Microsoft Word - 25-3444_s1_ETASR_V10_N2_pp5483-5486


Engineering, Technology & Applied Science Research Vol. 10, No. 2, 2020, 5483-5486 5483 
 

www.etasr.com Daslim & Mursadin: A Control Model for Reinforced Concrete Work Materials on the Construction … 

 

A Control Model for Reinforced Concrete Work 

Materials on the Construction of Duta Mall 2 
 

Sudiono Daslim 

Department of Civil Engineering 
Faculty of Engineering 

Lambung Mangkurat University 

Banjarmasin, Indonesia 
sudiono_daslim@yahoo.com 

Aqli Mursadin 

Department of Civil Engineering 
Faculty of Engineering 

Lambung Mangkurat University 

Banjarmasin, Indonesia 
a.mursadin@ulm.ac.id 

 

 

Abstract—Controlling is a crucial stage in achieving a project 

target, covering aspects of cost, quality, and time. In the 

construction industry, the cost aspect is often the main focus. The 

project of Duta Mall 2 (DM 2) is the development of an existing 

building and the cost aspect is a major concern to the owner. 

Dynamic internal and external factors of the DM 2 project cause 

the project control to be quite difficult, with the materials 

becoming the most dominant factor in construction cost. Cost 

control starts from reinforced concrete work materials, 

consisting of ready mixed concrete, concrete steel, wire, plywood, 
timber, and nails. Bad control of material purchasing can lead to 

cost escalation, degradation of material quality, and impact on 

the execution schedule of works. This research was conducted to 

obtain quantitative correlations between material components 

based on reinforced concrete works material supply data. From 

these data, some linear regression models can be designed to 

obtain a more accurate and effective prediction of material 
volume needs in the future. Model equations can be applied to 

control material demand, measure waste, reference of material 

volume in arranging the project cost budget, in addition to the 

process in the control procedure of the request for goods 

(materials and equipment). 

Keywords-reinforced concrete works; material control; linear 
regression; predictive capabilities; control procedure   

I. INTRODUCTION  

On all construction projects, cost, quality and time are 
parameters that need to be optimized. Cost is a very important 
project parameter. It stands as a single aspect and is also 
influenced by the quality and completion time of works. Poor 
quality works will lead to complaints and can potentially create 
a construction claim or at least a demand of reworks/repairs 
which will lead to cost overrun. Delay in project completion 
will cause cost overrun or even a fine. Cost management is a 
completion of three constraints covering cost, schedules, and 
scope. Each must be completed in order to complete the project 
on time and budget and meet all customer expectations. 
Projects must be settled on an approved budget. It is therefore 
very clear that the quality problem and the work schedule will 
also affect the cost [1]. Duta Mall 2 (DM 2) is a building 
construction project. It is the expansion of Duta Mall 1 (DM 1) 
which is already in operation. In this dynamic DM 2 project, 

there are several factors that cause difficulty in material 
control. Material management, especially for reinforced 
concrete works in the DM 2 project, is done by the contractor 
but its purchase system is controlled by a management team 
from the owner to minimize cost. Besides the cost aspect, the 
material management system also touches integrated 
environmental and social aspects [2]. Material control of 
reinforced concrete works is very important, because the 
material cost is a significant part of the overall cost of the 
project, representing anything from 40% to 60% of the final 
cost, so tight control is essential [3]. Based on the historical 
data on material supply of reinforced concrete works in DM 2, 
there are some regression models of volume supply of the 
materials. Material components of reinforced concrete works 
consist of ready mixed concrete, concrete steel, wire, plywood, 
timber and nails. The aims of the current research are: 

• To find the various causes of difficulty in material control 
of reinforced concrete works on the development of DM 2 
based on the existing procedure. 

• To develop a relationship model of volume supply between 
materials on the construction of DM 2. 

• To improve material planning procedures and control on 
reinforced concrete works in DM 2 project. 

II. THEORITICAL BASIS 

A. Project Management and Project Control 

A project is defined as a temporary effort made to create 
unique products, services or results [4]. It is defined by 
PMBOK (Project Management Body of Knowledge). Project 
management aims to plan, to organize, to lead, and to control 
company resources to achieve a predetermined short-term goal 
[5]. Control of construction project includes cost, quality, and 
time. The concept of controlling the project in the lean 
construction method has a principle in downsizing or 
reducing/eliminating waste. Construction waste is anything 
generated as a result of construction and is then abandoned, 
regardless weather it has been processed or stockpiled [6]. 

