DECLARATION OF CONFLICTING INTEREST The author(s) declared no potential conflicts of interest with respect to the research, authorship, and/or publication of this article. FUNDING The author(s) received no financial support for the research, authorship, and/or publication of this article. 1 Project Management Research and Practice Vol. 4 Jan.-June 2017 © 2017 by the author(s). This is an Open Access article distributed under the terms of the Creative Commons Attribution 4.0 International (CC BY 4.0) License (https:// creativecommons.org/ licenses/by/4.0/), allowing third parties to copy and redistribute the material in any medium or format and to remix, transform, and build upon the material for any purpose, even commercially, provided the original work is properly cited and states its license. Citation: Pasian, B.L. 2017. Editorial: We need to use the words … . Project Management Research and Practice, 4, 5405. http://dx.doi.org/10.5130/ pmrp.v4i0.5405 ISSN 2207-1415 | Published by UTS ePRESS | http://pmrp. epress.lib.uts.au PAGE NUMBER NOT FOR CITATION PURPOSES Sometimes it’s important to simply say the words … as it is in the beginning of wisdom that is the definition of terms. When historians look at the world of project management, what will they say that we have said about climate change? Certainly more general—but absolutely legitimate—terms such as ‘sustainability’ have been used, but in a basic term search in the 3 oldest project management journals, I was surprised to see only a few dozen uses of ‘climate change’ as a specific term. The conversation started a long time ago using those words, and PMRP would like to encourage more with this commentary on one of the central topics of this journal … climate change. Declarations have been made of the importance and necessity of the project management community to turn its attention toward climate change. The first was more than 25 years ago, when Laszlo (1991) indicated ‘the dangers of atmospheric warming and climate change ... as threats that face all societies, in every part of the world.’ He was commenting on the ‘unique role and great responsibility’ that project managers have to help organizations meet global problems. Morris has since made multiple entreaties in our journals as he raises our awareness to the scales and complexities of the 21st century (2012). He challenges us to move beyond scope, budget and timeliness and focus on the impact of our work as humankind faces the inevitable threat of climate change (Morris, 2013; Morris, 2016). Specific tools and methodologies have been carefully investigated in various regions and industries (T. Wang, Wang, Zhang, Huang, & Li, 2016; Y. Wang, Han, de Vries, & Zuo, 2016; Wong, Ng, & Shahidi, 2013). An emphasis has emerged on risk assessment and management with Loosemore (2010) describing, for example, multimedia technology used to engage stakeholders in risk management processes. It is positioned for possible application in a climate change strategy. Zhang (2007), in one of the earliest mentions of climate change in a project management journal, also addresses risk management and notes that the ‘influence of systems on risk consequences has been comprehensively assessed in climate change studies.’ Wang et al. propose an infrastructure assessment framework, and apply it on a cross-sea route project in the South China Sea. Disasters such as floods, drought, and heat waves (among others) associated with climate change are increasingly the focus of the project management community. Researchers EDITORIAL We need to use the words … Beverly L. Pasian Associate Professor, Institute of Business Administration, Utrecht University of Applied Sciences, Utrecht, The Netherlands. beverly.pasian@hu.nl DOI: http://dx.doi.org/10.5130/pmrp.v4i0.5405 https://creativecommons.org/licenses/by/4.0/ https://creativecommons.org/licenses/by/4.0/ https://creativecommons.org/licenses/by/4.0/ http://dx.doi.org/10.5130/pmrp.v4i0.5405 http://dx.doi.org/10.5130/pmrp.v4i0.5405 http://pmrp.epress.lib.uts.au http://pmrp.epress.lib.uts.au mailto:beverly.pasian@hu.nl http://dx.doi.org/10.5130/pmrp.v4i0.5405 Pasian Project Management Research and Practice, Vol. 4 Jan.-June 20172 PAGE NUMBER NOT FOR CITATION PURPOSES (Kim & Choi, 2013; Steinfort, 2016) are advocating the use of new program management methodology specifically for use by communities recovering from such catastrophes. Notably, Steinfort makes the point that there must first be the ‘realisation’ of climate change as a threat – something done by Klagegg & Haavaldsen (2011) when discussing the necessity for clarity in definitions and principles both in governance and project management. Staadt (2012) further explains the ‘vital role’ public organizations can play in realizing societal projects. New calls for expanded practitioner competencies have been made in the face of natural disasters and increasing challenges associated with climate change. First among these was Saynisch (RW.ERROR - Unable to find reference:4079) who focused on the ICCPM standard. He characterized it as an ‘emerging natural extension of traditional project management to create a specialist profession’ that can focus on the large projects such as climate change, international aid and others.’ In discussing the need to focus on the professionalism of project management, Konstantinou (2015) explains that ‘time critical problems’ such as climate change require ‘situated project knowledge.’ A more ‘meaningful’ relationship to researchers is needed to do this. Adhazie et al. (Ahadzie, Proverbs, & Sarkodie-Poku, 2014) highlight the competencies of project managers ‘at the design phase of mass building projects.’ They do this, in part, by referencing Malmquits and Glauman (2009) who argue that, as the building sector contributes to the challenge of climate change, a more ‘holistic approach’ for communicating design-related information to actors is needed. Central to supporting project management ‘actors’ is the work of professional associations but as Morris observes ‘project management [has been] almost silent on how to address’ challenges such as climate change (2013). The few references found for this commentary unfortunately seem to confirm this amongst the research community. Voices have been heard, on the other hand, by leading project management practitioner groups. The first articulation of the roles and responsibilities of a project manager in addressing the challenges associated with climate change occurred in the GPM P5 Standard for Sustainability in Project Management (GPM, 2014). A modest development occurred later with the latest version of the IPMA Individual Competency Baseline for Project, Programme and Portfolio Management (Version 4) that recognizes the critical role of sustainability practices in the competence of a project manager (IPMA, 2015). These efforts reflect the growing understanding that ‘doing good projects, good in projects, and good through projects must be heralded as overarching principles for shaping, managing, as well as researching projects’ (Geraldi & Söderlund, 2016). Project management researchers, if this brief review is any indication, are less vocal. And it is through submissions to PMRP that the words can be shared to further document our understanding and empower project managers to meet the challenges associated with climate change. To encourage submissions on this topic, PMRP would like researchers and practitioners to consider the following questions: • What competences are valuable in managing projects related to climate change? • What are the challenges and opportunities for project teams in dealing with climate change? • Does the project management community have a role to play in shaping public policy concerned with the environment? • What methodological strategies can serve project management researchers in their associated investigations in matters related to environment issues? Pasian Project Management Research and Practice, Vol. 4 Jan.-June 20173 PAGE NUMBER NOT FOR CITATION PURPOSES This commentary represents the first of a series dedicated to exploring the attention paid by project management researchers on the ’17 Sustainable Development Goals’ identified in September, 2015 by the United Nations. Each will serve to introduce PMRP’s commitment to each specific topic and encourage ongoing submissions. About the Editor Dr. Beverly Pasian is an avid educator, researcher, author and association leader committed to the development of project management as a tool to address critical public priorities. Her research collaborations have spanned the globe to examine project management from various industry, sector and topical perspectives (including project management maturity, e-Learning, construction consulting services, and ‘human factors’ such as trust, motivation and creativity). Multiple books are amongst her publication credits including Designs, Methods & Practices for Research of Project Management (Gower Publishing) and ‘Plan to Learn: Case studies in eLearning project management (CeLEA). Her immediate publications include A book for practitioners will be her next project, with an interpretative focus on award-winning research specifically written for project managers. References Ahadzie, D.K., Proverbs, D.G., & Sarkodie-Poku, I. 2014, ‘Competencies required of project managers at the design phase of mass house building projects’, International Journal of Project Management, vol. 32 no. 6, 958-969, http://dx.doi.org/10.1016/j.ijproman.2013.10.015 Geraldi, J. & Söderlund, J. 2016, ‘Project studies and engaged scholarship: Directions towards contextualized and reflexive research on projects’, International Journal of