(2 rânduri libere, 11p)


 
 

Overview about project planning 
 

Cătălin Drob, Ph.D, „Vasile Alecsandri” University of Bacau, Romania 
  

 
Abstract 
 
The purpose of this article is to present the main aspects regarding project planning. This study is 
generally based on the fourth edition of the Guide to the Project Management Body of Knowledge 
(PMBOK Guide) developed by the Project Management Institute (PMI) in 2008. According to this 
edition of PMBOK, project planning involves a group of processes required to establish the scope of 
the project, refine the objectives, and define the actions that must be undertaken to attain the objectives 
of the project. 
 
Keywords:   
 
Project, management, objectives, plan, schedule. 
  
JEL Codes: O21, O22 
 
 
Introduction  
 
In accordance with the Guide to the Project Management Body of Knowledge (PMBOK 
Guide) elaborated by the Institute of Project Management (PMI), a project is a temporary 
endeavor undertaken to create a unique product, service, or result1. 
Generally, a project can be characterized through five basic phases: 
 

 
 
 
 
 
 
 
 
 
 
 
 

Project 
initiation

Project close 

Project 
execution 

Project monitor 
and control

 
Project planning 

 
 
 
 

Figure. 1. The basic phases of project management 
 Source: Adapted from PMI (2008), Guide to the Project Management Body of Knowledge, Fourth Edition, p. 40 

                                                            
1
  PMI (2008), Guide to the Project Management Body of Knowledge, Fourth Edition, Project 

Management Institute, Inc., USA, p. 1 
 



Mainly, the initiation phase defines the problem that must to be resolved through the project, 
defines the objectives, requirements and overall project deliverables and identify the main 
risks of the project. 
The starting point in the planning phase are results of the initiation phase, materialized into a 
document named Project Charter. 
 
Project planning  
 
Planning is considered by many specialists the most important task of the project 
management. The main components of the planning phase are the following2: 
- objectives, that must be accomplished in a given period of time; 
- the program, that involves define the strategy and the main actions to be undertaken in 
order to achieve objectives; 
- the schedule, that is a working plan that shows when activities will be started and finished; 
- the budget, that shows expenditures that will be made for achieving the objectives; 
- the forecast, which prefigures the future status of the project; 
- the organization, which refers both to establish the component of the project team and the 
duties and responsibilities that will be assigned to project team members; 
- the policy, that provides a framework, a general guide for conducting project activities; 
- the procedure, that specifies the chronological sequences in which an activity or an action 
must be undertaken; 
- the standard, which is a level of performance, unanimous regarded as appropriate or 
acceptable. 
During the planning phase, starting from Project Charter it can proceed to elaborate another 
important document of the project called Project Scope Statement. This document presents, 
in detail, the description of the activities to be undertaken under the project, in order to 
obtain a product or service that meets the requirements requested by the client3. 
Also, the Scope Statement should include the information about: 
- project description and justification; 
- project objectives/deliverables (the products, services, or results that the project will 
produce);  
- product scope description (the characteristics, features and functions of the products, 
services, and/or results that the project will produce); 
- product acceptance criteria (the criteria used for accepting products, services, or other 
project results); 
- project constraints; 
- main project assumptions etc. 
After performing the Project Scope Statement the next phase of the project planning is to 
design the Work Breakdown Structure (WBS). The WBS is used for dividing the project into 
easily manageable components. The lowest level of the WBS is named work package. The 
work package (WP) represents a basic work sub-division of the project that is small enough 
so that the responsibility for its performing to be assigned to one person.   
The WBS can be structured into different forms, using the phases of the project life cycle (as 
shown in the following figure), using major deliverables or using subprojects as the first 
level of decomposition: 
 

 
 

                                                            
2 Kerzner, H. (2001) Project management: A systems approach to planning, scheduling and 
controlling, Seventh Edition, John Wiley & Sons, Inc.,USA, p. 552. 
3 Desmond, C.L. (2004), Project management for telecommunications managers, Kluwer Academic 
Publishers, USA., p. 36. 



 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

 
 
 
 
 
 
 
 
 

Figure. 2. Example of WBS elaborated using phases of the project life cycle  
as the first level of decomposition 

 Source: Adapted from PMI (2008), Guide to the Project Management Body of Knowledge, Fourth Edition, p. 120 
 

Usually, the Work Breakdown Structure is a deliverable-oriented, hierarchical decomposition 
of the work to be completed during the project. 
Starting of the WBS, the next steps in project planning involve define and sequence activities 
and estimate their resources and durations.  
Define activities involves the identification of the actions that must be undertaken to produce 
the project deliverables. For this is necessary to decompose the work packages of the project 
are into smaller components named activities. The result of the define activities process is the 
activities list. This list includes all schedule activities that are planned to be undertaken on 
the project. 
Sequence activities involve the identification of the logic relationships among activities. 
Sequencing can be performed by using different tools and techniques, such as: Precedence 
Diagramming method (PDM method), dependency determination, schedule network 
templates etc. 
Estimate activity resources involve estimating what type and quantity of resources (material, 
people, equipment etc.) are necessary to perform every activity of the project. This step is 
considerate critical because it determine the budget of the project. The most used and 
accurate method for  estimating activity resources is based on the Work Breakdown Structure 
and is known as the bottom-up estimating method. The main result of the estimating activity 
resources process is the list of requirements for each activity of the project.  
Estimate activity durations is also considerate critical step because the accuracy of the 
project schedule (that represents next step in the project planning) depends on the accuracy 
of these estimates. The most used tools to estimate the activities duration are: analogous 
estimating, parametric estimating and three point estimates. 
Analogous estimating is based on historical information about durations of a previous, 
similar activities undertaken in other similar projects. 

