Microsoft Word - ETASR_V12_N1_pp8096-8100


Engineering, Technology & Applied Science Research Vol. 12, No. 1, 2022, 8096-8100 8096 
 

www.etasr.com Mahamid: Critical Factors Influencing the Bid / No Bid Decision in the Palestinian Construction Industry 

 

Critical Factors Influencing the Bid / No-Bid 

Decision in the Palestinian Construction Industry 

Ibrahim Mahamid 

Civil Engineering Department 

Arab American University 
Jenin, Palestine 

imahamid@ymail.com 
 

 

Abstract-The purpose of this study is to identify and rank the 
factors influencing the bid/no-bid decision according to their 

relative importance from the perspective of the contractors in the 

West Bank in Palestine. To achieve the study objectives, a 

questionnaire survey was conducted. The survey covered a 

randomly selected sample of 64 contractors involved in the 

construction industry in the West Bank. The questionnaire’s 

structure is based on the related literature, the pilot study, and 
the feedback from local experts in the construction industry. A 

total of 32 factors that might influence the bid/no-bid decision 

were identified and considered. Then, the targeted population 

was asked to rank these factors according to their relative 

importance. The results indicate that the top five factors affecting 

a contractor’s decision to bid or not include the financial stability 
of the client, the identity and reputation of the client in the 

industry, the promptness of the client in the payment process, the 

expected profitability, and the project’s source of funding. On the 

other hand, the least affecting factors are the type of the project, 

client’s requirements, taxes, laws and government regulations, 

and weather conditions. The paper provides a comprehensive 

understanding of the factors affecting the bidding decision. 
Construction parties and researchers could benefit from the 
results of this study. 

Keywords-bids; bid/no-bid; construction; contractors  

I. INTRODUCTION  

The construction industry is a major business sector that 
provides necessary ingredients for the development of an 
economy [1, 2]. For instance, as an industry sector, 
construction contributes about 10% of global GDP and absorbs 
more than 7% of labor [3]. However, it is becoming more and 
more complex due to the huge number of parties involved in 
the construction process and of the sophistication of the process 
itself. According to [4], the construction industry is the 
business sector that faces most failures in comparison to other 
industries. This happens because it is too risky and full with 
uncertainties [5]. In Palestine, the construction industry plays a 
critical role in providing homes, infrastructure, and public 
facilities. It also plays a major role in absorbing the national 
workforce and in improving the Palestinian national economy 
as a whole. According to [6], the construction activities in 
Palestine absorb about 17.9% of national workforce. In 2011 
and 2012, the construction industry accounted for 11.2% and 
10.3% of the value added to the Gross Domestic Product 
(GDP) [6]. However, many local construction projects report 

poor performance due to reasons such as 21-
4538_s_ETASR_V12_N1_pp8096-8100 shortage in skilled 
labor or materials, bad relations between the construction 
parties, shortcomings in bidding strategy, and lack of 
managerial skills [7].  

Construction projects, public and private, are usually 
awarded to contractors via tenders. The bidding process 
involves the bid/no-bid decision which is crucial and associated 
with risks and uncertainties due to various factors that 
influence it [8]. The influencing factors might relate to the 
contractor himself, to the client, or to the project conditions and 
the general environment. Bidding decision problems are highly 
unstructured. Typically, contractors make their decisions based 
on their common sense or the rule of thumb which may lead to 
suboptimal decisions. This is why many researchers have been 
involved in the development of bidding strategy models. The 
objective of this study is to identify and rank the factors that 
might influence the bid/no-bid decision according to their 
relative importance from the perspective of the contractors in 
West Bank, Palestine. The next sections provide a summary of 
the previous studies conducted to identify the related factors, 
the research methods and the study results. 