Managing Projects in Business, vol. 9 no. 4, 767-797, https://doi.org/10.1108/IJMPB-02-2016-0016 GPM 2014, The GPM global P5 standard for sustainability in project management (1st ed.). USA: GPM Global. IPMA 2015, Individual competence baseline for PPPM (4th ed.). Zurich, Switzerland: International Project Management Association. Kim, K.N. & Choi, J. 2013, ‘Breaking the vicious cycle of flood disasters: Goals of project management in post-disaster rebuild projects’, International Journal of Project Management, vol. 31 no. 1, 147-160, http:// dx.doi.org/10.1016/j.ijproman.2012.03.001 Klakegg, O.J. & Haavaldsen, T. 2011, ‘Governance of major public investment projects: In pursuit of relevance and sustainability’, International Journal of Managing Projects in Business, vol. 4 no. 1, 157-167, https://doi.org/10.1108/17538371111096953 Konstantinou, E. 2015, ‘Professionalism in project management: Redefining the role of the project practitioner’, Project Management Journal, vol. 46 no. 2, 21-35, https://doi.org/10.1002/pmj.21481 Laszlo, E. 1991, ‘Responsible (project) management in an unstable world’, International Journal of Project Management, vol. 9 no. 2, 68-70, https://doi.org/10.1016/0263-7863(91)90061-Y Loosemore, M. 2010, ‘Using multimedia to effectively engage stakeholders in risk management’, International Journal of Managing Projects in Business, vol. 3 no. 2, 307-327, https://doi. org/10.1108/17538371011036608 http://dx.doi.org/10.1016/j.ijproman.2013.10.015 https://doi.org/10.1108/IJMPB-02-2016-0016 http://dx.doi.org/10.1016/j.ijproman.2012.03.001 http://dx.doi.org/10.1016/j.ijproman.2012.03.001 https://doi.org/10.1108/17538371111096953 https://doi.org/10.1002/pmj.21481 https://doi.org/10.1016/0263-7863(91)90061-Y https://doi.org/10.1108/17538371011036608 https://doi.org/10.1108/17538371011036608 Pasian Project Management Research and Practice, Vol. 4 Jan.-June 20174 PAGE NUMBER NOT FOR CITATION PURPOSES Malmqvist, T., & Glaumann, M. 2009, ‘Environmental efficiency in residential buildings – A simplified communication approach’, Building and Environment, vol. 44 no. 5, 937-947, http://dx.doi.org/10.1016/j. buildenv.2008.06.025 Morris, P.W.G. 2012, ‘Cleland and king: Project management and the systems approach’, International Journal of Managing Projects in Business, vol. 5 no. 4, 634-642, https://doi. org/10.1108/17538371211268951 Morris, P.W.G. 2013, ‘Reconstructing project management reprised: A knowledge perspective’, Project Management Journal, vol. 44 no. 5, 6-23, https://doi.org/10.1002/pmj.21369 Morris, P.W.G. 2016, ‘Reflections’, International Journal of Project Management, 34, 365-370, https://doi. org/10.1016/j.ijproman.2015.08.001 Staadt, J. 2012, ‘Redesigning a project-oriented organization in a complex system: A soft systems methodology approach’, International Journal of Managing Projects in Business, vol. 5 no. 1, 51-66, https:// doi.org/10.1108/17538371211192892 Steinfort, P. 2016, ‘Community and post-disaster program management methodology’, International Journal of Project Management, vol. 34 no. 6, http://dx.doi.org/10.1016/j.ijproman.2016.07.005 Wang, T., Wang, S., Zhang, L., Huang, Z. & Li, Y. 2016, ‘A major infrastructure risk-assessment framework: Application to a cross-sea route project in china’, International Journal of Project Management, vol. 34 no. 7, 1403-1415, http://dx.doi.org/10.1016/j.ijproman.2015.12.006 Wang, Y., Han, Q., de Vries, B., & Zuo, J. 2016, ‘How the public reacts to social impacts in construction projects? A structural equation modeling study’, International Journal of Project Management, vol. 34 no. 8, 1433-1448, http://dx.doi.org/10.1016/j.ijproman.2016.07.008 Wong, P.S.P., Ng, S.T.T., & Shahidi, M. 2013, ‘Towards understanding the contractor’s response to carbon reduction policies in the construction projects’, International Journal of Project Management, vol. 31 no. 7, 1042-1056, http://dx.doi.org/10.1016/j.ijproman.2012.11.004 Zhang, H. 2007, ‘A redefinition of the project risk process: Using vulnerability to open up the event- consequence link’, International Journal of Project Management, vol. 25 no. 7, 694-701, https://doi. org/10.1016/j.ijproman.2007.02.004 http://dx.doi.org/10.1016/j.buildenv.2008.06.025 http://dx.doi.org/10.1016/j.buildenv.2008.06.025 https://doi.org/10.1108/17538371211268951 https://doi.org/10.1108/17538371211268951 https://doi.org/10.1002/pmj.21369 https://doi.org/10.1016/j.ijproman.2015.08.001 https://doi.org/10.1016/j.ijproman.2015.08.001 https://doi.org/10.1108/17538371211192892 https://doi.org/10.1108/17538371211192892 http://dx.doi.org/10.1016/j.ijproman.2016.07.005 http://dx.doi.org/10.1016/j.ijproman.2015.12.006 http://dx.doi.org/10.1016/j.ijproman.2016.07.008 http://dx.doi.org/10.1016/j.ijproman.2012.11.004 https://doi.org/10.1016/j.ijproman.2007.02.004 https://doi.org/10.1016/j.ijproman.2007.02.004