Phase 1

PROJECT 

WP 1.1.1.

D
el

iv
er

ab
le

 1
.1

. 

WP 1.1.2.

WP 1.1.3.

WP 1.2.1.

WP 1.2.2.

D
el

iv
er

ab
le

 2
.1

. 

D
el

iv
er

ab
le

 1
.2

. 

WP 2.1.1.

WP 2.1.2.

WP 2.1.3.

D
el

iv
er

ab
le

 3
.1

. 

WP 3.1.1. 

WP 3.1.2. 

WP 3.1.3. 

Phase 3 Phase 2

D
el

iv
er

ab
le

 3
.2

. 

WP 3.2.1. 

WP 3.2.2. 

WP 3.2.3. 



Parametric estimating considerate that activity duration can be estimated by multiplying the 
quantity of work by the productivity rate. 
Three point estimates tool is relative similar with PERT (Program evaluation and review 
technique). Both methods involve the estimation of three activity durations: most likely, 
optimistic and pessimistic. The method considers that the duration of an activity can be 
estimated as an average of the three estimated durations. 
The next step in project planning consists in the developing schedule of the project. Develop 
Schedule is the process that merges all of the work tasks to be performed, their relationships, 
their estimated durations, and their assigned resources to a calendar4. The project schedule 
can be presented in summary form or in graphical form (as milestone charts, bar charts or 
project schedule network diagrams). The schedule provides a basis for monitoring and 
controlling project activities and for tracking project progress. 
The next step in project planning refers on developing budget. The budget of the project is 
the amount of money available to the project team to achieve objectives under the 
requirements specified by the client. For the determination of the budget, the first step 
consists in the identification and estimation of the activities cost. After this step, for 
developing a document called the project budget is necessary to aggregate the individual 
costs originally estimated. 
In practice, for determining the budget can be applied some tools and technique, also used in 
estimating costs, such as reserve analysis. Other techniques used for determining budget are: 
cost aggregation, expert judgment, funding limit reconciliation etc. For example, cost 
aggregation is used to determine total costs for an entire project starting from estimated cost 
of the work packages at the lowest level of the WBS until the higher component levels of the 
WBS. 
The last step in project planning consists in the developing the supporting plans, such as: 
quality plan, human resource plan, communications plan, risk management plan, 
procurements plan. 
The most important result of project planning is a document called the project management 
plan. This plan describes how the project is executed, monitored, controlled and completed. 
The supporting plans can be considered as sub-plans of the project management plan. 
  
Conclusion  
 
Many authors are agreed that project planning is the key element for project success. There 
are some theories and standards regarding project management that have proposed different 
approach regarding project planning. For example, the Project Management Institute (PMI) 
has proposed a set of standards and practical guidance for project management, in a 
document known as the PMBOK (Project Management Body Of Knowledge). The fourth 
edition of this guide (standard), elaborated in 2008, consider that the project planning refers 
to the following processes: Develop Project Management Plan; Collect Requirements; 
Define Scope; Create Work Breakdown Structure; Define Activities; Sequence Activities; 
Estimate Activity Resources; Estimate Activity Durations; Develop Schedule; Estimate 
Costs; Determine Budget; Plan Quality; Develop Human Resource Plan; Plan 
Communications; Plan Risk Management; Identify Risks; Perform Qualitative Risk 
Analysis; Perform Quantitative Risk Analysis; Plan Risk Responses and Plan Procurements.  
In this article I tried to present the project planning steps based on the approach proposed by 
the PMI. In fact, the project planning is relative easy to define in theory, but in practice is 
more difficult to realize. 
  
 
                                                            
4 Horine, G.M. (2005), Absolute Beginner's Guide to Project Management, Que Publishing, USA, 
2005, p. 54. 



References 
 
1. Desmond, C.L. (2004), Project management for telecommunications managers, Kluwer Academic 

Publishers, U.S.A. 
2. Drob, C. (2010), Management de proiect, Editura Alma Mater, Bacau 
3. Horine, G.M. (2005), Absolute Beginner's Guide to Project Management, Que Publishing, U.S.A. 
4. Lewis, J.P. (2007), Fundamentals of project management, Third Edition, AMACOM Books, 

U.S.A. 
5. PMI (2008), Guide to the Project Management Body of Knowledge, Fourth Edition, Project 

Management Institute, Inc., U.S.A.  
6. Verzuh, E. (2003), The portable MBA in project management, John Wiley & Sons, Inc., U.S.A.