II. PREVIOUS STUDIES 

The literature abounds with studies that have investigated 
the topic of bidding decisions and the relative strategy. Many 
of these studies focused on identifying the main factors 
influencing the bid/no-bid decision in construction projects. 
Authors in [9] concluded that the critical factors affecting the 
bidding decision in Saudi Arabia to be client financial capacity, 
prompt payments, project payment system, clarity of the work 
and specifications, and project cash flow. Authors in [10] 
conducted a study to identify the factors affecting the bidding 
decision in construction projects in Qatar, and found 10 critical 
factors. Authors in [11] revealed that bidding policy has a high 
impact on variation orders during the construction phase. 
Authors in [8] identified and ranked the factors that affect the 
bid/no-bid decision from the contractors’ perspective. The 
factors are classified into 4 groups: (a) external environmental 
factors, (b) factors related to the contractor, (c) factors related 
to the clients, (d) factors related to contract and project 
characteristics. They found that the top affecting factors 
include the stability of the construction industry, the 
contractor's financial capability, the reputation of the client, and 

Corresponding author: Ibrahim Mahamid



Engineering, Technology & Applied Science Research Vol. 12, No. 1, 2022, 8096-8100 8097 
 

www.etasr.com Mahamid: Critical Factors Influencing the Bid / No Bid Decision in the Palestinian Construction Industry 

 

the financial value of the project. The author in [12] considered 
the bid/no-bid decision factors in Auckland with the utilization 
of face-to-face structured interviews incorporating a 
questionnaire. He concluded that bid/ no-bid decision making 
is very dependent on the location. He also indicated that the 
macro environment has a great influence on bidding decision. 
Authors in [13] reported a significant negative relationship 
between risk perception and bidding decision and a significant 
positive relationship between risk propensity and bidding 
decision.  

Authors in [14] conducted a study to investigate and rank 
the critical factors influencing the bid/no-bid decision criteria 
and their importance in the Australian construction industry. 
They identified the 26 most common decision-making criteria 
and they accordingly grouped them into 5 categories, namely 
project, market, contractor, client, and contract. Using a 
questionnaire survey, they revealed that the most highly ranked 
factors are: client financial capability, project risk, project 
future benefits, profitability, and number of competitors. 
Authors in [15] stated that one of the critical decisions taken by 
contractors is whether or not to bid for a project, due to the 
complexity and uncertainty surrounding this decision, which is 
influenced by many factors. They conducted a study in Saudi 
Arabia to find out the key factors affecting the contractors’ 
bidding decisions in construction projects. They concluded that 
the top 6 (out of 31) critical factors were: project size, project 
type, company strength, design quality, expected profit, and 
cash flow. Authors in [16] conducted a study to identify the 
main factors influencing contractors’ bidding decisions in 
construction projects in Nigeria. They concluded that the most 
significant factors affecting the bid/no-bid decision are: 
financial capability of clients, availability of capital, and 
availability of material. Author in [17] conducted a study to 
identify the factors affecting the bidding and markup decisions 
of contractors, considering a total of 55 factors. The top 3 
factors were the need for work, the number of competitors, and 
the amount of experience on such projects.  

Authors in [18] indicated that the decision to bid is a 
complex activity that requires the consideration of several 
factors. These factors can be related to capability, time 
requirement, and cost implication. They performed a study to 
evaluate the factors related to time and cost performance to test 
their effect on the bidding decision. Structured questionnaires 
were used to gather data from construction professionals in 
both consulting and contracting firms. The study reported the 
reputation of the client as the most critical factor related to time 
performance that influences bidding decisions, while location 
and condition of the site were identified as the key factors 
related to cost performance. Thus, the reputation of the client, 
the location, and the condition of the site should be given the 
most priority by a contractor at the time of bidding. Authors in 
[19] investigated the factors affecting bid/no-bid decisions of 
international projects in Chinese construction projects. A total 
of 41 factors were identified through a literature review as 
having an impact on the bid decision. Ultimately, 9 main 
factors were identified as influencing the bidding decision, with 
contractor’s capability and country risk of the host country, 
being the most important.  

Authors in [20] investigated and ranked the critical factors 
influencing the bid or no-bid decision and their importance for 
the indigenous small building contractors within the Tanzanian 
construction industry. The 7 most highly ranked factors (among 
the 30 considered) are: availability of capital, financial 
condition of the client, project size, expected profit, project 
type, need of work, and current workload. Authors in [21] 
examined the effects of different factors on the success or 
failure of bids for infrastructure projects in Australia. They 
found that the most significant factors that increase the success 
chances of bid are: having a competitive advantage and a local 
partner and also not competing against a local company. They 
also concluded that the essential factors to be able to compete 
include: relevant expertise, resource availability, previous 
relationship with the client, and previous relationship with 
consortium members. Authors in [22] and [23] linked the 
delays in construction projects and bid award policy. 

