mangi et al.: Parametric Study of Pile Response to Side-by-Side Twin Tunneling in Stiff Clay 

 

with magnitude of 50kNm was induced. Owing to the soil 
inward movement towards the first tunnel when zt/Lp=1.00, 
positive bending moment was induced at the lower part of the 
pile (0.7≤Z/Lp≤1.0). To counter-balance this induced positive 
bending moment, negative bending moment was developed 
along the upper part of the pile (0≤Z/Lp≤0.7). The magnitudes 
of maximum induced positive and negative bending moment 
were 130kNm. The measured induced bending moment along 
the pile due to single tunneling in centrifuge reported by [9] 
was positive and smaller than the one computed in magnitude. 
This may be caused by the tunneling-induced volume loss 
which was modeled as 1% in the centrifuge test. The 
subsequent tunneling at zt/Lp=1.00 on the opposite side of the 
pile reduced the induced bending moment significantly. The 
maximum induced bending moment was 37kNm at Z/Lp=0.6 
after the twin tunnel excavation.  

 

 
Fig. 5.  Induced bending moment along the pile length 

In contrast to the induced bending moment in the case 
zt/Lp=0.67, negative bending moment was induced along the 
entire pile length due to the first tunnel advancement in the case 
of zt/Lp=1.33. However, the magnitude of maximum bending 
(100kPa at Z/Lp=0.7) was less than the one in the case 
zt/Lp=0.67. Also, no bending was induced at the pile toe and 
head. It can be seen that the induced bending moment during 
the first tunnel advancement in the case of tunneling near the 
mid-depth of the pile (zt/Lp=0.67) and adjacent the pile toe 
(zt/Lp=1.00) was less than that in the case of tunneling below 
the pile toe (zt/Lp=1.33). Therefore, in the case of zt/Lp=1.33, 
the most critical issue to be considered is the relatively large 
settlement. 

VI. DISCUSSION  

It is well recognized that the stress-strain relationship of 
soils is highly nonlinear even at very small strains. The 
stiffness of most soils decreases as strain increases and depends 
on the recent stress or strain history of the soil. Owing to non-

linear soil behavior, a tunnel excavation can cause reduction in 
the stiffness of the soil. Therefore, it is vital to investigate the 
pile responses not only to the first tunnel but also to the 
subsequent tunnel in clay in a twin-tunneling transportation 
system. Keeping these issues into consideration, effects of twin 
side by side tunneling on a single pile in stiff clay were 
investigated in this study. It was revealed that the second 
tunneling caused larger settlement and smaller bending 
moment in the pile. This finding is the major contribution of 
this parametric study. 

VII. CONCLUSIONS 

Based on the modeled ground conditions, geometry, and 
tunneling method, the following conclusions can be drawn: 

• Due to the degradation of the stiffness of the clay 
surrounding the pile as a result of tunneling-induced stress 
release and shear strain, the second tunneling caused larger 
settlement than the first in each case. When zt/Lp=0.67 the 
second tunneling-induced settlement was the largest (i.e. 
175% of Sp from the first tunnel) of all cases. The 
cumulative settlements of the pile resulting from the 
working load and twin tunneling in the cases zt/Lp=0.67, 
1.00 and 1.33 were 25, 39, and 47mm (i.e. 3.1, 4.9, and 5.9 
of the pile diameter) respectively. 

• The first tunneling in the case zt/Lp=0.67 induced the largest 
bending moment (50% of the pile BM capacity) at the 
spring line of the tunnel. However, the induced bending 
moment along the pile decreased significantly due to the 
excavation of the second tunnel in each case because of the 
side-by-side twin tunneling configuration in which the 
second tunnel caused a stress release on the opposite side of 
the pile. 

• When of zt/Lp=0.67, the second tunneling-induced soil 
movement due to stress release mobilized negative shaft 
friction at the upper part of the pile. Consequently, a 
downward load transfer was observed along the pile, further 
mobilizing the pile end-bearing. Similarly, in the case 
zt/Lp=1.00, the load borne by the pile shaft was transferred 
to the pile toe as a result of the twin tunneling reduction in 
the shaft resistance at the lower part of the pile 
(0.3≤Z/Lp≤0.9). 

ACKNOWLEDGEMENT 

The authors would like to acknowledge the financial 
support provided by the Quaid-e-Awam University of 
Engineering, Science & Technology, Sindh and Pakistan. 