B. Material Control on Construction Projects 

In the production system, especially in the construction 

Corresponding author: Sudiono Daslim



Engineering, Technology & Applied Science Research Vol. 10, No. 2, 2020, 5483-5486 5484 
 

www.etasr.com Daslim & Mursadin: A Control Model for Reinforced Concrete Work Materials on the Construction … 

 

industries related to supply chain management, there are two 
methods, i.e. push system and pull system. The DM 2 
construction project utilizes a combination of both methods. 
Controlling of reinforced concrete work materials to optimize 
construction project cost can be achieved by the following 
process: 

• Fulfillment of demand or submission of materials. 

• Estimation of inventory according to the job stage or work 
schedule that has been planned some time ahead. 

• Supervision of material acceptance to fit the demand. 

• Storage and protection of materials. 

• Efficiency of material use in the project through appropriate 
supervision and working methods. 

• Evaluation of progressive material usage. 

The ability to control reinforced concrete work materials 
certainly increases the effectiveness of the contractor. In 
addition to economic reasons, effective material control also 
reduces material waste. Material cost, delay of material arrival 
and inaccurate estimates are examples of causes of cost overrun 
[7]. The objective is to assure that the right materials in the 
right quantities and at the right locations are provided at the 
right time to the construction crews on the project. Most 
construction site layout planning for construction sites is based 
upon contractors’ prior experience and it is designed only once 
before construction starts without consideration of the dynamic 
nature of the supply problems, such as dynamic changes of 
requirements and available site information in consecutive 
construction project phases [8]. Material procurements on 
several projects also have constraints on the availability of 
location in the field. Adequate supply of materials in 
accordance with the planned job site will help the 
implementation of construction effectively and efficiently. 
However, in some projects the stages of construction activities 
may differ from the initial planning, due to the dynamic 
implementation of construction. Consequently, there is a 
distortion between the material supplies previously proposed 
based on estimates and the new areas of the work. 

C. Simple Linear Regression Model  

In the construction industry, some problems have 
relationships that can be predicted through regression models. 
The relationship between a variable in a group and other groups 
is often very useful in statistical analysis. The relationship 
between the independent variable and the matched response is 
an equation of regression [9]. Steps or stages that need to be 
conducted in order to obtain a good linear regression model 
consist of model identification, parameter estimation, 
parameter testing, and application of regression models [10].  

III. RESEARCH METHOD 

In this research, preliminary analysis is applied to the 
recapitulation acceptance data of reinforced concrete materials, 
i.e. ready mixed concrete, concrete steel, wire, plywood, 
timber, and nails with the scatter plot method. Parameter 
estimation for linear regression models was conducted with the 

least squares method and validation followed [11]. The formed 
linear regression model was adopted into the pre-existing 
model of the DM 2 materials control procedure. The 
implementation steps of the research are: 

• Preliminary study, in the form of observations in the field 
(Project DM 2).  

• Literature review. 

• Primary and secondary data collection. 

• Study of the causes of difficulty in controlling reinforced 
concrete work materials by observation of the work 
processes and materials used. 

• Regression model construction based on the supply data. 

• Validation of the linear regression models. 

• Model of planning and material volume control. 

• Conclusion. 

IV. DATA ANALYSIS 

A. Initial Data Collection  

The materials of reinforced concrete works are exhibited in 
Table I along with the periodic data which must be transformed 
in cumulative data. The cumulative data of each material have 
been tested for normality distribution as shown in Table II. 

B. Developing of Linear Regression Models 

1) Regression Equations of Reduction Data Constructed with 

the Least Squares Method 

In developing linear regression models, the research uses 
the cumulative data, so the periodic data should be modified or 
transformed. Table II shows that models for plywood-timber 
and timber-nails do not pass the normality test. The P values 
for both data pairs are less than 0.05, which means that the data 
have non-normal distribution. Therefore it is necessary to 
reduce outlier data. The data that should be eliminated for the 
above models are described below. 

• Plywood-timber: Data that should be eliminated are 
variable no. 12 (December 2017) and no. 15 (March 2018). 

• Timber-nails: Data that should be eliminated are only 
variable no. 12 (data on December 2017). 

After eliminating the outlier data, the normality tests for 
both models are fulfilled. Next, the used data are normally 
distributed variables that generate the following equations: 

• Ready mixed concrete and concrete steel:  

���	 = −109.92+ 	0.1787	��    (1) 

• Concrete steel-wire:  

��� =   1,885.25 +  7.6577 ��    (2) 

• Ready mixed concrete-plywood: 

�� � = −358.95 + 	0.4228	��    (3) 



Engineering, Technology & Applied Science Research Vol. 10, No. 2, 2020, 5483-5486 5485 
 

www.etasr.com Daslim & Mursadin: A Control Model for Reinforced Concrete Work Materials on the Construction … 

 

TABLE I. SUPPLY OF REINFORCED CONCRETE WORK MATERIALS 

No. Month Ready mixed concrete (m
3
) Concrete steel (×1000kg) Wire (kg) Plywood (pcs) Timber (m