III. RESEARCH METHOD 

Thirty two (32) factors that might affect the bid/no-bid 
decision were identified from the literature review and the 
feedback from local construction experts. The factors were 
tabulated in a questionnaire. The questionnaire was developed 
to evaluate the importance of the identified factors from the 
target population (contractors). The information was collected 
from the Palestinian Contractors Union (PCU). The survey was 
used as a tool to collect the data, and then the data were 
analyzed with the Relative Importance Index (RII).  

A. Questionnaire Design 

The questionnaire is divided into two parts. Part 1 includes 
general questions related to the respondent and company such 
as the respondent’s role in the company, experience in the line 
of work, decision makers in the company, etc. Part 2 included 
the list of factors affecting the bid/no-bid decision in 
construction projects. These factors were categorized into 4 
groups according to their sources, namely: (1) factors related to 
client characteristics, (2) factors related to contractor 
characteristics, (3) factors related to contract and project 
characteristics, (4) factors related to the general environment. 
The respondents were asked to identify the impact level of each 
factor on the bidding decision. Impact level is classified on a 4-
point scale as follows: very important, important, somewhat 
important, and not important (a 4 to 1 point scale). 

B. Study Population 

The target population in this study is the total number of 
contractors with valid registration in the Palestinian 
Contractors Union (PCU) with grade 1, grade 2 and grade 3 
(120 registered contractors). Equation (1) was used to calculate 
the representative sample size [24]: 

n = n'/(1 + n'/N)           (1) 

where n is the sample size of the population, n' is the sample 
size, which can be calculated from: [n' = S²/V²], N is the total 
population (120 contractors), V is the standard error of sample 
population, equal to 0.05 for 95% confidence level, t =1.96, S² 
is the standard error variance of population elements,  
S² = P (1-P), maximum at P = 0.5. 



Engineering, Technology & Applied Science Research Vol. 12, No. 1, 2022, 8096-8100 8098 
 

www.etasr.com Mahamid: Critical Factors Influencing the Bid / No Bid Decision in the Palestinian Construction Industry 

 

The sample size for the contractors' population can be 
calculated from (1) as follows: 

n' = S² / V² = (0.5)² / (0.05)² = 100 

n contractors = 100/(1 + 100/120) = 54 

which means that the minimum sample size needed for this 
study is 54 respondents. 

The questionnaire was distributed to 80 contractors. The 
contractors were selected randomly from an available list 
obtained from the PCU. Sixty-four questionnaires were 
received (response rate = 80%). The respondents indicate that 
the bidding decision is mostly taken by the general manager of 
the company (92% of the cases) and sometimes by the project 
manager (8% of cases). Figure 1 shows the respondents’ 
positions in their organizations. The distribution of the 
respondents’ years of experience in the line of work indicates 
that 13.2% had less than 5 years of experience, 18.8% had 
between 5 and 10 years of experience, 45.9% had between 10 
and 20 years of experience, and 32.1% had more than 20 years 
of experience. The distribution of project types that the 
respondents are involved in shows that 52% are involved in 
building construction projects, 18% are involved in 
infrastructure projects, and 30% are involved in both building 
and infrastructure projects. 

 

 
Fig. 1.  Respondents’ position. 

C. Data Analysis 

The statistical tools of Microsoft Excel were used to 
analyze the collected data. The considered factors were ranked 
by the measurement of RII, which is calculated based on the 
importance level identified by the respondents. RII can be 
calculated according to (2): 

RII% =
	�	�	��	�	�	�	��	�	�	�	��	�	�	�	��

�	�	�
 ×100%   (2) 

where N4, N3, N2, N1 represent the number of respondents for 
very important, important, little important, not important and N 
it the total number of respondents. For example, the RII% of 
the "financial stability of client", which got these values: N4 = 
33, N3 = 30, N2 = 1, N1 = 0 from the survey, is: 

RII% = 
�	�	��	�	�	�	�		�	�	�	�	�			�	�

�	�	
�
� 100%  = 87.50% 

The group index is calculated by using the average of 
factors under each group as shown in (3):  

Group importance index (%) =	∑ Xi/n��     (3) 

where Xi is the relative importance index of factor i under the 
group and n is the number of factors under the group. 