REFERENCES 

[1] G. Gudehus, “A comprehensive constitutive equation for granular 

materials”, Soils and Foundations, Vol. 36, No. 1, pp. 1-12, 1996 

[2] K. Ishihara, “Liquefaction and flow failure during earthquakes”, 
Geotechnique, Vol. 43, No. 3, pp. 351-451, 1993 

[3] C. W. W. Ng, “The state-of-the-art centrifuge modelling of geotechnical 

problems at HKUST”, Journal of Zhejiang University Science A, Vol. 
15, pp. 1-21, 2014 

[4] J. Jaky, “The coefficient of earth pressure at rest”, Journal of the Society 

of Hungarian Architects and Engineers, pp. 355-358, 1944 

0.0

0.1

0.2

0.3

0.4

0.5

0.6

0.7

0.8

0.9

1.0

-150 -100 -50 0 50 100 150 200 250 300 350 400 450

N
o
r
m

a
li
z
e
d
 d

e
p
th

 (
Z
/L

p
)

Induced bending moment: kNm

Measured Series3

Series11 Series12

1st tunnel 2nd tunnel

C/D=1.5 C/D=1.5

C/D=2.5 C/D=2.5

C/D=3.5 C/D=3.5

After 1st tunnelling After 2nd tunnelling

Meaured (Loganathan et al., 2000)

Computed (This study)

zt/Lp = 0.67 zt/Lp = 0.67

zt/Lp = 1.00

zt/Lp = 1.33 zt/Lp = 1.33

zt/Lp = 1.00



Engineering, Technology & Applied Science Research Vol. 10, No. 2, 2020, 5361-5366 5366 
 

www.etasr.com Mangi et al.: Parametric Study of Pile Response to Side-by-Side Twin Tunneling in Stiff Clay 

 

[5] K. H. Chiang, C. J. Lee, “Responses of single piles to tunneling-induced 
soil movements in sandy ground”, Canadian Geotechnical Journal, Vol. 

44, No. 10, pp. 1224-1241, 2007 

[6] A. Niemunis, I. Herle, “Hypoplasic model for cohesionless soils with 
elastic strain range”, Mechanics of Cohesive-frictional Materials, Vol. 2, 

No. 4, pp. 279-299, 1997 

[7] C. W. W. Ng, M. A. Soomro, Y. Hong, “Three-dimensional centrifuge 
modelling of pile group responses to side-by-side twin tunnelling”, 

Tunelling and Underground Space Technology, Vol. 43, pp. 350-361, 
2014 

[8] C. W. W. Ng, H. Lu, S. Y. Peng, “Three-dimensional centrifuge 
modelling of the effects of twin tunnelling on an existiong pile”, 

Tunneling and Underground Space Technology, Vol. 35, pp. 189-199, 
2013 

[9] N. Loganathan, H. G. Poulos, D. P. Stewart, “Centrifuge model testing 

of tunnelling-induced ground and pile deformations”, Geotechnique, 
Vol. 50, No. 3, pp. 283-294, 2000 

[10] Abaqus user’s manual, version 6.8.2, Dassault Systemes, 2008 

[11] D. Masin, “Hypoplastic cam-clay model”, Geotechnique, Vol. 62, No. 6, 

pp. 549-553, 2012 

[12] A. M. Marshall, R. J. Mair, “Tunneling beneath driven or jacked end-
bearing piles in sand”, Canadian Geotechnical Journal, Vol. 48, No. 12, 

pp. 1757-1771, 2011 

[13] S. W. Jacobsz, J. R. Standing, R. J. Mair, T. Hagiwara, T. Sugiyama, 
“Centrifuge modelling of tunnelling near driven piles”, Soils and 

Foundations, Vol. 44, No. 1, pp. 49-56, 2004 

[14] P. W. Mayne, F. H. Kulhawy, “K0-OCR relationships in soils”, Journal 

of the Geotechnical Engineering-ASCE, Vol. 108, No. 6, pp. 851-872, 
1982 

[15] D. A. Mangejo, M. A. Soomro, N. Mangi, I. A. Halepoto, I. A. Dahri, 

“A parametric study of effect on single pile integrity due to an adjacent 
excavation induced stress release in soft clay”, Engineering, Technology 

& Applied Science Research, Vol. 8, No. 4, pp. 3189-3193, 2018 

[16] M. A. Soomro, A. S. Brohi, D. K. Bangwar, S. A. Bhatti, “3D numerical 
modelling of pile group responses to excavation-induced stress release in 

Silty Clay”, Engineering, Technology & Applied Science Research, Vol. 
8, No. 1, pp. 2577-2584, 2018 

[17] D. R. Coutts, J. Wang, “Monitoring of reinforced concrete piles under 

horizontal and vertical loads due to tunnelling”, International Conference 
on Tunnels and Underground Structures, Singapore, November 26-29, 

2000