3
) Nails (kg) 

1 Jan’17 1,653.5 182.513 2,780 546 56.11 1,125 

2 Feb’17 715.0 244.771 200 294 64.03 1,040 

3 Mar’17 890.5 44.746 1,500 104 20.01 695 

4 Apr’17 815.0 167.096 1,400 448 4.31 770 

5 May’17 896.0 63.952 1,300 240 11.00 695 

6 Jun’17 355.5 190.131 800 - 6.11 270 

7 Jul’17 211.0 - 110 60 33.00 - 

8 Aug’17 1,067.0 145.029 1,830 583 84.50 860 

9 Sep’17 948.5 297.365 1,050 528 65.70 1,040 

10 Oct’17 509.5 455.435 1,800 150 42.30 520 

11 Nov’17 1,125.0 - 1,550 607 72.45 1,130 

12 Dec’17 952.5 112.619 600 304 184.18 510 

13 Jan’18 1,764.5 - 3,150 832 136.91 1,650 

14 Feb’18 1,587.5 218.068 1,100 900 85.81 1,550 

15 Mar’18 1,402.5 415.649 2,100 252 151.30 2,330 

16 Apr’18 1,579.5 - 2,150 1,202 101.06 1,205 

17 May’18 827.5 177.642 1,500 165 33.11 827 

18 Jun’18 346.0 144.040 - - - - 

19 Jul’18 599.5 135.359 2,100 150 38.14 1,706 

20 Aug’18 1,543.5 - 2,700 391 63.75 1,363 

21 Sep’18 969.5 567.687 600 510 12.54 1,200 

22 Oct’18 1,297.5 60.561 1,600 820 38.31 170 

23 Nov’18 973.0 313.245 1,200 300 19.28 814 

24 Dec’18 1,135.5 260.196 1,700 150 31.04 520 

25 Jan’19 1,062.5 270.529 1,250 1,118 55.94 955 

26 Feb’19 1,255.5 275.682 1,900 551 53.53 1,125 

27 Mar’19 2,009.0 75.035 2,100 625 82.49 1,030 

28 Apr’19 1,789.5 583.495 1,700 475 95.32 605 

29 May’19 1,051.0 367.654 1,200 295 51.57 381 

30 Jun’19 247.0 215.986 500 150 6.52 690 

  
31,579.5 5,984.485 43,470 12,750 1,700.32 26,776 

TABLE II. VALUE OF NORMALITY TEST IN SAPHIRO WILK METHOD 

No. Model Statistic P value Remark 

1 Ready mixed concrete-concrete steel 0.974 0.641 normal distribution 

2 Concrete steel-wire 0.982 0.875 normal distribution 

3 Ready mix concrete-plywood 0.963 0.374 normal distribution 

4 Plywood-timber 0.891   0.005* non-normal distribution 

5 Timber-nails 0.874   0.002* non-normal distribution 

* p value < 0.05 
 

• Plywood-timber:  

�� �	 = 	39.29 + 	0.1095	��    (4) 

• Timber-nails: 

�� � = 	613.76+ 16.9934	��    (5) 

The result of normality retest to the regression of plywood 
and timber was P=0.369 and the regression of wood and nails 
was value P=0.145.  

2) Heteroscedasticity Test 

The results of heteroscedasticity test with Glejser method 
are shown in Table III. 

3) Modification of the Regression Equations Model with 

Mathematics Substitution Method Shown (5-10) 

• Ready mixed concrete and concrete steel:  

�� � =  − 109.92 + 0.1787 ��    (6) 

• Ready mixed concrete-wire:  

�� � = −1,043.52 + 1.3684 ��    (7) 

• Ready mixed concrete-plywood: 

�� � = 	−358.95 + 0.4228	��    (8) 

• Ready mixed concrete-timber:  

�� � = 	−2.97+ 0.0463	��    (9) 

• Ready mixed concrete-nails: 

�� � = 	563.29+ 0.7868	��    (10) 

TABLE III. HETEROSCEDASTICITY TEST VALUES 

No. Model t value P value Remark 

1 
Ready mixed concrete -

concrete steel 
1.862 0.073 homoscedasticity 

2 Concrete steel -wire 1.869 0.072 homoscedasticity 

3 
Ready mixed concrete -

plywood 
1.715 0.097 homoscedasticity 

4 Plywood-timber 0.179 0.859 homoscedasticity 

5 Timber-nails 0.917 0.368 homoscedasticity 



Engineering, Technology & Applied Science Research Vol. 10, No. 2, 2020, 5483-5486 5486 
 

www.etasr.com Daslim & Mursadin: A Control Model for Reinforced Concrete Work Materials on the Construction … 

 