IV. RESULTS AND DISCUSSION 

The factors under each group are ranked by the 
measurement of RII according to (2).  

A. General Environment Factors 

Table I shows the RII and the ranking of each factor under 
the general environment group from contractors’ view. Seven 
factors are considered under this group. The results show that 
the top 3 factors are: economic environment (RII = 80.64%), 
political situation (RII = 77.27%) and probable number and 
identity of competitors (RII = 76.59%). 

TABLE I.  RANKING OF GENERAL ENVIRONMENT FACTORS 

Factors related to the general environment group RII% Rank 

Economic environment 80.64 1 

Political situation 77.27 2 

Probable number and identity of competitors 76.59 3 

Inflation rate 69.21 4 

Taxes 62.50 5 

Laws and government regulations 58.47 6 

Weather conditions 54.45 7 

 

B. Factors Related to the Contract and Project 

Characteristics 

Nine factors are identified under this group. Table II shows 
the RII and ranking of each factor under the contract and 
project characteristics group from the contractors’ point of 
view. The results show that the top 3 factors are: size or project 
(RII = 82.19%), location of project and accessibility (RII = 
80.88%) and adequacy of tender information (RII = 78.25%). 

TABLE I.  RANKING OF CONTRACT AND PROJECT CHARACTERITICS 
FACTORS 

Factors related to the contract and project 

characteristics 
RII % Rank 

Size of project 82.19 1 

Location of project and accessibility 80.88 2 

Adequacy of tender information 78.25 3 

Identity of consultant & designer   75.62 4 

Contract duration 71.01 5 

Complexity of the project 69.69 6 

Time available for tendering preparation 69.69 6 

Contract conditions 67.72 8 

Type of roject 67.06 9 

 

C. Factors Related to the Client Characteristics 

Table III shows the RII and ranking of each of the 7 
considered factors under the client group. The results indicate 
that the top 3 factors under this group are: financial stability of 
the client (RII = 87.21%), identity and reputation of client in 
the industry (RII = 86.15%), and promptness of the client in 
payment process (RII = 84.91%). 

D. Factors Related to Contractor Characteristics 

Table IV shows the RII and ranking of each of the 9 factors 
under the contractor group. The results indicate that the top 3 
factors under this group are: expected profitability (RII = 
83.80%), current workload (RII = 82.46%), and need for work 
(RII = 81.79%). 



Engineering, Technology & Applied Science Research Vol. 12, No. 1, 2022, 8096-8100 8099 
 

www.etasr.com Mahamid: Critical Factors Influencing the Bid / No Bid Decision in the Palestinian Construction Industry 

 

TABLE II.  RANKING OF CLIENT CHARACTERITICS FACTORS 

Factors related to client characteristics RII% Rank 

Financial stability of the client 87.21 1 

Identity and reputation of the client in the industry 86.15 2 

Promptness of client in payments process 84.91 3 

Project source of funding 83.24 4 

Previous experience of contractor with the employer 73.05 5 

Type of client 72.4 6 

Client’s requirements 66.48 7 

TABLE III.  RANKING OF CONTRACTOR CHARACTERITICS FACTORS 

Factors related to contractor characteristics RII% Rank 

Expected profitability 83.80 1 

Current workload 82.46 2 

Need for work 81.79 3 

Classification criteria for the contractors 81.12 4 

Strategy of the company 78.43 5 

Availability of required cash 76.13 6 

Availability of required resources (raw materials, 

labors, equipment) 
74.41 7 

Previous experience in similar projects 71.72 8 

Pre-qualification requirement 71.05 9 

 

E. Overall Ranking 

The RII and ranking of the investigated 32 factors affecting 
the bidding decision in construction projects in the West Bank 
from the contractors’ view are listed in Table V. The results 
show that the top 5 factors are: financial stability of the client, 
identity and reputation of client in the industry, promptness of 
the client in payment process, expected profitability, and 
project source of funding, whereas the least affecting factors 
are: type of project, client’s requirements, taxes, laws and 
government regulations, and weather conditions. It can be 
noted that among the top 5 factors, 4 factors are related to the 
client characteristics group, while the 5th factor is related to 
contractor characteristics group.  

1) Financial Stability of the Client 

In general, financial stability of the client indicates his 
ability to meet debts as they fall due. Financial stability in 
construction leads to good cash flow for contractors during the 
project which implies that the contractor will be able to pay for 
labor, materials, equipment, and other expenditures. In contrast, 
instability of the clients’ economic condition leads to payment 
delay which affects the contractor’s financial abilities and 
might lead to poor project performance. This result is in line 
with the findings in [1, 8-10]. 

2) Identity and Reputation of the Client 

A contractor seeks smooth performance for his project. His 
performance will affect his reputation in the industry. 
Therefore, clients with good reputation will encourage the 
contractors to take the bidding decision more comfortably. On 
the other hand, bad reputation of the client will make the 
bidding decision to be more difficult, since bad expectations, 
such as financial problems and delays, will come to mind along 
with the fact that this may affect the reputation of the 
contractor himself. This result is in line with the findings in 
[10]. 

3) Promptness of Client in Payment Process 

Contractors take into considerations in their deals, the 
client’s payment process during the project. It is very important 
for the contractor to have good cash flow conditions in order to 
continue the work smoothly. Therefore, promptness in payment 
of the client is considered as a very important factor that the 
contractors care about during their bidding decision. Clients 
that make payments on time will encourage contractors to deal 
with them and will facilitate their decision to bid. Conversely, 
delays in payments might lead to conflicts between 
construction parties which might affect the process of bidding 
decision making. This result agrees with [9]. 

4) Project Source of Funding 

The source of funding of the project is one of the main 
factors that the contractors have to know before making their 
decision to bid. The source of funding may be a person, private 
institutions, governmental institutions, or donors. Each source 
has its advantages and disadvantages. Fund sources may differ 
in their financial stability, payment methods, and promptness. 
Moreover, contractors may prefer a specific source of funding 
over the others as they may have previous experience with it 
and this will significantly affect their bidding decision.  

5) Expected Profitability 

Expected profitability is a significant factor that affects the 
bidding decision. If the contractor feels that he will not achieve 
the expected profit, he probably will not enter the tender. The 
profit made in projects that the contractor experienced in the 
past could possibly forecast the possible profit that can be made 
from the proposed project. Usually, contracting companies 
submit for bids and opportunities that are expected to exceed 
the Minimum Acceptable Rate of Return (MARR). Normally, 
there is no need for contractors to submit bids when the 
expected profit is less that the targeted one. However, in some 
cases the contractors are forced to bid for projects that do not 
exceed the MARR due to reasons such as the need for work 
and to cover overhead costs. This result is in line with [14, 15]. 

TABLE IV.  TOP FIVE FACTORS AFFECTING BID/NO BID DECISION 

Factor RII% Overall rank 

Financial stability of the client 87.5 1 

Identity and reputation of the client in the industry 86.15 2 

Promptness of client in payments process 84.91 3 

Expected profitability 83.80 4 

Project source of funding 83.24 5 

 

V. CONCLUSION  

In this paper, a total of 32 factors affecting the bidding 
decision in construction projects were identified and 
categorized in 4 groups. The identified factors were ranked 
according to the RII of the contractors’ point of view in the 
West Bank in Palestine. Overall, the results indicate that the top 
5 factors affecting a contractor’s decision to bid or not are the 
financial stability of the client, the identity and reputation of the 
client in the industry, the promptness of client in payment 
process, the expected profitability, and the project's source of 
funding.  