Note in (1)-(10): s: concrete steel, w: wire, p: plywood, t: 
timber, n: nails, c: ready mixed concrete 

C. Development of the Material Planning and Controlling 

Procedure Model 

The obtained regression model of reinforced concrete work 
materials will be absorbed by the existing procedure. The 
proposed revision procedure is a corrective plan that adds 
predictive capabilities based on historically valid information 
and thus improving the existing procedure. Although there is a 
volume analysis check, the additional process is necessary in 
order to minimize the causes of material control difficulties 
based on research observation results. The model of the 
procedure of material request submission control can be seen in 
Figure 1. The additional processes in this revised procedure 
include: 

• A controlling process of the material volume of reinforced 
concrete works by using the equation reference of 
regression models. This control uses the regression model 
of reinforced concrete works as an independent variable by 
relaying the predictive capability to the needs of various 
materials of reinforced concrete works. 

• An evaluation process of the submission of volume, 
inventory, and deviation of material waste. 

 

START

Acceptance of PRF submission / 

Purchase Request Form (materials 

& equipment)

PRF & Materials 

Analysis (limited)

Materials & 

Equipment 

Specification 

Check

Materials/Goods 

Volume Analysis 

Check

CONFORM?

Returning of 

the PRF to 

Project for 

Correction

Submission of PRF to 

Purchasing Department

Project Director Approval

APPROVED?

Ordered by Purchasing 

Department

To inform to project 

about PRF refusing

END

List of 

Materials & 

Equipment 

Specification

Materials 

Calculation 

Analysis

No

Yes

No

Yes

Controlling on 

materials of reinforced 

concrete work 

Evaluation on 

Materials Quantities, 

Available Stock & 

Level of Materials 

Waste 

Materials 

Regression 

Model

Budgeting 

Plan

 
Fig. 1.  Flowchart of the revised standard operating procedure 

V. CONCLUSION 

Various project problems that occur in the case of Duta 
Mall 2 project are caused by material controlling, especially 
regarding reinforced concrete works. The control of these 
materials becomes a critical point of the construction process of 
Duta Mall 2, and aside from its impact to cost it also has impact 
to the material quality and the schedule of work completion. 
Effective material control methods are required for complex 
and dynamic projects such as the construction of Duta Mall 2. 
The proposed method considers linear regression equation 
models between various material components of reinforced 
concrete works based on available historical data. The model 
equations that are formed can be modified by referring to one 
independent variable, i.e. the volume of ready mixed concrete. 
Other material components such as concrete steel, wire, 
plywood, timber, and nails can be planned more easily and 
according to its needs. The validated model of the equations 
can be an analysis tool in the control procedure model for 
material requests of reinforced concrete works. The evaluation 
of material waste that occurs can also be done during the works 
process. Another benefit from the regression model is that it 
can be a reference of cost budget calculations.  

REFERENCES 

[1] M. W. Newell, Preparing for the project management professional, 

American Management Association, 2002 

[2] D. Battini, M. Calzavara, I. Isolan, F. Sgarbossa, F. Zangaro, F. 

“Sustainability in material purchasing: A multi-objective economic order 
quantity model under carbon trading”, Sustainability, Vol. 2018, No. 10, 

Article ID 4438, 2018 

[3] C. March, Operations management for construction, Taylor and Francis, 
2009 

[4] I. Suharto, Project management from conceptual to operational, 

Erlangga, 2017 (in Indonesian) 

[5] Project Management Institute, Inc., A guide to the project management 
body of knowledge, Sixth Edition, Newtown Square, 2017 

[6] K. Kupusamy, S. Nagapan, A. H. Abdullah, S. Kaliannan, S. Sohu, S. 

Subramaniam, H. Maniam, “Construction waste estimation analysis in 
residential projects of malaysia”, Engineering, Technology & Applied 

Science Research, Vol. 9, No. 5, pp. 4842-4845, 2019 

[7] S. Sohu, A. H. Abdullah, S. Nagapan, T. A. Rind, A. A. Jhatial, 
“Controlling measures for cost overrun causes in highway projects of 

Sindh province”, Engineering, Technology & Applied Science Research, 
Vol. 9, No. 3, pp. 4276-4280, 2019 

[8] Q. Yu, K. Li, H. Luo, “A BIM-based dynamic model for site material 
supply”, Procedia Engineering, Vol. 164, pp. 526-533, 2016 

[9] R. E. Walpole, R. H. Myers, Probability & statistics for engineers & 

scientists, 9th edition, Prentice Hall, 2012 

[10] M. F. Quadratullah, Applied statistics: Theory, examples of cases and 
applications with SPSS, Andi Offset, 2014 (in Indonesian) 

[11] A. Mursadin, Module of applied statistical Volume 4: Measures of 

association, University of Lambung Mangkurat, 2019 (in Indonesian)