Economic environment, political situation, and the probable 
number and identity of competitors are ranked in the top 3 



Engineering, Technology & Applied Science Research Vol. 12, No. 1, 2022, 8096-8100 8100 
 

www.etasr.com Mahamid: Critical Factors Influencing the Bid / No Bid Decision in the Palestinian Construction Industry 

 

positions under the environment group. Laws and government 
regulations in construction and weather conditions are ranked 
in the bottom 2 positions as factors having a weak influence on 
the bidder’s decision. Size, location, and accessibility of the 
project along with the adequacy of tender information are 
considered key factors affecting a contractor’s decision to 
participate in tenders. Therefore, full and clear tender 
information should be provided by the owner and consultants 
to help contractors in taking the bidding decision. Contract 
conditions and type of project are ranked in the lowest 2 
positions and have a weak influence on a bidder’s behavior. 
The current workload and the need of work are identified as the 
top factors affecting contractor’s strategy in bidding. Current 
and projected workload should be known to the contractor in 
order to be able to know whether to bid or not. The contractor 
doesn’t want to exceed his capabilities because this might 
affect his performance and lead to negative effects in terms of 
delay and disputations with the owners. On the other hand, 
contractors with low current workload will bid for projects 
even though these projects may not achieve the expected 
profits or the MARR in order to cover the job overhead costs 
and the operating costs.  

VI. REFERENCES 

[1] B. Santosh, "Risk Management in Building Projects: Owners’ 
Perspective," The Islamic University Journal (Series of Natural Studies 

and Engineering), vol. 16, no. 1, pp. 95–123, 2008. 

[2] R. W. Liebing, The Construction Industry: Processes, Players, and 
Practices, 1st ed. Upper Saddle River, N.J, USA: Pearson, 2000. 

[3] "Construction," Wikipedia. Dec. 13, 2021, Accessed: Dec. 20, 2021. 

[Online]. Available: https://en.wikipedia.org/w/index.php?title= 
Construction&oldid=1060139590. 

[4] R. J. Chapman, "The controlling influences on effective risk 

identification and assessment for construction design management," 
International Journal of Project Management, vol. 19, no. 3, pp. 147–

160, Apr. 2001, https://doi.org/10.1016/S0263-7863(99)00070-8. 

[5] I. Mahamid, A. Bruland, and N. Dmaidi, "Causes of Delay in Road 
Construction Projects," Journal of Management in Engineering, vol. 28, 

no. 3, pp. 300–310, Jul. 2012, https://doi.org/10.1061/(ASCE)ME.1943-
5479.0000096. 

[6] "PCBS | Indicators," Palestinian Centre Bureau of Statistics (PCBS). 

https://www.pcbs.gov.ps/site/881/default.aspx%20-%20Population 
(accessed Dec. 20, 2021). 

[7] I. Mahamid, "Analysis of schedule deviations in road construction 
projects and the effects of project physical characteristics," Journal of 

Financial Management of Property and Construction, vol. 22, no. 2, pp. 
192–210, Jan. 2017, https://doi.org/10.1108/JFMPC-07-2016-0031. 

[8] A. Enshassi, S. Mohamed, and A. El Karriri, "Factors affecting the 

bid/no bid decision in the Palestinian construction industry," Journal of 
Financial Management of Property and Construction, vol. 15, no. 2, pp. 

118–142, Jan. 2010, https://doi.org/10.1108/13664381011063421. 

[9] A. Bageis and C. Fortune, "Factors affecting the bid/no bid decision in 
the Saudi Arabian construction contractors," Construction Management 

& Economics, vol. 27, no. 1, pp. 53–71, Jan. 2009, https://doi.org/ 
10.1080/01446190802596220. 

[10] A. M. Jarkas, S. A. Mubarak, and C. Y. Kadri, "Critical Factors 

Determining Bid/No Bid Decisions of Contractors in Qatar," Journal of 
Management in Engineering, vol. 30, no. 4, Jul. 2014, Art. no. 

05014007, https://doi.org/10.1061/(ASCE)ME.1943-5479.0000223. 

[11] W. M. A. Khalifa and I. Mahamid, "Causes of Change Orders in 
Construction Projects," Engineering, Technology & Applied Science 

Research, vol. 9, no. 6, pp. 4956–4961, Dec. 2019, https://doi.org/ 
10.48084/etasr.3168. 

[12] H. Ma, "Factors affecting the bid/ no bid decision making process of 
small to medium size contractors in Auckland," Unpublished document 

submitted in partial fulfilment of the requirements for the degree of 
Bachelor of Construction, Unitec Institute of Technology, New Zealand, 

2011. 

[13] Y. Q. Chen, S. J. Zhang, L. S. Liu, and J. Hu, "Risk perception and 
propensity in bid/no-bid decision-making of construction projects," 

Engineering, Construction and Architectural Management, vol. 22, no. 
1, pp. 2–20, Jan. 2015, https://doi.org/10.1108/ECAM-01-2013-0011. 

[14] M. Shokri-Ghasabeh and N. Chileshe, "Critical factors influencing the 

bid/no bid decision in the Australian construction industry," 
Construction Innovation, vol. 16, no. 2, pp. 127–157, Jan. 2016, 

https://doi.org/10.1108/CI-04-2015-0021. 

[15] M. Alsaedi, S. Assaf, M. A. Hassanain, and A. Abdallah, "Factors 

Affecting Contractors’ Bidding Decisions for Construction Projects in 
Saudi Arabia," Buildings, vol. 9, no. 2, Feb. 2019, Art. no 33, 

https://doi.org/10.3390/buildings9020033. 

[16] O. Oyeyipo, K. T. Odusami, R. A. Ojelabi, and A. O. Afolabi, "Factors 
Affecting Contractors’ Bidding Decisions for Construction Projects in 

Nigeria," Journal of Construction in Developing Countries, vol. 21, no. 
2, pp. 21–35, Dec. 2016. 

[17] A. A. Shash, "Factors considered in tendering decisions by top UK 

contractors," Construction Management and Economics, vol. 11, no. 2, 
pp. 111–118, Mar. 1993, https://doi.org/10.1080/01446199300000004. 

[18] A. Oke, A. Omoraka, and A. Olatunbode, "Appraisal of factors affecting 

bidding decisions in Nigeria," International Journal of Construction 
Management, vol. 20, no. 2, pp. 169–175, Mar. 2020, https://doi.org/ 

10.1080/15623599.2018.1484846. 

[19] G. Li, C. Chen, G. Zhang, and I. Martek, "Bid/no-bid decision factors for 
Chinese international contractors in international construction projects," 

Engineering, Construction and Architectural Management, vol. 27, no. 
7, pp. 1619–1643, Jan. 2019, https://doi.org/10.1108/ECAM-11-2018-

0526. 

[20] N. Chileshe, N. Kavishe, and D. J. Edwards, "Critical factors influencing 
the bid or no-bid decision of the indigenous small building contractors in 

Tanzania," Construction Innovation, vol. 21, no. 2, pp. 182–202, Jan. 
2020, https://doi.org/10.1108/CI-09-2019-0098. 

[21] B. Aznar, E. Pellicer, S. Davis, and P. Ballesteros-Pérez, "Factors 
affecting contractor’s bidding success for international infrastructure 

projects in Australia," Journal of Civil Engineering and Management, 
vol. 23, no. 7, May 2017, https://doi.org/10.3846/13923730.2017. 

1341955. 

[22] F. A. Soomro, M. J. Memon, A. F. Chandio, S. Sohu, and R. Soomro, 
"Causes of Time Overrun in Construction of Building Projects in 

Pakistan," Engineering, Technology & Applied Science Research, vol. 9, 
no. 1, pp. 3762–3764, Feb. 2019, https://doi.org/10.48084/etasr.2449. 

[23] K. M. M. El-Dash, O. M. O. Ramadan, and W. M. M. A. Youssef, 

"Duration Prediction Models for Construction Projects in Middle East," 
Engineering, Technology & Applied Science Research, vol. 9, no. 2, pp. 

3924–3932, Apr. 2019, https://doi.org/10.48084/etasr.2531. 

[24] L. Kish, Survey Sampling. New York, NY, USA: Wiley-Interscience, 
1995. 

 

AUTHORS PROFILE 

 

Ibrahim Mahamid received his BSc in Civil Engineering from Birzeit 

University of Palestine in 2001, and his PhD in Construction Engineering and 

Project Management from Norwegian University of Science and Technology 

(NTNU), Norway in 2011. He is currently the head and an associate professor 

at the Civil Engineering Department, Arab American University, Palestine. 

His research interests include construction engineering and surveying.